Viewing inquiries for 02-4G6204

Submit new inquiry for this project


Inquiry #1: Is coating the existing steel water storage tank shown on sheet W-5 part of item #56 Building Work?
Inquiry submitted 09/23/2020

Response #1:
(BI#1)-Your inquiry has been received and is being reviewed.

Response posted 09/24/2020


Response #2:(BI#1)-Yes, coating the existing water storage tank shown on plan sheet W-5 is included in the bid item #56, 994650 Building Work.
Response posted 09/25/2020




Inquiry #2: Is coating the existing steel water storage tank shown on sheet W-5 part of item #56 Building Work?
Inquiry submitted 09/23/2020

Response #1:
(BI#2)-Your inquiry has been received. However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response. If no additional response is posted please bid per the current contract documents.

Response posted 09/24/2020


Response #2:
(BI#2)-Yes, coating the existing water storage tank shown on plan sheet W-5 is included in the bid item #56, 994650 Building Work.


Response posted 09/25/2020




Inquiry #3: Specification Section 99-09900 is included with the special provisions. However the plans do not indicate any painting other than the interior of the tank. Please clarify if we are to paint the restroom building?
Inquiry submitted 09/23/2020

Response #1:
(BI#3)-Your inquiry has been received. However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response. If no additional response is posted please bid per the current contract documents.

Response posted 09/24/2020


Response #2:
(BI#3)-There is no painting of the comfort station and water treatment equipment building, only touch up painting due to building modifications. Please bid per the current contract documents.
Response posted 09/25/2020




Inquiry #4: Bid item #8 is for Prepare Water Pollution Control Program. Should this be Prepare Storm Water Pollution Control Plan? A WPCP does not require: REAPs (bid item #9), Storm Water Sampling & Analysis Days (bid item #10), and Storm Water Annual Reports (bid item #11).
Inquiry submitted 09/25/2020

Response #1:(BI#4)-Your inquiry has been received. However, please be aware due to the short time frame between when this inquiry was received and the bid opening, there may not be time to provide a response. If no additional response is posted please bid per the current contract documents.

Response posted 09/25/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.