Inquiry #1: Per the Traffic Handling Plans, MGS Locations 3, 4 & 9 are protected by temporary k-rail. Please confirm that the Contractor will not be compensated to place k-rail to protect the traveling public and Contractor employees during removal and replacement of the MGS at Locations 1, 5, 6 & 7.
Inquiry submitted 01/26/2022

Response #1:Pending
Response posted 01/26/2022


Response #2:Correct, bid per plans
Response posted 01/26/2022




Inquiry #2: Is it Caltrans intent to modify the 334LS to only include what is specified in section 87-9.02 B.


Inquiry submitted 02/04/2022

Response #1:Pending
Response posted 02/04/2022




Inquiry #3: The Base Bond Breaker quantity seems to be higher than what is needed for the square yardage of the Precast Panels. Is there another scope of work the Base Bond Breaker is needed for, or is the quantity an overrun? Please advise.
Inquiry submitted 02/10/2022

Response #1:Pending
Response posted 02/10/2022


Response #2:Base bond breaker is provided for precast concrete panels and individual slab replacement. Bid per plans
Response posted 02/14/2022




Inquiry #4: Regarding Bid Item #34, on sheet C-7, Note #3, what is the maximum length that a standard panel can be? Can it be 14'-6" or 15'-0" long?
Inquiry submitted 02/15/2022

Response #1:Pending
Response posted 02/15/2022


Response #2:Maximum length for a standard panel is 14'-0
Response posted 02/25/2022




Inquiry #5: Regarding Bid Item #34, on Sheet X-1, it shows existing PCC at .93' on top of .57' LCB. For the new section it shows .92' Precast Concrete Pavement plus .02' Grind New PCP and remove concrete pavement .90'. This does not allow room for any underslab grout. Note, it is nearly impossible to remove fractions of an inch from existing LCB. We recommend that the Precast be no more than .90' + .02' for sacrificial grinding. Also does the Bid Quantity include the .02' Sacrificial Grinding Layer?
Inquiry submitted 02/15/2022

Response #1:Pending
Response posted 02/15/2022


Response #2:The fabricated PCP panel thickness will be 0.92' (which includes 0.02' for sacrificial grinding). The final in-place PCP panel thickness will be 0.90' (after the sacrificial 0.02' grinding has been completed). The Bid Quantity for Bid Item #34 does include the 0.02' sacrificial grinding layer."
Response posted 02/28/2022




Inquiry #6: Regarding Bid Item #34, on Sheet L-3, there is a double diagonal break line going across the freeway. Is this a break in the pavement?
Inquiry submitted 02/15/2022

Response #1:Pending
Response posted 02/15/2022


Response #2:There is no break in the pavement, the lines represent a pedestrian overcrossing
Response posted 02/17/2022




Inquiry #7: Regarding Bid Item #34, on Sheet X-1, it shows the two lanes to be replaced at 12' wide. On Sheets L-1 and L-5 there appears to be a step in the width on the shoulder of the Southbound Lanes. Do the panel widths get reduced from the 12'? Do the panels start wider than 12'? Once panels get wider than 12' then the length has to be reduced to 11'-3" (plus the dowels) or a trail car is required for shipping. Trail cars increase the cost of freight by approx. 50%.
Inquiry submitted 02/15/2022

Response #1:Pending
Response posted 02/15/2022


Response #2:Addendum will be issued
Response posted 02/25/2022




Inquiry #8: Lane Closure Charts G1 and G2 show that 4 Lanes must be open starting at 9pm. However, the job limits only have 4 lanes throughout. Please advise in both directions. Please advise.
Inquiry submitted 02/28/2022

Response #1:Pending
Response posted 02/28/2022




Inquiry #9: New Structural Section 1 calls for the new precast panels to be .92' with the removal of .90' of concrete pavement. SB Lane 3 & NB Lane 4 shows the existing structural section to be 0.93' off concrete pavement. The contractor must remove the full .93' of existing concrete. What is the Contractor to place to make up the extra .03' and how is it to be paid?
Inquiry submitted 03/02/2022

Response #1:Pending
Response posted 03/02/2022


Response #2:Clarification will be provided in an upcoming addendum
Response posted 03/08/2022




Inquiry #10: Bid item 24 calls for 1,310 CY of replace base. On the summary of quantity's it show this item at the slab removals, but the details, notes, and or specials do not indicate or show removal and or replacement of base. Please explain the intent of this bid item location, material, thickness...
Inquiry submitted 03/04/2022

Response #1:Pending
Response posted 03/04/2022


Response #2:Please bid per plans
Response posted 03/10/2022




Inquiry #11: In regards to the still unreleased upcoming Addendum in the Caltrans response to Bidder Inquiry #7, and with other unanswered Bidder Inquiries, will Caltrans look to extend the bid date for this project?
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Addendum #2 will extend Bid Opening date
Response posted 03/08/2022




Inquiry #12: Regarding Bid Item 34, the quantities on Sheet Q-2 do not match the quantities taken from Sheets L-1 through L-8 unless the panel width is more than 12' lanes. Please clarify?
Inquiry submitted 03/09/2022

Response #1:Pending
Response posted 03/09/2022


Response #2:Please see upcoming Addendum
Response posted 03/09/2022




Inquiry #13: With the recent addendum, will Caltrans consider extending the bid date for one week in order for contractors to make the necessary changes in regards to the addendum information and coordinate with precast panel suppliers?
Inquiry submitted 03/14/2022

Response #1:Pending
Response posted 03/14/2022


Response #2:No further extension of the Bid Open date is planned at this time
Response posted 03/14/2022




Inquiry #14: Regarding item 71, the bid schedule presents this as a solid 6" line with contrast, no breaks. But the plans call out for Detail 12A, which would be 12' line, 36' gap. Please review item 71.
Inquiry submitted 03/15/2022

Response #1:Pending
Response posted 03/15/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.