Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 02-1H74U4

Submit new inquiry for this project


Inquiry #1: Please specify the working days for permanent erosion control establishment period.
Inquiry submitted 08/29/2019

Response #1:
(#1)-Your inquiry has been received and is being reviewed.
Response posted 08/30/2019


Response #2:
An addendum will be issued to address this.
Response posted 09/04/2019


Response #3:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 1, issued on Friday, September 13, 2019. Please bid per the current contract documents.
Response posted 09/13/2019




Inquiry #2: the specials state that trees will be fell by others will the trees be left for contractor clean up or will the area be logged and only stumps remaining ,as the logs have value it effects the bidding process for clearing and grubbing ?
Inquiry submitted 09/04/2019

Response #1:
(#2)-Your inquiry has been received and is being reviewed.
Response posted 09/05/2019


Response #2:
Merchantable timber will be removed by others. Please bid per the current contract documents.
Response posted 09/09/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.