Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 12-0P7004

Submit new inquiry for this project


Inquiry #1: Is a DVBE material supplier dollar amount allocatation towards dvbe goal 60% or 100%? For example: DVBE material cost quoted $100.00. Does $100.00 go toward the goal or $60.00?
Inquiry submitted 09/17/2020

Response #1:Pending
Response posted 09/18/2020




Inquiry #2: Inquiry #1: Is a DVBE material supplier dollar amount allocatation towards dvbe goal 60% or 100%? For example: DVBE material cost quoted $100.00. Does $100.00 go toward the goal or $60.00?

Rephrased: Does a DVBE material supplier total claimed participation allocation count as 100%or 60%. Example: DVBE material cost quoted $100.00. Is the total claimed participation $100.00 or$ 60.00?

Inquiry submitted 09/18/2020

Response #1:Pending
Response posted 09/18/2020




Inquiry #3: Can we get CAD files for this project?
Inquiry submitted 09/22/2020

Response #1:Pending
Response posted 09/22/2020


Response #2:Please bid as you see it
Response posted 09/22/2020




Inquiry #4: The specifications do not give anticipated stormwater flows in the channel. Please provide a basis for bidding in cfs (cubic feet per second) for channel flows and for the various lines that have outlets into the existing channel right-of-way.
Inquiry submitted 09/23/2020

Response #1:Pending
Response posted 09/23/2020


Response #2:Please bid as you see it
Response posted 09/23/2020




Inquiry #5: 1: Does the 1602 permit included in the informational handout serve to satisfy the requirements of the Fish Passage Plan cited in specification 13-12.01C(1)(10)?

2: Will the District provide the qualified biologist for sensitive species surveys and species avoidance measures?

3: Does the TCSD require review and approval from Orange County Public Works?

4: Will the project require an encroachment permit from OCPW?

Inquiry submitted 10/08/2020

Response #1:Pending
Response posted 10/09/2020


Response #2:Please bid as you see it
Response posted 10/12/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.