Viewing inquiries for 05-1J8604
Submit new inquiry for this projectInquiry #1: Would Caltrans change the bid item #83 Rubberized Hot Mix Asphalt (Gap Graded) to include Statistcal Pay Factor specifications? SPF would qualify as there is 51,000 Tons of RHMAG on this project.
Inquiry submitted 09/24/2024
Response #1:Your inquiry is submitted for review.
Response posted 09/25/2024
Response #2:Your inquiry is being reviewed.
Response posted 09/27/2024
Response #3:Your inquiry is being reviewed.
Response posted 09/30/2024
Response #4:Your inquiry is being reviewed.
Response posted 10/02/2024
Response #5:Your inquiry is being reviewed.
Response posted 10/05/2024
Response #6:2024-10-05 11:07:15 Your inquiry is being reviewed.
Response posted 10/07/2024
Response #7: Your inquiry is being reviewed.
Response posted 10/09/2024
Response #8:Statistical Pay Factor specifications will not be included in the contract. Please bid per advertised contract documents.
Response posted 10/10/2024
Inquiry #2: Specification 94-1.04 for tack oil states the emulsion quantity is the weight determined before adding water. Will the emulsion quantity that is directly from the tack oil refinery be paid or reduced?
Inquiry submitted 09/26/2024
Response #1:Your inquiry is submitted for review.
Response posted 09/27/2024
Response #2:The quantity of asphaltic emulsion is the weight from the refinery or supplier before further dilution.
Response posted 09/30/2024
Inquiry #3: Specification 39-3.04A requires the contractor to schedule cold plane activities and HMA paving during the same work shift. Would Caltrans change this specification to allow 3 days between mainline grind and pave?
Inquiry submitted 10/04/2024
Response #1:Your inquiry is submitted for review.
Response posted 10/05/2024
Response #2:Your inquiry is submitted for review.
Response posted 10/09/2024
Response #3:Your inquiry is submitted for review.
Response posted 10/15/2024
Response #4:Your inquiry is submitted for review.
Response posted 10/16/2024
Response #5:Your inquiry is submitted for review.
Response posted 10/17/2024
Response #6:Your inquiry is submitted for review.
Response posted 10/21/2024
Response #7:The requirements will be changed to "schedule cold planing activities such that not more than 48 hours has elapsed
between the time the pavement is cold planed and the time the HMA is placed, except at repaired failed area." An addendum will be issued.
Response posted 10/23/2024
Response #8:Your attention is directed to Addendum No. 1 dated October 25, 2024.
Response posted 10/25/2024
Inquiry #4: On plan sheet 258, ECL-2, at the top left corner is NOTE: For Erosion Control Type 1, See Sheet C-11. On Sheet C-11 there is not any information for Erosion Control Type 1 stated. Please clarify.
Inquiry submitted 10/20/2024
Response #1:Your inquiry is submitted for review.
Response posted 10/21/2024
Response #2:Your inquiry is under review.
Response posted 10/23/2024
Response #3:An addendum will be issued to delete the note reference of C-11.
Response posted 10/25/2024
Response #4:An addendum will be issued to delete the note reference of C-11.
Response posted 10/28/2024
Response #5:An addendum will be issued to delete the note reference of C-11.
Response posted 10/30/2024
Response #6:Your attention is directed to Addendum No. 2 posted on Oct 31, 2024. The note to reference C-11 is deleted.
Response posted 11/01/2024
Inquiry #5: Regarding special provisions section 83-2.01D(2), is filter fabric required for the Vegetation Control Crushed Shale areas? If yes, what is the specification for the fabric material and where does it go?
Inquiry submitted 10/21/2024
Response #1:Your inquiry is submitted for review.
Response posted 10/22/2024
Response #2:Filter fabric is not required. An addendum will be issued.
Response posted 10/23/2024
Response #3:Filter fabric is not required for vegetation control work. An addendum will be issued.
Response posted 10/25/2024
Response #4:Filter fabric is not required for vegetation control work. An addendum will be issued.
Response posted 10/28/2024
Response #5:Filter fabric is not required for vegetation control work. An addendum will be issued.
Response posted 10/30/2024
Response #6:Filter fabric is not required for vegetation control work. An addendum will be issued.
Response posted 11/01/2024
Response #7:Please refer to Addendum No. 3 posted on Nov 6, 2024. In the Special Provisions, Section 83-2.01D(2) items 2 and 3 are deleted.
Response posted 11/07/2024
Inquiry #6: The typical cross sections show grading outside the typical 4’ wide shoulder in order to build a 4:1 slope. Some of these areas show dirt to be placed, and some areas show dirt to be removed. The Summary of Quantities for Roadway Excavation does not include any quantities for this earthwork/grading. How is this earthwork/grading paid?
Inquiry submitted 10/30/2024
Response #1:Your inquiry is submitted for review.
Response posted 10/30/2024
Response #2:An addendum will be issued to remove the 4:1 cut/fill grading work beyond the hinge point.
Response posted 11/01/2024
Response #3:An addendum will be issued to revise the Typical Cross Section sheet.
Response posted 11/04/2024
Response #4:Please refer to Addendum No. 3 posted on Nov 6, 2024.
Response posted 11/07/2024
Inquiry #7: The summary of quantities for Vegetation Control shows new Veg Control being installed where existing veg control is not being removed. The Summary of Quantities for Roadway Excavation does not include any quantities for this earthwork/grading. How is the excavation/grading for the new Veg Control paid?
Inquiry submitted 10/30/2024
Response #1:Your inquiry is submitted for review.
Response posted 10/30/2024
Response #2:Existing vegetation control shall be removed under Bid Item 168 (Remove Vegetation Control) prior to installation of new vegetation control.
Excavation and grading are included in Bid Item 167 VEGETATION CONTROL (CRUSHED SHALE), per Special Provision 83-2.01D(4)(b), "Earthwork" and Standard Specifications 9-1.03, "PAYMENT SCOPE", Full compensation for all work involved in each bid item shown on the Bid Item List by the unit of measure shown for that bid item.
Response posted 11/02/2024
Inquiry #8: Can allowable loading information of the existing bridges throughout the project be provided? After visual inspection of the existing bridges it appears the shuttle buggy is not able to cross bridges in accordance with Section 5-1.37B(1).
Inquiry submitted 10/30/2024
Response #1:Your inquiry is submitted for review.
Response posted 10/30/2024
Response #2:Your inquiry is submitted for review.
Response posted 11/02/2024
Response #3:Your inquiry is being reviewed.
Response posted 11/05/2024
Response #4:Reference Section 5-1.37B “Load Limits” of the Standard Specifications in regard to construction equipment exceeding the size or weight limits of Veh Code Div 15.
Response posted 11/06/2024
Inquiry #9: As written, the gravel filter gradations may be difficult or impossible for certain mining operations to achieve. Will Caltrans consider accepting permeable materials as substitute?
Inquiry submitted 10/30/2024
Response #1:Your inquiry is submitted for review.
Response posted 10/30/2024
Response #2:Substitution is not allowed. Please bid per contract documents.
Response posted 11/02/2024
Inquiry #10: Regarding Inquiry #1 Response for Item #83 RHMAG Statistical Pay Factor Specifications, would Caltrans be willing to include SPF specifications without the positive payment adjustment in 39-2.10A(4)(c)(iv)(D) as an alternative?
Inquiry submitted 11/01/2024
Response #1:No. Statistical Pay Factor will not be included. Please bid per contract documents.
Response posted 11/01/2024
Inquiry #11: Please clarify the traffic handling plan for improvements at Los Berros Creek Bridge, specifically the approach slab. It appears temporary railing is only shown for constructing the concrete barrier transitions (Sheet TH-3, Stage 1).
Inquiry submitted 11/01/2024
Response #1:Traffic Handling Plans with temporary barrier system is not available for the approach slab construction. Please construct the approach slab using Standard Plan Temporary Traffic Control Systems and comply with the Lane Requirement Chart G2 shown in the Special Provisions.
Response posted 11/02/2024
Inquiry #12: Are the requirements of Special Provisions Section 7-1.02M(2) regarding a truck and operator patrolling the work area as 'fire watch' applicable when work is being performed at night?
Inquiry submitted 11/05/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/05/2024
Response #2:Special Provisions Section 7-1.02M(2) requires the truck and operator to be available at the site of work, and patrol 1/2 hour after job site activities have ended. If the fire danger rating is "very high" or "extreme" or "fire weather watches" or "red flag warning" is issued, the truck and operator must patrol the area of construction while work is being done and for at least 1/2 hour after job site activities have ended.
Response posted 11/07/2024
Inquiry #13: Where is the Wildlife passage way Type ML to be paid? No bid item for this work and it is not accounted for in the Type MS Wildlife Passage Way quantity.
Please Advise
Inquiry submitted 11/05/2024
Response #1:An addendum is being prepared to rename the Wildlife Passage Way Type ML to Type L.
Per Standard Specification 83-3.01A, concrete barrier work includes constructing Type L Wildlife passageways.
Response posted 11/07/2024
Response #2:An addendum is being prepared to rename the Wildlife Passage Way Type ML to Type L. Per Standard Specification 83-3.01A, concrete barrier work includes constructing Type L Wildlife passageways.
Response posted 11/10/2024
Response #3:Please refer to Addendum No.4 dated Nov 13, 2024. Wildlife Passage Way Type ML is revised to Type L. Per Standard Specification 83-3.01A, concrete barrier work includes constructing Type L Wildlife passageways. Passageway Type L is included in Concrete Barrier (Type 60MS) quantity.
Response posted 11/14/2024
Inquiry #14: Please povide rebar details for Passageway Type ML. No extra rebar is shown.
Please advise.
Inquiry submitted 11/05/2024
Response #1:An addendum will be issued to rename the Wildlife Passage Way from Type ML to Type L, and show reinforcement for the footing and end anchorage.
Response posted 11/07/2024
Response #2:An addendum will be issued to rename the Wildlife Passage Way from Type ML to Type L, and show reinforcement for the footing and end anchorage.
Response posted 11/10/2024
Response #3:Please refer to Addendum No.4 dated Nov 13, 2024. Wildlife Passage Way Type ML is revised to Type L. Reinforcement is shown at concrete footing and end anchorage.
Response posted 11/14/2024
Inquiry #15: Please point to a detail showing Wildlife Passageway Type S.
Type MS is in the Standard plans, Type S is not.
Please advise.
Inquiry submitted 11/05/2024
Response #1:An addendum will be issued to provide a construction detail for Wildlife Passageway (Type S).
Response posted 11/07/2024
Response #2:An addendum will be issued to provide a construction detail for Wildlife Passageway (Type S).
Response posted 11/10/2024
Response #3:Please refer to Addendum No.4 dated Nov 13, 2024 for Wildlife Passage Way (Type S) construction detail.
Response posted 11/14/2024
Inquiry #16: Please point to a detail showing Wildlife Passageway Type S.
Type MS is in the Standard plans, Type S is not.
Please advise.
Inquiry submitted 11/05/2024
Response #1:An addendum will be issued to provide a construction detail for Wildlife Passageway (Type S).
Response posted 11/07/2024
Response #2:An addendum will be issued to provide a construction detail for Wildlife Passageway (Type S).
Response posted 11/10/2024
Response #3:Please refer to Addendum No.4 dated Nov 13, 2024 for Wildlife Passage Way (Type S) construction detail.
Response posted 11/14/2024
Inquiry #17: Standard plan A76J shows Concrete Barrier Wildlife Passageway (Type MS) going in type M barrier with 10 continuous #5 bars. With this project being type MS barrier(36" tall), that only requires 8 #5's continuous. Please confirm only 8 #5's are needed for the barrier with the MS Passageways.
Inquiry submitted 11/05/2024
Response #1:An addendum will be issued to rename Wildlife Passageway from Type MS to Type S. A construction detail will be provided to show 8 #5 bars.
Response posted 11/07/2024
Response #2:Please refer to Addendum No.4 dated Nov 13, 2024. Wildlife Passageway is revised from Type MS to Type S. Construction detail shows 8 #5.
Response posted 11/14/2024
Inquiry #18: SCD-1 and SCD-2 show Krail and Concrete Barrier type MS overlapping.
Please clarify what stage the barrier @ station 625+15.44 goes in and provide cross sections for the krail placement. These sheets do not highlight the barrier section as a work area within the traffic handling plans.
Please advise ASAP.
Inquiry submitted 11/15/2024
Response #1:An addendum will be issued to provide the information.
Response posted 11/18/2024
Response #2:An addendum will be issued to provide the information.
Response posted 11/20/2024
Response #3:An addendum will be issued to provide the information.
Response posted 11/24/2024
Response #4:Please refer to Addendum No. 6 posted on Nov 26, 2024 for the revised traffic handling plans showing work area and temporary barrier placement.
Response posted 11/26/2024
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.