Viewing inquiries for 04-2K1704

Submit new inquiry for this project


Inquiry #1: FYI-Caltrans to-All Bidders- How do I register for Mandatory Pre-Bid Meeting?
Inquiry submitted 10/03/2022

Response #1:Please do not use the Bidder Inquiry platform for Mandatory Pre-Bid Meeting registration; it is for inquiries related to bidding on the project contract. Register in advance of the Mandatory Pre-Bid Meeting, and no later than 1 hour before the meeting time, by sending an email with bidder information to "D4.Construction.Duty.Senior@dot.ca.gov" Please include the project number & "Mandatory Pre-Bid Meeting", within the subject of the email.
Response posted 10/03/2022




Inquiry #2: For Bid Item #23, did you mean the unit to be in SF instead of SY?
Inquiry submitted 10/24/2022

Response #1:Submitted for consideration.
Response posted 10/25/2022


Response #2:Bid item 23 and Plan Sheets 32, 34, 35, 36, 37 have been replaced per addendum 2 issued on 11/22/2022. Please refer to addendum 2.
Response posted 11/22/2022




Inquiry #3: In the temporary traffic control chart, for Stage 2 at Location 2, you do not list any temp k-rail, yet the plans show us closing off the westbound side of the Tennyson Road bridge. Should there be an entry for temp k-rail in this stage?

In Stage 1 at Location 2, we are installing and removing k-rail each night to provide for worker safety as we complete median work from Sta "T" 45+79 to 53+28. How are we being paid for this k-rail since THQ-1 shows no quantity entry for this area?

Inquiry submitted 11/10/2022

Response #1:Submitted for consideration.
Response posted 11/10/2022


Response #2:Bid item 15, 18, and Plan Sheets 77, 78, 79, 86, 87, 88, 99 have been replaced per addendum 2 issued on 11/22/2022. SSP 8-1.10B is added per addendum 2 issued on 11/22/2022. Please refer to addendum 2.
Response posted 11/22/2022




Inquiry #4: Can Caltrans update plan sheet SC-15 to show the k-rail positions in Stage 1?
Inquiry submitted 11/10/2022

Response #1:Submitted for consideration.
Response posted 11/10/2022


Response #2:Plan Sheets 89 and 95 have been replaced per addendum 2 issued on 11/22/2022. Please refer to addendum 2.
Response posted 11/22/2022




Inquiry #5: Will the Department pay for Rain Event Action Plan, and Storm Water Sampling and Analysis Day?
Inquiry submitted 11/15/2022

Response #1:Submitted for consideration.
Response posted 11/16/2022


Response #2:Bid item 147 and 148 have been added per addendum 4 issued on 12/05/2022. Please refer to addendum 4.
Response posted 12/09/2022




Inquiry #6: Drawings X-3 thru X-7 suggest Tennyson Rd has a road section that includes .5' of CTB (Cemented Treated Base) .... however drawing C-2 suggest the road section does not have any CTB. Please clarify as CTB excavation is much more difficult.
Inquiry submitted 11/18/2022

Response #1:Submitted for consideration.
Response posted 11/21/2022


Response #2:Plan Sheets 22 has been replaced per addendum 4 issued on 12/05/2022. Please refer to addendum 4.
Response posted 12/09/2022




Inquiry #7: What item will the removal of existing Chain Link Railing be paid under?

Will the new Chain Link Railing Item 123 need to be installed at same time as removal?

Will the chain link railing Item 123 work be during day or night work?

What color vinyl clad will the chain link railing Item 123 need to be?

Inquiry submitted 11/21/2022

Response #1:Submitted for consideration.
Response posted 11/22/2022


Response #2:1. For the question regarding removal of Chain Link Railing pay item, reference is directed to Note 13 on plan sheets 207 of 231 and plan sheet 216 of 231 for limits of bridge removal. Chain link railing removal is a part of bridge removal (Portion).
2. For the question regarding Chain Link Railing Item 123 to be installed at same time as removal, please bid per current contract documents.
3. For the question regarding chain link railing Item 123 work be during day or night, please bid per current contract documents.
4. For the question regarding vinyl clad color for chain link railing Item 123, reference is directed to section 83-2.06B of the special provisions for the color of chain link fabric and chain link railing.
Response posted 12/09/2022




Inquiry #8: How is the 126 CY of Minor Concrete (i.e. trash structures) being paid for as shown on DQ-1 and DD-3?


Inquiry submitted 11/22/2022

Response #1:Submitted for consideration.
Response posted 11/22/2022


Response #2:The minor concrete for the trash structures is included in the cost of the pay items for TRASH NET (EA) each, refer to 62-16 of the Project’s Special Provisions.
Response posted 11/29/2022




Inquiry #9: The staging at Tennyson (stages 1 and 4) needs serious reconsideration by CalTrans. The idea of attempting to laydown 700+lf of k-rail each night, then demoing' the road and attempting to either put back temp AC pavement (12"+) or quickly install a median double curb (all in the course of one night shift), and then pick up the 700+lf of k-rail and fully restore the road is unattainable ... especially in the course of 6 nights. By my measurements there is enough room to laydown permanent k-rail and still maintain 4 lanes of traffic during the day .... we would then take one lane at night. Please provide new staging.
Inquiry submitted 11/30/2022

Response #1:Submitted for consideration.
Response posted 12/01/2022


Response #2:Stage plans do not require installation of the temporary barrier system for the entire length of removal and placement, of the median barrier on the same night. This can be done incrementally. Refer to note #2 on plan sheets # 77, 78, 79 of 231, and note #4 on sheets # 86, 87, & 88 of 231, “REMOVE RAISED MEDIAN FROM Sta 45+79.08 TO 53+28.40 INCREMENTALLY DURING NIGHT SHIFT WITH Temp LANE CLOSURE...” and “PLACE RAISED MEDIAN FROM Sta 45+79.08 TO 53+28.40 DURING NIGHT SHIFT INCREMENTALLY WITH Temp LANE CLOSURE...”, respectively.

Contractor may provide Value Engineering Change Proposal to the Resident Engineer during construction.

"Please bid per current contract documents."
Response posted 12/09/2022




Inquiry #10: It appears there is a 16" diameter gas main lashed on the underside of the San Leandro St bridge (directly beneath south sidewalk). This gas main will directly conflict with Contractors scaffold brackets (required for demolition and restoration of bridge barriers). Has CalTrans had any discussions with PG&E about temporary shut down/reroute of gas main?
Inquiry submitted 12/05/2022

Response #1:Submitted for consideration.
Response posted 12/05/2022


Response #2:PG&E gas main is to be protected in-place. Please bid per current contract documents.
Response posted 12/09/2022




Inquiry #11: Has the below inquiry been addressed?

Inquiry #7: What item will the removal of existing Chain Link Railing be paid under?

Will the new Chain Link Railing Item 123 need to be installed at same time as removal?

Will the chain link railing Item 123 work be during day or night work?

What color vinyl clad will the chain link railing Item 123 need to be?
Inquiry submitted 11/21/2022

Response #1:Submitted for consideration.
Response posted 11/22/2022

Inquiry submitted 12/06/2022

Response #1:Submitted for consideration.
Response posted 12/08/2022


Response #2:Please see responses to Inquiry #7
Response posted 12/09/2022




Inquiry #12: Following up on Inquiry #9 ... in addition the Temporary Decking needs to be installed within this 6 night shifts ... this adds significant more work ... and adds to the massive concern that the work at Tennyson median is not constructable as currently designed/staged.
Inquiry submitted 12/07/2022

Response #1:Submitted for consideration.
Response posted 12/08/2022


Response #2:Please refer to response to inquiry # 9.
Response posted 12/09/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.