Viewing inquiries for 02-4H0504
Submit new inquiry for this projectInquiry #1: There does not appear to be a specification for the cured-in-place pipeliner (CIPP) included in the special provisions for this project, which is normally specified under section 71-3.08. Please provide the special provision section 71-3.08 that will apply to the CIPP pipeliner required under bid items 0116 to 0118 for this project.
Inquiry submitted 08/28/2023
Response #1:(BI#1)-Your inquiry has been received and is being reviewed.
Response posted 08/28/2023
Response #2:(BI#1)-This will be addressed by an addendum.
Response posted 09/15/2023
Response #3:(BI#1)-This has been addressed by Addendum #1.
Response posted 09/28/2023
Inquiry #2: Bid Item #81 is for RHMA Open Graded Bonded Wearing Course. But there is no bid item for Bonded Wearing Course Asphaltic Emulsion. Can the State please ass a bid items and quantity to pay for the Bonded Wearing Course Emulsion needed on this project.
Inquiry submitted 08/29/2023
Response #1:(BI#2) Your inquiry has been received and is being reviewed.
Response posted 08/29/2023
Response #2:(BI#2)-This will be addressed by an addendum.
Response posted 09/25/2023
Response #3:(BI#2)-This has been addressed by Addendum #1.
Response posted 09/28/2023
Inquiry #3: Per the Erosion Control Legend (ECL-1), under the Fiber Rolls table..."In EC Type 1 Areas, Fiber Rools must be installed after BFM" by "Type 1 Installation". Please reconsider sequencing of the Fiber Rolls installation before Compost and Bonded Fiber Matrix (SQFT) to avoid digging furrows per "Type 1 Installation" of Fiber Rolls through the EC Type 1 areas already seeded with Bonded Fiber Matrix (SQFT). This will avoid adversely impacting the EC Type 1 areas after the Bonded Fiber Matrix (SQFT) is in place.
Inquiry submitted 09/12/2023
Response #1:(BI#3)-Your inquiry has been received and is being reviewed.
Response posted 09/12/2023
Response #2:(BI#3)-Bid per current contract documents. Attention is directed to Standard Plan H51for the compost sock detail.
Response posted 09/15/2023
Inquiry #4: Section 71-3.08B(1) included in addendum 1 requires minimum CIPP thicknesses of 0.7 inch at location 24.96, and .3 inch at locations 25.18 and 26.85. This equates to minimum thicknesses of 17.78mm for a 18" culvert, and 7.62mm for 42" and 48" culverts. CIPP thickness requirements typically increase with pipe diameter and depth. Are these minimum thicknesses accurate?
Inquiry submitted 09/29/2023
Response #1:(BI#4)-Your inquiry has been received and is being reviewed.
Response posted 09/29/2023
Response #2:(BI#4)-This information is correct. It is based on calculated flow velocities in the culverts.
Response posted 09/29/2023
Inquiry #5: The CIPP lining specification section 71-3.08B(1) published in Addendum No. 1 says that for the 18" culvert at location 24.96, the minimum wall thickness for the CIPP is 0.7 inches or the minimum thickness shown in the authorized installation plan, whichever is greater. This will require the CIPP installed in the 18" diameter pipe to be, at a minimum, at least 17.78mm thick, which is too thick for this diameter of CIPP and will likely be impossible to install. This minimum thickness requirement for location 24.96 needs to be reduced to something more feasible for installation in 18" diameter pipe, like 0.3 inches.
Inquiry submitted 10/02/2023
Response #1:(BI#5)-Your inquiry has been received and is being reviewed.
Response posted 10/03/2023
Response #2:(BI#5)-Bid per current contract plans.
Response posted 10/04/2023
Response #3:(BI#5)-This has been addressed by Addendum #3.
Response posted 10/16/2023
Inquiry #6: The detail for Replace AC Surfacing detail on X-3 calls for 0.1' CPACP then 0.33' .
This is a conflict with CPACP of 0.2' - 0.3' on the entire project.
Please clarify the States intent.
Inquiry submitted 10/03/2023
Response #1:(BI#6)-Your inquiry has been received and is being reviewed.
Response posted 10/03/2023
Response #2:(BI#6)-Bid per current contract documents.
Response posted 10/04/2023
Response #3:(BI#6)-This has been addressed by Addendum #3.
Response posted 10/16/2023
Inquiry #7: Roadway excavation does not appear to encompass the excavation needed to place shoulder backing the way it is shown on cross sections. Please advise how this quantity will be compensated.
Inquiry submitted 10/03/2023
Response #1:(BI#7)-Your inquiry has been received and is being reviewed.
Response posted 10/04/2023
Inquiry #8: Sheet C-20 shows the retaining wall stationing equals to 510.57'.
Sheet C-21 gives a L=505' but when you add up the individual sections it equals 763.5'
Please confirm which is correct as this is a final pay item.
Inquiry submitted 10/03/2023
Response #1:(BI#8)-Your inquiry has been received and is being reviewed.
Response posted 10/04/2023
Response #2:(BI#8)-Bid per current contract documents.
Response posted 10/16/2023
Inquiry #9: There is a clear conflict in the current contract documents between the Typical Cross Sections and the Typical Cross Sections for Replace AC Surfacing.
Based on the current contract documents there is no where on the project that calls for only a 0.1' CPACP.
Please bid per current contract documents is not an acceptable answer when the current contract documents do not provide enough information to provide an accurate bid.
Inquiry submitted 10/04/2023
Response #1:(BI#9)-Your inquiry has been received and is being reviewed.
Response posted 10/04/2023
Response #2:(BI#9)-This has been addressed by Addendum #3.
Response posted 10/16/2023
Inquiry #10: On sheets X - 1 thru X - 3 the cross sections for routes 299 & 273 call for a cpacp at depth of 0.2' & 0.3'. On Sheet X - 3 the "replace ac surfacing" detail shows the cpacp at a depth of 0.1'. This is conflicting with the cross sections for routs 299 & 273, is it Caltrans intention for the contractor to cpacp at a depth of 0.1' for routes 299 & 273 then perform the replace ac surfacing at a depth of 0.33' and then perform cpacp at a depth of 0.2' & 0.3' therefore leaving 0.13' to 0.03' of the new asphalt installed during the replace ac surfacing portion of work? Also with the cpacp being performed twice, 1st at a depth of 0.1' and then 2nd at a depth of 0.2'-0.3', the current quantity for cpacp will overrun by 200%. The current detail for "Replace AC Surfacing" conflicts with the cross sections for route 299 & 273.
Inquiry submitted 10/04/2023
Response #1:(BI#10)-Your inquiry has been received and is being reviewed.
Response posted 10/04/2023
Response #2:(BI#10)-This has been addressed by Addendum #3.
Response posted 10/16/2023
Inquiry #11: The scope of work cannot be completed within the time frames allowed in the contract (minimum or maximum).
Historically bidders have been required to bid the minimum days to ensure their chances at securing the low bid.
Will Caltrans consider adding days to this contract?
Inquiry submitted 10/04/2023
Response #1:(BI#11)-Your inquiry has been received and is being reviewed.
Response posted 10/04/2023
Response #2:(BI#11)-Bid per current contract documents.
Response posted 10/16/2023
Inquiry #12: Reference is made to the roadside sign quantity sheets. There are four signs requiring laminated wood box posts, but the quantities only provide for installing two. The other two are under roadside sign two post. The high cost of the laminated posts will skew the bid price of the two post roadside signs. please consider a revision to increase the quantity for bid item 158 to 4 each.
Inquiry submitted 10/04/2023
Response #1:(BI#12)-Your inquiry has been received and is being reviewed.
Response posted 10/04/2023
Inquiry #13: Sheet Q-1 Addendum 1 increases the Roadway Excavation quantity to 4,597cy however the bid item list included in addendum 1 does not update the Roadway Excavation quantity.
Which quantity should bidders use?
Inquiry submitted 10/04/2023
Response #1:(BI#13)-Your inquiry has been received and is being reviewed.
Response posted 10/04/2023
Response #2:(BI#13)-This has been addressed by Addendum #3.
Response posted 10/16/2023
Inquiry #14: Reference is made to the roadside sign quantity sheets. There are four signs requiring laminated wood box posts, but the quantities only provide for installing two. The other two are under roadside sign two post. The high cost of the laminated posts will skew the bid price of the two post roadside signs. please consider a revision to increase the quantity for bid item 158 to 4 each.
Inquiry submitted 10/05/2023
Response #1:(BI#14)-Your inquiry has been received and is being reviewed.
Response posted 10/05/2023
Response #2:(BI#14)-Attention is directed to Section 82-3.02D of the Standard Specifications. Bid per current contract documents.
Response posted 10/05/2023
Inquiry #15: The State issued Addendum 3 on 10/13/2023. Addendum 3 revised the quantity table on sheet Q-1 for Roadway Excavation and Replace AC Surfacing in the Summary of Roadway Quantities table.
The Summary of Roadway Quantities table directs the bidder to "From Pavement Quantities" or "From Conform Quantities" for the added or change quantities for Roadway Excavation and Replace AC Surfacing.
Addendum 3 did not include revised a Pavement Quantity Table or a revised Conform Quantity Table. These will be required for estimating purposes. Will the State please revised the appropriate tables that correspond with the revised quantities shown in Addendum 3?
Inquiry submitted 10/13/2023
Response #1:(BI#15)-Your inquiry has been received and is being reviewed.
Response posted 10/13/2023
Inquiry #16: Addendum 3 revised the roadway excavation quantity on the bid item list to 6420 CY.
The new Summary of Roadway Quantities that was issued with addendum 3 states the quantity is 6684.6 CY's.
Which quantity should the bidder use?
Inquiry submitted 10/13/2023
Response #1:(BI#16)-Your inquiry has been received and is being reviewed.
Response posted 10/13/2023
Response #2:(BI#16)-Bid per current contract documents. Attention is directed to section 9-1.06 of the Standard Specifications.
Response posted 10/16/2023
Inquiry #17: Please provide a revised Pavement Quantities sheet (Sheet Q-2) that corresponds with the updates in addendum 3.
This information is necessary for bidding purposes.
Inquiry submitted 10/17/2023
Response #1:(BI#17)-Your inquiry has been received and is being reviewed.
Response posted 10/17/2023
Response #2:(BI#17)-Bid per current contract documents. Attention is directed to section 9-1.06 of the Standard Specifications.
Response posted 10/17/2023
Inquiry #18: Please provide an updated Summary of Quantities Sheet Q-2 that correspond to the changes made by Addendum 3
Inquiry submitted 10/17/2023
Response #1:(BI#18)-Your inquiry has been received and is being reviewed.
Response posted 10/17/2023
Response #2:(BI#18)-Bid per current contract documents. Attention is directed to section 9-1.06 of the Standard Specifications.
Response posted 10/17/2023
Inquiry #19: Section 9-1.06 does not clarify the inconsistency in the current contract documents.
The current contract documents have discrepancies and do not provide clear and concise information to provide an accurate estimate.
Which of the current contract documents are accurate Sheet Q-1, Sheet Q-2 or the bid item sheet issued on 10/13?
If the Bid Item Sheet and Sheet Q-1, issued with addendum 3 on 10/13 are correct please provide an updated Summary of Quantities Sheet Q-2 that shows accurate alignment and stationing for Replace Asphalt Concrete Surfacing.
Inquiry submitted 10/17/2023
Response #1:(BI#19)-Your inquiry has been received and is being reviewed.
Response posted 10/18/2023
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.