Viewing inquiries for 05-1P5304

Submit new inquiry for this project


Inquiry #1: On sheet 24, LQ-1, the Prune Existing Plants table has 12ea Callistemon to be pruned on LL-6, and the Roadside Clearing table has 12ea repair of plant basin on LL-6 as well.
However, on the left side of page LL-6 it calls out 12ea Callistemon to be removed and grind stumps. Please confirm which action is to take place.

Inquiry submitted 01/24/2023

Response #1:Your inquiry has been submitted for review.
Response posted 01/24/2023


Response #2:An addendum has been issued today, January 26, 2023, in response to this inquiry. Place your bids in accordance with Contract Documents.
Response posted 01/26/2023




Inquiry #2: Landscape Layout plans show to remove existing trees. Is the contractor also to remove any existing irrigation? Is the existing irrigation to be abandoned in place? Not clear Please advise.
Inquiry submitted 01/27/2023

Response #1:Attention is directed to plan sheet ISS-1 & L – 1-12 for existing irrigation facilities. Attention is also directed to section 20.10.02C(2) of the contract special provisions. Place your bid in accordance with current contract documents.”
Response posted 01/27/2023




Inquiry #3: For bid item 34 check and test existing irrigation facilities are there any irrigation as-builts If so can they be provided? Not clear what existing irrigation is to be checked and operated? Please advise.
Inquiry submitted 01/27/2023

Response #1:Attention is directed to plan sheet ISS-1 & L – 1-12 for existing irrigation facilities. Attention is also directed to section 20.10.02C(2) of the contract special provisions. Place your bid in accordance with current contract documents.”
Response posted 01/27/2023


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.