Viewing inquiries for 11-056404
Submit new inquiry for this projectInquiry #1: Looks like you forgot some bid items for the overhead sign work. No bid item to install Laminated Panel Sign (1"-Type A), removal of walkways, removal of existing signs, installation of new sign supports, etc.
Inquiry submitted 10/08/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/08/2024
Response #2:Please refer to Addendum No. 1, dated October 28, 2024.
Response posted 10/29/2024
Inquiry #2: Item #0039 Install Precast Box Culvert 8'x4' (85 LF). At DS -2 there is 192 feet of 8'x4' RCB on the ground. Also ad DS-1 there is 24 feet on the ground, for a total of 216 feet on site, How is this extra feet going to be paid as to install?
Can we use Precast RCB on Items 0037F (Structure Concrete Box Culvert). and item 0042 (Bar Reinforcing Steel) Box Culvert)? With the contract completion time of 100 working days, this will allow so time savings. It looks like the previous project the precast RCB was used.
Inquiry submitted 10/18/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/18/2024
Response #2:All existing RCB pieces on site are accounted for. Only 85 LF are shown on the project plans to be installed and paid for under item #39 (Install Precast Box Culvert 8’x4’). All other box culverts are shown to be CIP and paid for under items #37 (Structural Concrete, Box Culvert) and #42 (Bar Reinforcing Steel, Box Culvert).
For changes, please refer to standard specification, section 5 “Control of Work” regarding means and methods and section 4-1.07 “Value Engineering” for submittal of a Value Engineering Change Proposal.
Response posted 10/25/2024
Inquiry #3: Item #0039 Install Precast Box Culvert 8'x4' (85 LF). At DS -2 there is 192 feet of 8'x4' RCB on the ground. Also ad DS-1 there is 24 feet on the ground, for a total of 216 feet on site, How is this extra feet going to be paid as to install?
Can we use Precast RCB on Items 0037F (Structure Concrete Box Culvert). and item 0042 (Bar Reinforcing Steel) Box Culvert)? With the contract completion time of 100 working days, this will allow so time savings. It looks like the previous project the precast RCB was used.
Inquiry submitted 10/18/2024
Response #1:Please refer to the response to inquiry #2.
Response posted 10/18/2024
Inquiry #4: _Please confirm Owner is generator of pre-existing haz mat and will sign all transportation manifests for disposal of pre-existing haz mat.
Inquiry submitted 10/21/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/21/2024
Response #2:Please clarify and provide more information on this question.
Response posted 10/29/2024
Inquiry #5: _Will owner waiver consequential Damages?
Inquiry submitted 10/21/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/21/2024
Response #2:Please clarify and provide more information on this question.
Response posted 10/29/2024
Inquiry #6: _Will owner waiver consequential Damages?
Inquiry submitted 10/21/2024
Response #1:Duplicate inquiry. Please refer to the response to inquiry #5.
Response posted 10/21/2024
Inquiry #7: _Is there a cap on liquidated damages?
Inquiry submitted 10/21/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/21/2024
Response #2:Please refer to standard specification section 8-1.10, "Liquidated Damages".
Response posted 10/23/2024
Inquiry #8: _Will owner provide waiver of subrogation?
Inquiry submitted 10/21/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/21/2024
Response #2:Please refer to the standard specifications section 7-1.05 "INDEMNIFICATION", Section 7-1.06 "INSURANCE" including Section 7-1.06C "Workers' Compensation and Employer's Liability Insurance", and section 7-1.06D(4) "Contractor's Insurance - Waiver of Subrogation".
Response posted 10/30/2024
Inquiry #9: _Please consider extending the bid due date due to schedule conflicts.
Inquiry submitted 10/21/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/21/2024
Response #2:Unless an addendum is issued to revise the bid opening date, please bid per the current contract documents.
Response posted 10/23/2024
Inquiry #10: _Please provide any geotechnical information available for the project.
Inquiry submitted 10/21/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/21/2024
Response #2:Please refer to Addendum No. 1, dated October 28, 2024.
Response posted 10/29/2024
Inquiry #11: Can you please confirm the concrete quantity for the Straight Wingwall in Drainage System 3 Element J?
Inquiry submitted 10/22/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/22/2024
Response #2:Please refer to Addendum No. 1, dated October 28, 2024.
Response posted 10/29/2024
Inquiry #12: Bid Item #76 "Remove Concrete Barrier (Type) quantity is 60 lf. However plan sheet C-4 and C-8 total Remove Concrete Barrier quantity is 60 lf + 120 lf = 180 lf. And plan sheet Q-1 summary of quantities also shows 180 lf. of Remove Concrete Barrier. Please advise.
Inquiry submitted 10/22/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/22/2024
Response #2:Please refer to Addendum No. 1, dated October 28, 2024.
Response posted 10/29/2024
Inquiry #13: Will the removed barrier rail, crash cushion, barricades be contractor's property or salvaged at a location directed by owner? Please advise
Inquiry submitted 10/22/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/22/2024
Response #2:Please refer to Bid Item list which does not show bid items for salvaging barrier rail, crash cushion, or barricades. Please refer to Section 15, "Existing Facilities", of the standard specifications for performing work on existing facilities.
Response posted 10/23/2024
Inquiry #14: Drainage Profile DP-1, element F describes the Headwall, wingwalls with a height of 7' However Drainage Detail page DD-6 calls out top of wall and footing elevations equaling 8.6' Please Advise as to what height is to be used.
Inquiry submitted 10/22/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/22/2024
Response #2:The inquiry has been received and submitted for consideration.
Response posted 10/22/2024
Response #3:Please refer to Addendum No. 1, dated October 28, 2024.
Response posted 10/29/2024
Inquiry #15: Section A-A on plan sheet DD-10 shows 6"x6" wire mesh and #4 Rebar that must maintain 1.5" from the mesh. The 1.5" will be hard to maintain as this area will be walked on when placing concrete. Would the owner consider using a thicker wire mesh or just rebar to construct the concrete channel?
Inquiry submitted 10/22/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/22/2024
Response #2:Please refer to Addendum No. 1, dated October 28, 2024.
Response posted 10/29/2024
Inquiry #16: Sheet #1 of the notice to bidders cites prevailing wages are required on this contract. 7-1.11B FHWA-1273 of the notice to bidders, IV. DAVIS-BACON AND RELATED ACT PROVISIONS, cites the minimum wages in part or in its entirety as cited are required to be per the Davis Bacon wage requirement(s). Please clarify.
Inquiry submitted 10/22/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/22/2024
Response #2:Please refer to Federal Wage General Decision Number: CA20240001, dated 09/06/2024. You can find a copy of this file in the Advertised Contract Documents, it is named: “11-056404fw.pdf”
Response posted 10/23/2024
Inquiry #17: Would the contractor be able to use the property within the end of the present concrete paving on Route 11 and the work areas described in this contract for construction traffic, storage, and laydown if restored to its current condition?
Inquiry submitted 10/24/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2024
Response #2:Please refer to standard specification, section 4, "Scope of Work", and section 4-1.07, "Value Engineering".
Response posted 10/25/2024
Inquiry #18: The project only has a duration of 100 working days and a 15 day start. There is not enough time to complete all this work within 100 working days. Please add additional working days to the contract duration.
Inquiry submitted 10/24/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2024
Response #2:Unless an addendum is issued to revise the working days, please bid per the current contract documents.
Response posted 10/25/2024
Inquiry #19: There is remedial grading shown on Sheet C-6 that is outside of the grading limits shown on the Grading Plans particularly in the SW corner of the site. Is this correct? If so, does this material get put back to specific design grades or just removed and recompacted to a depth of 2.5'?
Inquiry submitted 10/24/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2024
Response #2:Please refer to Addendum No. 1, dated October 28, 2024. Remedial grading shown is to be excavated and recompacted in-place.
Response posted 10/29/2024
Inquiry #20: Stage Construction Plan SC-1 has a "Stage 1D - Spray Temporary Hydraulic Mulch (Bonded Fiber Matrix)". Where is this temporary hydraulic mulch being placed? The import and roadway excavation does not take place until Stage 2. Are we required to spray the entire site with temporary hydraulic mulch after clearing and grubbing?
Inquiry submitted 10/24/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2024
Response #2:Please refer to Addendum No. 1, dated October 28, 2024 for revisions, and bid per current contract documents.
Response posted 10/29/2024
Inquiry #21: Bid Item 18 - Temporary Hydraulic Mulch (BFM) has a bid qty of 69,800 SY however the quantity on Sheet WPCQ-1 is 329,006 SY. Please revise bid qty.
Inquiry submitted 10/24/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2024
Response #2:Please refer to Addendum No. 1, dated October 28, 2024.
Response posted 10/29/2024
Inquiry #22: Stage 1C - Line Channel Near Drainage System 3 is specified on Sheet SC-1. Please clarify which channel is to be lined in this stage. Is it Drainage System #2-c or Drainage System #3-l?
Inquiry submitted 10/24/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2024
Inquiry #23: There is material stockpiled towards the NE corner of the site, however it is not shown on the grading plans and appears to be outside of the grading limits shown on the plans. Is this material to be removed as roadway excavation and placed as embankment, or left in place as a stockpile?
Inquiry submitted 10/24/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2024
Response #2:Please refer to Addendum No. 1, dated October 28, 2024.
Response posted 10/29/2024
Inquiry #24: SSP Section 6-1.03B(2) states that material "obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material". The contract duration is only 100 working days. There is not enough working days in the contract to wait 60 days for a local material plan. Please add days to the contract duration.
Inquiry submitted 10/24/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2024
Response #2:Please refer to Addendum No. 1, dated October 28, 2024 for additional information, and bid per current contract documents.
Response posted 10/29/2024
Inquiry #25: How long are the sections of the 8'x 4' precast box culverts that are already on side and how much does each weigh?
Inquiry submitted 10/29/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/29/2024
Inquiry #26: Addendum 1 Sheet C-6 & C-7 show remedial grading outside of the design grading limits. What grade is the area to be restored to?
Inquiry submitted 10/29/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/29/2024
Response #2:Please refer to response on bidder inquiry #19 and bid per current contract documents.
Response posted 11/01/2024
Inquiry #27: Sheet C-6 shows remedial grading outside of the design grading limits. What grade is this area to be restored to?
Inquiry submitted 10/29/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/29/2024
Response #2:Please refer to response to inquiry #26.
Response posted 11/01/2024
Inquiry #28: Drainage system 1 element f & g for the wing wall and rock slope protection are outside of the design grading limits. There is no way for the contractor to determine the earthwork involve in constructing this. Please provide a grading plan for this area.
Inquiry submitted 10/29/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/29/2024
Response #2:The inquiry has been received and submitted for consideration.
Response posted 10/29/2024
Inquiry #29: Addendum 1 Draft Interim As-Graded Geotechnical Report Otay Mesa East Port Of Entry makes reference to materials that may not meet the specification as fill for this project for being expansive, oversized or corrosive. There is no way for the contractor to know if they will encounter these materials. Confirm that the contractor can assume that existing on site material will be suitable for use as fill material.
Inquiry submitted 10/29/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/29/2024
Response #2:Contractor can assume existing onsite material is suitable for fill material. Please refer to Standard Specification 19-6 Embankment Construction.
Response posted 11/01/2024
Inquiry #30: Addendum 1 Crossed out Section A-A & DS2 Channel line Sta 23+00-23+10.3 on plan sheet DD-10. Does the owner no want rebar #4 at 8” longitudinal, and #4 at 18” transverse per the detail on plan sheet DD-4. Please clarify.
Inquiry submitted 10/30/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/30/2024
Inquiry #31: Caltrans response to inquiry #13 did not clarify the question. Section 15 of standard specifications notes to salvage material to the location specified in the special provision and stockpile. Please clarify if the removed 180 LF. temporary barrier rail will be contractor's property or salvaged per Section 15 specifications.
Inquiry submitted 10/30/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/30/2024
Inquiry #32: Contractor requests additional elevations on the plans for the existing and new contours to provide a complete take off - please provide.
Inquiry submitted 10/30/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/30/2024
Inquiry #33: Contractor requests additional elevations on the plans for the existing and new contours to provide a complete take off - please provide.
Inquiry submitted 10/30/2024
Response #1:Duplicate inquiry. Please refer to the response to inquiry #32.
Response posted 10/30/2024
Inquiry #34: _Special Provisions section 13-3.01A notes that this project's risk level is 2. Per 2023 Caltrans Standard Specifications 13-3.01C(1) Rain Even Action Plan is not required for Project Risk Level 2. Only the Lake Tahoe Hydrologic Unit projects require REAPs. Will BI 0014 be deleted?
Inquiry submitted 10/31/2024
Response #1:Please refer to Addendum #1, dated October 28, 2024, which deleted item #0015 Rain Event Action Plan.
Response posted 10/31/2024
Inquiry #35: Please consider extending the due date to due to schedule conflicts.
Inquiry submitted 11/01/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/01/2024
Inquiry #36: _Due to the Scope of Work available and the 22% DBE goal, our initial outreach has indicated limited coverage. To potentially increase DBE participation, would you consider postponing the bid one (1) week to Thursday, November 21st?
Inquiry submitted 11/01/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/01/2024
Inquiry #37: _Please update the .col file for the quantities and bid items that have changed per Addendum 1.
Inquiry submitted 11/01/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/01/2024
Inquiry #38: Response #2 to bidders Inquiry #24 refers to the contractor to Addendum No. 1. Addendum No. 1 does not address SSP Section 6-1.03B(2) or the contract duration of 100 working days. Please provide a response to the question: SSP Section 6-1.03B(2) states that material "obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material". The contract duration is only 100 working days. There is not enough working days in the contract to wait 60 days for a local material plan. Please add days to the contract duration.
Inquiry submitted 11/01/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/01/2024
Inquiry #39: Bid Item #56 quantity (Rock Slope Protection Fabric-Class 8 ) is 230 sy and only used at DS#1 Rock Slope Protection. Will Class 8 fabric required under Bid Items #53, #54, #55 rock slope protection works. If yes is it incidental to bid items?
Inquiry submitted 11/01/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/04/2024
Inquiry #40: _"Sign Plan sheet PD-3 shows what appears to be W19-2 signs (identified duplicative as Sign No. 302 & 303) to be installed on two-posts. These signs and posts do not appear to be reflected in the bid item or plan quantities. Please clarify where these are to be paid.
Additionally, Sign No 502 is identified as to be relocated however it is not accounted for in Bid item 62 quantity. Please clarify where this is to be paid."
Inquiry submitted 11/04/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/04/2024
Inquiry #41: Sheet C-3 shows approximately 600 SF of cold plane ac pavement, however, sheet Q-1 shows 600 SY. Please confirm that there are no more locations.
Inquiry submitted 11/04/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/04/2024
Inquiry #42: May the contractor use the rip rap material onsite as source of Rock Slope Protection at related bid items for free ?
Inquiry submitted 11/04/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/04/2024
Inquiry #43: Please provide the design cad files for grading work so that a detailed takeoff can be performed.
Inquiry submitted 11/04/2024
Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/04/2024
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.