Submit new inquiry for this projectInquiry #1: Plan sheet 28 of 29, Section Thru Waler, calls for 8”X16” Blocks. Plastic lumber suppliers carry 6”x16”. The 8”X16” is not available. Will 6”X16” plastic lumber be acceptable?
Inquiry submitted 04/03/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/03/2025
Response #2:Refer to section 4-1.07B, "Value Engineering Change Proposal," of the Standard Specifications. Proposals for modifications to the contract documents may be submitted to the Engineer after contract award. Please bid per the current contract bid documents.
Response posted 04/10/2025
Inquiry #2: Per section 7-1.02K(6)(e)(ii) Bridge Scaffolding, the available bridge uniform load (Unfactored) is 50 LB/sq.ft. Does this account for the temporary barrier system across the length of the bridge?
Inquiry submitted 04/11/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/11/2025
Response #2:Refer to paragraph 1 and paragraph 2 of section 7-1.02K(6)(e)(ii), "Bridge Scaffolding," of the Special Provisions. Please bid per the current contract bid documents.
Response posted 04/23/2025
Inquiry #3: Per Section 12-4.02C(3)(f) Closure Restrictions for Designated Holidays and Special Days it says the full width of travel needs to be open before each holiday and multiple days after. Is there anyway to keep one lane closed through the holidays listed.
Inquiry submitted 04/17/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/18/2025
Response #2:Closure Restrictions for Designated Holidays and Special Days may not be applied to the long-term lane closure.
Response posted 04/21/2025
Inquiry #4: Below the south end of the bridge there is a homeless encampment. The homeless person has the access to the area under the bridge fenced off, limiting contractors ability to inspect the underside of the bridge, Will Caltrans remove this person prior to bid date?
Inquiry submitted 04/22/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/22/2025
Response #2:Yes, Caltrans is scheduled to clear the encampment area by Thursday, May 1, 2025. Please be advised, the area may be reoccupied shortly thereafter, due to ongoing challenges related to homelessness in the area.
Response posted 04/24/2025
Inquiry #5: Will Caltrans clean up syringes and Human waste from the homeless encampment under the south end of the bridge?
Inquiry submitted 04/22/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/22/2025
Response #2:Yes this will be completed prior to the beginning of work.
Response posted 04/24/2025
Inquiry #6: Are the galvanized conduit under the bridge to be painted?
Inquiry submitted 04/22/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/22/2025
Inquiry #7: Given the limitations of access due to the width of the bridge and the lack of a Northside laydown area can a barge be used for access and equipment?
Inquiry submitted 04/22/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/22/2025
Inquiry #8: Marine activities in support of this project are not addressed in the special provisions. Can these be added?
Inquiry submitted 04/22/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/22/2025
Response #2:Bid per current contract documents.
Response posted 04/22/2025
Inquiry #9: Are there restrictions on wind loading for the containment which would limit the amount of the bridge that can be contained at any one time?
Inquiry submitted 04/22/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/22/2025
Inquiry #10: To what extent is the bridge turntable to be painted?
Inquiry submitted 04/22/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/22/2025
Inquiry #11: Given that the containment will cover much of the bridge other than the driving lane, what lighting requirements are required for the section of roadway open to the public?
Inquiry submitted 04/22/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/22/2025
Response #2:Bid per current contract documents.
Response posted 04/22/2025
Inquiry #12: How can as built drawings for the bridge be acquired?
Inquiry submitted 04/22/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/22/2025
Inquiry #13: Please review traffic chart L1. This is a 12-hour Sunday complete closure.
Note #4 says this chart is for installing/removing temp. barrier, bridge PPC overlay, and erecting/dismantling scaffolding.
Note #5 goes on to say duration of full closure not to exceed one weekend (12 hour Sunday) for this work?
Please review and revise.
Inquiry submitted 04/23/2025
Response #1:Your Inquiry has been submitted for review.
Response posted 04/23/2025
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.