Viewing inquiries for 05-1E0104

Submit new inquiry for this project


Inquiry #1: The pumps for the EQ Tank and the Water Tank have design points listed, but the type of pump wanted is not very clear in the specifications. Please clarify the intended type of pumps wanted for the EQ Tank and the Water Tank.
Inquiry submitted 09/20/2019

Response #1:Submitted for consideration.
Response posted 09/20/2019


Response #2:For equalization tank, please refer to submersible turbine pumps in section 221329 Sanitary Sewerage Pumps. For water tank, please refer to booster pump in section 99-02666 Water Supply System.

Response posted 09/23/2019




Inquiry #2: Reading the specifications for this project we have found that the control system -and ancillary components- are specified to only one supplier. This specification requires a single supplier for pump controllers (PLC's), the field instrumentation, (such as flow meters etc,) for fiber optic cables, and the cloud based monitoring system. This seems to be contrary to California Public Contracting Code, (PCC 3400) for specifying equipment which limits the ability for other manufacturers to compete for state contracts. Please advise if substitution for these single source products can be submitted which will provide the same functionality for the controllers, instrumentation, communications, and monitoring, as the sole source manufacturer?
Inquiry submitted 09/26/2019

Response #1:Bid per current contract documents.
Response posted 09/29/2019




Inquiry #3: - Please indicate what permits will be required from Cal Trans for the Bore and Jack. What type of insurance with the Bore and Jack contractor be required to provide.
- Please extend the Bid date by 2 weeks. Additional time is needed to obtain subcontractor and material quotes
- Are there requirements to provide plumbing fixtures in either of the rest rooms or in the new crew buildings
- What is the plant maintenance requirements after the 260 days to complete the work.
- Please provide the finish elevation and the invert of the influent line for each lift station

Inquiry submitted 09/30/2019

Response #1:Your inquiry has been submitted for review
Response posted 10/02/2019


Response #2:1a.> For crossover piping underneath freeway, there is no permit required. Contractor must comply with the requirements in Section 330523.13 - UTILITY HORIZONTAL DIRECTIONAL DRILLING of the Special Provisions.

1b> Refer to Section 7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC of the Standard Specifications.

2> An extension to the bid opening will not be considered at this time. Please bid per the current contract documents.

3> Plumbing fixtures are required in the Southbound crew building. Please bid per the current contract documents.

4> There is no plant maintenance after 260 days. Per page 1 of the Special Provisions. Please bid per the current contract documents.

5> Refer to plan sheets 198 (SS-11) and 199 (SS-12).



Response posted 10/02/2019




Inquiry #4: The project plans page ECL-1, Seed Mix states the seed is per pound per 1,000 SF. This is excessive and the seed cost is extremely expensive. Please clarify if it should be pounds per acre.
Inquiry submitted 10/02/2019

Response #1:Your inquiry has been submitted for review
Response posted 10/02/2019


Response #2:Refer to Addendum No. 2, dated October 10, 2019.
Response posted 10/10/2019


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.