Submit new inquiry for this projectInquiry #1: Can Caltrans take a second look at the amount of working days to complete the project?
Inquiry submitted 09/07/2023
Response #1:(BI#1)-Your inquiry has been received and is being reviewed.
Response posted 09/07/2023
Response #2:(BI#1)-An addendum has been issued to address this bidder inquiry.
Response posted 09/25/2023
Inquiry #2: Will you be providing a tack quantity and a pay item for it?
Inquiry submitted 09/15/2023
Response #1:(BI#2)-Your inquiry has been received and is being reviewed.
Response posted 09/15/2023
Response #2:(BI#2)-An addendum has been issued to address this bidder inquiry.
Response posted 09/25/2023
Inquiry #3: Stage 3 and 4 shows a single 12' paved lane with reversing traffic control on Hwy 36 which will require 24 hour traffic control. Traffic chart K1 (SR 36/EB&WB) does not allow for reversing traffic control over the weekend. The work required to complete stage 3 and 4 will require more than one week to complete. Please Advise.
Inquiry submitted 09/18/2023
Response #1:(BI#3)-Your inquiry has been received and is being reviewed.
Response posted 09/18/2023
Response #2:(BI#3)-Please bid per current contract documents.
Response posted 10/04/2023
Inquiry #4: Stage 3 and 4 shows a single 12' paved lane with reversing traffic control on Hwy 36 which will require 24 hour traffic control. Traffic chart K1 (SR 36/EB&WB) does not allow for reversing traffic control over the weekend. The work required to complete stage 3 and 4 will require more than one week to complete. Please Advise.
Inquiry submitted 09/18/2023
Response #1:(BI#4)-Your inquiry has been received and is being reviewed.
Response posted 09/18/2023
Inquiry #5: 80 - 90 days does not seem like enough days to complete this project. Would the State consider adding additional days.
Inquiry submitted 09/18/2023
Response #1:(BI#5)-Your inquiry has been received and is being reviewed.
Response posted 09/18/2023
Response #2:(BI#5)-An addendum has been issued to address this bidder inquiry.
Response posted 09/25/2023
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.