Viewing inquiries for 04-3G3644
Submit new inquiry for this projectInquiry #1: FYI. Caltrans to All Bidders - How do I register for Mandatory Pre-Bid Meeting?
Inquiry submitted 08/07/2023
Response #1:Please do not use the Bidder Inquiry platform for Mandatory Pre-Bid Meeting registration; it is for inquiries related to bidding on the project contract. Register in advance of the Mandatory Pre-Bid Meeting, and no later than 1 hour before the meeting time, by sending an email with bidder information to D4.Construction.Duty.Senior@dot.ca.gov Please include the project number & "Mandatory Pre-Bid Meeting", within the subject of the email.
Response posted 08/07/2023
Response #2:Companies that attended the Mandatory Pre-Bid Meeting:
• AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC
• ANVIL BUILDERS INC
• ANVIL POWER INC
• GLOBAL PPE DISTRIBUTORS LLC
• HSQ
• MASS ELECTRIC (KIEWIT)
• PERRY ELECTRIC INCORPORATED
• RAGNAR BENSON CONSTRUCTION
• SHIMMICK CONSTRUCTION COMPANY INC
• ST. FRANCIS ELECTRIC LLC
• STUDEBAKER ELECTRIC INC
• THOMPSON BUILDERS CORPORATION
• WESTERN STATE CONTROLS (IWESTCO)
Response posted 10/27/2023
Response #3:For the contact list, click on the link below:
http://website.dot.ca.gov/dist4/construction/contracts/04-3G3644/04-3G3644MPBMCompanies.pdf
Response posted 10/27/2023
Inquiry #2: FYI. Caltrans to All Bidders - The Mandatory Pre-Bid Meeting has been postponed to October 11, 2023, at 10:00 am. Please see Addendum 1.
Inquiry submitted 08/08/2023
Response #1:.
Response posted 08/08/2023
Response #2:Rescheduled. See addendum No. 2,
"A mandatory prebid meeting is scheduled on October 25, 2023, at 1:00 pm at WebEx Meeting."
Response posted 10/11/2023
Inquiry #3: FYI. Caltrans to All Bidders - The bid open has been postponed. Bids for this work will be opened on Thursday, October 26, 2023, instead of the original date of Thursday,
September 7, 2023. See Addendum 1.
Inquiry submitted 08/08/2023
Response #1:.
Response posted 08/08/2023
Response #2:The bid open has been postponed. See Addendum No. 2,
"Bids for this work will be opened on Wednesday, November 15, 2023, instead of the original date of Thursday,
October 26, 2023."
Response posted 10/11/2023
Response #3:Addendum 3 issued on 11/03/2023, changed the Bid Open date to Dec. 14, 2023.
Response posted 11/07/2023
Inquiry #4: Would it be possible for Caltrans to arrange a pre-bid site visit for bidding contractors? Particularly, we would like an opportunity to take a closer look at the (4) existing electrical substations.
Inquiry submitted 09/08/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/08/2023
Response #2:There is no site visit for this project.
Response posted 11/02/2023
Inquiry #5: Section A-A and Section B-B on Plan Sheet E-15 & E-30 do not depict the actual structure in these areas. These cross sections are currently depicting a steel curb covering a trough which houses existing conduit and wiring. The actual structure at Sections A-A and B-B appear to have no steel curb & trough. Instead, these areas have transitioned from steel curb & trough to concrete barrier. It is unclear how the existing & new cables are installed in these areas. These details are further referenced on Plan Sheets E-5, E-6, E-20, and E-21.
Sections A-A shown on the Utility plans (U-2 & U-3) are also depicting a structure that is not representative of the actual structure in these areas.
Would Caltrans be able to revise these plan sheets to show the actual cable setup in these areas? We are trying to determine if any of the existing/new cables in these areas are surface mounted to the exterior of the concrete barrier, underside soffit, or if portions are cast into the concrete barrier. These details are not apparent in the as-built drawings we have reviewed. Please advise?
Inquiry submitted 09/08/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/08/2023
Response #2:Please see the revised plan sheets in Addendum 4.
Response posted 11/30/2023
Inquiry #6: Please confirm whether (1) Temporary Generator needed at one substation at a time or (4) Temporary Generators used simultaneously.
Inquiry submitted 09/26/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/26/2023
Response #2:It's for one Temporary Generator needed at one substation at a time. Simultaneous operation of the Temporary Generators might be needed during the transition to the new switchgear. As long as there is no interruption in the bridge system's operations, the Contractor can elect to operate one or multiple Temporary Generators at one time.
Response posted 11/02/2023
Inquiry #7: Generator Run Hours imply continuous use for 24/7. Please confirm.
Inquiry submitted 09/26/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/26/2023
Response #2:As long as there is no interruption in the bridge system's operations, the generators can run for a limited time or 24/7, depending on the need.
Response posted 11/02/2023
Inquiry #8: Drawing UD-2, E-17, E-18, E-32, and E-33 calls for 150 kV Generators for Substation 2 and 3. Spec Section 87-20.02B calls for 150 KW for the generator. Please clarify.
Inquiry submitted 09/26/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/26/2023
Response #2:Yes, it's KW.
Response posted 11/02/2023
Inquiry #9: The anticipated lead time on the (4) new unit substations approximately 24 months. Will
the project schedule be adjusted to accommodate this?
Inquiry submitted 09/26/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/26/2023
Response #2:There are 400 working days per Addendum 4.
Response posted 11/30/2023
Inquiry #10: Regarding the steel plate covers, is there an expectation that the contractor needs to remove every cover to install the new cables?
Inquiry submitted 09/26/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/26/2023
Response #2:See the National Electrical Code (NEC) and the Standard Specifications for the Installation of the Cables in the Cable Tray. The contractor can use any method to install the new cables.
Please note the conduit length needs to be secured every 4.5' per NEC section - See NEC Article 320.30 regarding armored cable - Sections A through D.
Response posted 11/09/2023
Inquiry #11: Regarding the steel plate covers, is there an expectation that the removed covers need to be reinstalled at the end of every work shift?
Inquiry submitted 09/26/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/26/2023
Response #2:The steel curb and exposed cable tray must be covered at the end of each work shift. A fastened temporary rigid cover authorized by the Engineer can be used in case if the steel plate can’t be reinstalled in the same shift.
Response posted 11/09/2023
Inquiry #12: What are the distance intervals that the cables need to be secured to the trough structure in the horizontal raceways?
Inquiry submitted 09/26/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/26/2023
Response #2:See the National Electrical Code (NEC) and the Standard Specifications for the Installation of the Cables in the horizontal raceways. See NEC Article 320.30 - Sections A through D.
Response posted 11/30/2023
Inquiry #13: What are the distance intervals that the cables need to be secured to the structure in the vertical legs of the towers?
Inquiry submitted 09/26/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/26/2023
Response #2:See the National Electrical Code (NEC) and the Standard Specifications for the Installation of the Cables in the horizontal raceways. See NEC Article 320.30 - Sections A through D.
Response posted 11/09/2023
Inquiry #14: Where can the contractor set the temporary generators that will provide power to the (2) substations located on the piers?
Inquiry submitted 09/26/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/26/2023
Response #2:It's up to the Contractor per the Plans, the Standard Plans, the Standard Specifications, per the Special Provisions and per direction of the Engineer.
Response posted 11/02/2023
Inquiry #15: Does the existing curb duct need to be disassembled to access cables within or is there an access point along the bridge?
Inquiry submitted 09/29/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/29/2023
Response #2:The existing curb duct will need to be disassembled to access the cables within.
Response posted 11/02/2023
Inquiry #16: Are the pier legs defined as confined spaces? Does Caltrans have specific entry procedures for pier legs on Piers 34 and 48.
Inquiry submitted 09/29/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/29/2023
Response #2:The inquiry has been received and submitted for consideration.
Response posted 09/29/2023
Inquiry #17: Please provide As-Built drawings for Pier 34 and 48.
Inquiry submitted 09/29/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/29/2023
Response #2:Please complete and submit a Confidentiality Agreement (link below) to the Duty Senior (D4.Construction.Duty.Senior@dot.ca.gov). Instructions will be sent on how to access the asbuilts.
LINK - http://website.dot.ca.gov/dist4/construction/contracts/04-3G3644/ConfidentialityAgreement_3G3644.pdf
Response posted 11/02/2023
Inquiry #18: Has Caltrans performed lead testing on this bridge? Is Contractor expected to touch up paint after curb disassembly and reinstallation?
Inquiry submitted 09/29/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/29/2023
Response #2:The grey paint on the steel members of the bridge has been tested to contain hazardous waste levels of lead. See the Limited Asbestos and Lead-Containing Paint Survey Report for project 3G474 in May 2018.
The Contractor is not expected to touch up paint.
Response posted 11/02/2023
Inquiry #19: Drawing E-32 Pier 34 Plan view shows solid items for generators, panels, transformers, circuit breakers, conduit, navigational lighting, and automatic transfer switch. Please confirm these items are by others or already installed.
Inquiry submitted 09/29/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/29/2023
Response #2:The electrical notes 12, 13, 14 and 18 are the work items to be performed. The generators, panels, transformers, circuit breakers, conduit, navigational lighting, and automatic transfer switch are part of the temporary sytem during the transition to the new system (final configuration) at Substation 2. The temporary system will be removed after the new system is installed per Specs Section 87-20.02B. The temporary generator is 150 kW, not 150 kVA.
Response posted 11/09/2023
Inquiry #20: Drawing E-19, Pier 34 Elevation shows Minor Channel Light as solid. Please confirm whether this item is to be furnished by Contractor.
Inquiry submitted 09/29/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/29/2023
Response #2:Please do not include in your bid work to furnish or install this Minor Channel Light.
Response posted 11/30/2023
Inquiry #21: Please provide sizes of existing conduits, conductors, and cables relating to cable layout removal (i.e. armored communication cable, 5kV cable in existing conduit, etc).
Inquiry submitted 09/29/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 09/29/2023
Response #2:The existing 5kV Cables are 3#4/0 Medium Voltage Cables in a 3" Conduit (See Plans) and 1-3#4/0 Medium Voltage Armored Cable; and the 1-50 pair Cable are an existing 1-50 pair #19 Conductor Armored Cable and 1-50 pair #19 Conductor Cable.
Response posted 11/02/2023
Inquiry #22: Liquidated damages are not listed in the project's special provisions, please confirm there are no liquidated damages for this project.
Inquiry submitted 10/04/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/04/2023
Response #2:Please refer to the Standard Specifications for Liquidated Damages.
Response posted 11/02/2023
Inquiry #23: The bid documents indicate a project duration of 270 working days. Is this based on the Caltrans 5-day work week or the Caltrans 7-day work week?
Inquiry submitted 10/05/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/05/2023
Response #2:Please refer to Section 1-1.07B Glossary of the Standard Specifications under “day”, item #2 working day definition.
Response posted 11/02/2023
Inquiry #24: There are multiple items listed on the Electrical Legend on Plan Sheet E-4 that are not referenced anywhere else in the Plan Sheets. Please confirm that the items listed in the Electrical Legend that are not shown on the Plan Sheets are not part of the scope for this project. If this is correct, please revise the Electrical Legend to include only the items that are part of this project.
Inquiry submitted 10/05/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/05/2023
Response #2:Please do not include in your bid the items listed in the electrical legend on plan sheet E-4 that are not referenced elsewhere in the plan sheets.
Response posted 11/30/2023
Inquiry #25: Plan Sheets U-12 and U-13 don't show the Air and Water lines in the elevation view, please confirm this is an error.
Inquiry submitted 10/06/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/06/2023
Response #2:Yes, there are air and water lines.
Response posted 11/30/2023
Inquiry #26: Is Type 2C conduit (PVC coated rigid) required to be installed in the Substation rooms/vaults?
Inquiry submitted 10/09/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/09/2023
Response #2:See General Notes 22 on Sheet E-1.
Response posted 11/02/2023
Inquiry #27: Sheet E-4, Note 26 calls out 3#700KCMIL conductors and Sheet EQ-5 indicates quantity length for #700 KCMIL conductor is 350 LF. Is this quantity for only one conductor or the (3) conductors total from Call-out 26?
Inquiry submitted 10/09/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/10/2023
Response #2:This is total amount of conductors used for the item.
Response posted 11/02/2023
Inquiry #28: Call-out #29 on Sheet E-75 indicates 4#350 KCMIL CONDUCTORS. Length for this conductor is not shown anywhere and there is no scale for the plan drawings. Please provide further information on these lengths.
Inquiry submitted 10/09/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/10/2023
Response #2:The EQ Sheets may provide some information on the amount of conductors.
Response posted 11/02/2023
Inquiry #29: Sheet EQ-1 Table "Cable Layout Installation" indicates Sheet E-32 and E-33 has 2500 LF of the four armored cables. Does this linear footage account for the substation pier level only or the length of the tower legs as well?
Inquiry submitted 10/09/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/10/2023
Response #2:Yes.
Response posted 11/02/2023
Inquiry #30: FYI. Caltrans to All Bidders - The Mandatory Pre-Bid Meeting has been postponed, details to be provided in upcoming addendum.
Inquiry submitted 10/10/2023
Response #1:
.
Response posted 10/10/2023
Response #2:See addendum No. 2, "A mandatory prebid meeting is scheduled on October 25, 2023, at 1:00 pm at WebEx Meeting."
Response posted 10/11/2023
Inquiry #31: Does Caltrans have a SCADA System Integrator that we can contact to perform the SCADA scope of work on this project?
Inquiry submitted 10/12/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/12/2023
Response #2:No.
Response posted 11/02/2023
Inquiry #32: Is there any possibility of receiving the existing PLC & SCADA project backups for analysis?
Inquiry submitted 10/24/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2023
Response #2:Please complete and submit a Confidentiality Agreement (link below) to the Duty Senior (D4.Construction.Duty.Senior@dot.ca.gov) with a copy of your Driver's License/ID. Instructions will be sent on how to access the SCADA information from asbuilts.
LINK - http://website.dot.ca.gov/dist4/construction/contracts/04-3G3644/ConfidentialityAgreement_3G3644.pdf
Response posted 12/01/2023
Inquiry #33: We will need detailed specifications on the currently installed SCADA terminal.
Inquiry submitted 10/24/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2023
Response #2:The plan shown for the SCADA System was based on the existing as-builts.
Response posted 11/02/2023
Inquiry #34: We will need the exact software versions being used on the SCADA terminal.
Inquiry submitted 10/24/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2023
Response #2:The SCADA HMI Software that was used was GE IFIX and the Controllers that were is GE RX3i; The work finished in 2011 and started in about 2007.
Response posted 11/02/2023
Inquiry #35: We will need more details on the PLC code modifications that are required, and the PLC code additions required.
Inquiry submitted 10/24/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2023
Response #2:Please refer to the Special Provisions.
Response posted 11/02/2023
Inquiry #36: In conconcurrence with Inquiry #9 - Switchgear Mfgr has confirmed 24-months after issuance of PO for equipment delivery.
In addition, Okonite is quoting 12+ months for the 15kV cable.
Recommend a more realistic project duration.
Inquiry submitted 10/25/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/25/2023
Response #2:There are 400 working days per Addendum 4.
Response posted 11/30/2023
Inquiry #37: Where can a list of Mandatory Pre-Bid Meeting attendees be found?
Inquiry submitted 10/26/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/26/2023
Response #2:See Bidder Inquiry #1.
Response posted 10/30/2023
Inquiry #38: Specification 87-16.03A states: “Program the existing SCADA system including computers, PLC's and remote I/O, …”. Please provide detailed information on the existing SCADA system, including software name and version. Will as-built drawings and programs be made available?
Inquiry submitted 10/31/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/31/2023
Response #2:See Response to bidder's inquiry no. 34.
Response posted 11/02/2023
Inquiry #39: Specification 87-16.03F refers to “… the FCS for the Outdoor Utility Compartment …”. Is this new? Where is it located?
Inquiry submitted 10/31/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/31/2023
Response #2:The location of the utility compartment is approx. south of Substation 1. The plans and specs will be included in the upcoming addendum.
See the pre-bid meeting's Powerpoint presentation for approx. location of the utility compartment. For directions on how to acquire the slides, see Bidder Inquiry #41.
Response posted 11/09/2023
Inquiry #40: During the pre-bid meeting, mention was made about an optional site visit. Has a date and time been scheduled yet?
Inquiry submitted 11/02/2023
Response #1:No optional/mandatory site-visit has been decided.
Response posted 11/02/2023
Inquiry #41: Can Caltrans please share a copy of the slideshow presentation given to bidders at the pre-bid meeting?
Inquiry submitted 11/02/2023
Response #1:Please complete a Confidentiality Agreement (see link below) and submit it to the Duty Senior (D4.Construction.Duty.Senior@dot.ca.gov). You will then receive instructions on how to download the files.
CONFIDENTIALITY AGREEMENT - http://website.dot.ca.gov/dist4/construction/contracts/04-3G3644/ConfidentialityAgreement_3G3644.pdf
Response posted 11/02/2023
Inquiry #42: Access to Substation Rooms 1 and 4 is limited to a single man door below grade with stairs and a railing. Is there an expectation that the contractor is to dismantle the railing and widen the man door opening in order to remove the existing gear and install the new gear?
Inquiry submitted 11/03/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/03/2023
Response #2:The inquiry has been received and submitted for consideration.
Response posted 11/03/2023
Response #3:There is no expectation to remove the railing or widen the man door. It is up to the contractor to determine the method used to perform the work.
Response posted 11/30/2023
Inquiry #43: During the Prebid meeting it was announced that there is an Addendum for the drawings coming out. It was about substation #1. Can we expect this addendum prior to the job bid on Nov 15th?
Inquiry submitted 11/03/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/03/2023
Response #2:An addendum(s) is anticipated to address the substation and provide time to prepare bids.
Response posted 11/03/2023
Inquiry #44: Section 87-9.02D(12) Transformer states the transformer rating shall be 500 kVA. Sheet E-45 calls out 750kVA transformer for Substation 1. Please clarify.
Inquiry submitted 11/06/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/06/2023
Response #2:The transformer rating is 500kVA.
Response posted 11/09/2023
Inquiry #45: Given the tight timeframe for the armored Fiber installation, would Caltrans consider allowing a 48-hour lane closure on this project?
Inquiry submitted 11/06/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/06/2023
Response #2:Caltrans may consider a 48-hour continuous lane closure on the lower deck or 48-hour bike path closure on the upper deck if there would be a significant benefit for the project in terms of cost and schedule. For example, we may consider it if all of the armored fiber installation on the upper deck could be completed within one 48-hour path closure.
Response posted 11/09/2023
Inquiry #46: There are no details or mention of expansion joints thermal, seismic or otherwise.
Pleases confirm there are no expansion joints or :
provide quantities and locations of the expansion joints
provide movement ratings for each expansion joint
provide design for supporting cables across the joints that includes droop line dimensions
Inquiry submitted 11/06/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/06/2023
Response #2: The work does not impact or involve thermal expansion joints.
Response posted 11/30/2023
Response #3:The work does not directly impact or involve thermal expansion joints.
There are 8 expansion joints on the upper deck, and another 8 on the lower deck. The expansion joints are rated for a maximum of 18 inches. The seismic movement is about 52”.
In regards to the cable slack, it is suggested that an additional 8 foot long loop is used at the expansion joints.
Response posted 12/02/2023
Inquiry #47: There are no details or mention of expansion joints thermal, seismic or otherwise.
Pleases confirm there are no expansion joints or :
provide quantities and locations of the expansion joints
provide movement ratings for each expansion joint
provide design for supporting cables across the joints that includes droop line dimensions
Inquiry submitted 11/06/2023
Response #1:Same question as above.
Response posted 11/06/2023
Response #2:Refer to answer on bidder inquiry #46.
Response posted 11/30/2023
Inquiry #48: The X-section provided on Dwg U2 Sta 250 through U-3 to STA 282 does not appear correct.
While driving on the Lower Deck the concrete trestle section “does not” have any elevated walkway / cable trough as the drawings indicate.
This discrepancy is also shown on E-5 to E-7 for the cable removal and on E20-E22 for Cable installation.
Please provide clarification and drawings on actual conduit/cable routing.
Inquiry submitted 11/10/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/13/2023
Response #2:Please see updated plan sheets U-2, U-3, E-15A, E-15B, and E-30A in Addendum 4.
Response posted 11/30/2023
Inquiry #49: The X-section provided on Dwg U2 Sta 250 through U-3 to STA 282 does not appear correct.
While driving on the Lower Deck the concrete trestle section “does not” have any elevated walkway / cable trough as the drawings indicate.
This discrepancy is also shown on E-5 to E-7 for the cable removal and on E20-E22 for Cable installation.
Please provide clarification and drawings on actual conduit/cable routing.
Inquiry submitted 11/10/2023
Response #1:Same question as above.
Response posted 11/13/2023
Response #2:Refer to response BI #48.
Response posted 11/30/2023
Inquiry #50: Dwg UD-1 shows a "typical" X-section that is completely different from any other X-sections to include those shown on U-series and E-series drawings.
Please confirm that this drawing is not correct, or provide actual Station #'s where this x-section is applicable.
Inquiry submitted 11/10/2023
Response #1:Please provide the source of your asbuilts.
Response posted 11/13/2023
Response #2:Plan sheet UD-1 has been removed in Addendum 4.
Response posted 11/30/2023
Inquiry #51: Drawing E-51 shows a new FCS#1 for substation no. 1 with a note “see sheet E-51 for connection”. No connection details are shown. Please provide connection details for FCS#1.
Inquiry submitted 11/22/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/22/2023
Response #2:Please see the link to the scematics below:
http://website.dot.ca.gov/dist4/construction/contracts/04-3G3644/Schematic%20Sheet%20-%20FCS%201.pdf
Response posted 12/01/2023
Inquiry #52: Drawing E-134 shows a schematic for “Substation No. 1 FCS Wiring Diagram” but this appears to be unrelated to the FCS for substation no. 1. Please clarify.
Inquiry submitted 11/22/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/22/2023
Response #2:The battery system on Sheet E-134 is for the Outdoor Utility Compartment's power at Substation 1. The sheet title should say “Power Supply (PS) System Wiring Diagram” instead of "FCS Wiring Diagram."
Response posted 11/30/2023
Inquiry #53: The specs call for 270 days of completion. Is Caltrans flexible with this completion date? Can we take exception to that in our bid for the switchgear equipment?
Inquiry submitted 11/22/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/22/2023
Response #2:There are 400 working days per Addendum 4.
Response posted 11/30/2023
Inquiry #54: E-90 shows some items to be relocated to a “new backpan” and shows “space for backpan” on the left but it is unclear what this backpan is for (other than the two relocated items). It is also not clear if there is enough space in the existing enclosure since the drawing does not show a side view. Please clarify.
Inquiry submitted 11/22/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/22/2023
Response #2:
Response posted 11/22/2023
Inquiry #55: Spec 87-16.03J Additional Work reads: “Additional work must include debugging and fine-tuning of the current alarms, event alarms, display screens, and all other parameters for the existing SCADA system that must include the existing computers, the existing PLC's and the existing remote I/O and the new fiber optic modems, serial switch and RS-232 to RS-485 converters shown at the Richmond-San Rafael Bridge plans.” Will this be on a T&M basis?
Inquiry submitted 11/22/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/22/2023
Response #2:All SCADA work is included in the bid items. This "Additional work" is part of the Bid Item 23, SCADA System. Including all work to deliver a functional SCADA system.
Response posted 11/30/2023
Inquiry #56: Please refer to inquiry #55, This was a YES or NO question.
Please confirm that the existing SCADA system is a "FUNCTIONAL SYSTEM", if the repairs to the system are NOT being paid for on a force account basis, please quantify the exact quantities of repairs required to make it conform to your standard of "FUNCTIONAL".
Inquiry submitted 12/01/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 12/01/2023
Inquiry #57: The Addenda 4 biological report within Species Protection Area-4 states, “Install bird exclusion devices between September 16 to January 31 on top of the substation roof.” Bird exclusion devices are not show within the drawings. Please clarify where and what types of bird exclusion devices are required.
Inquiry submitted 12/01/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 12/01/2023
Response #2:The intent is to discourage seagulls from nesting on the sub-station roof. It is up to the Contractor to determine the appropriate location of the bird exclusion devices. There is no requirement for the types of the bird exclusion devices to be used. It is suggested that the use of traffic cones to occupy the space is sufficient.
Response posted 12/08/2023
Inquiry #58: The Addenda 4 biological report within Species Protection Area-5 states, “Avoid excess activity on pier to avoid disturbing seals from February 15 to July 15.” Please define excess activity.
Inquiry submitted 12/01/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 12/01/2023
Response #2:Excess activity is defined as non-essential work that is unrelated to keeping the generator re-fueled and maintained and re-conditioning the sub-station. Also, boat access is limited to the ladder that is hidden from the Castro Rocks- northwest side.
Response posted 12/08/2023
Inquiry #59: Good afternoon,
on addenda 4, spec section 87-9.02 was added calling out for outdoor utility compartment fence.
I am unable to locate on any of the plans where this fence will go. It is also not on the bid item list.
please advise.
Inquiry submitted 12/08/2023
Response #1:The inquiry has been received and submitted for consideration.
Response posted 12/08/2023
Response #2:Please do not include in your bid the outdoor utility compartment fence referenced in the Specifications.
Response posted 12/08/2023
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.