Inquiry #1: On two previous rumble strip contracts in District 5 there were items for "Fog Seal", to be placed on the newly ground rumble strip. This project does not have an item for fog seal. Is fog sealing of the new rumble strip NOT required on this contract?
Also; There are 2 items for Traffic Tape (Warranty), items 29 & 30; while on the plans there are no quantities for these tape items, everything is called out as Thermoplastic (Enhanced Wet Night Viibility). Could you please clarify what it is that you want (tape, or thermoplastic) for these two items.
Thank you.

Inquiry submitted 10/12/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 10/13/2022


Response #2:
Response posted 10/13/2022


Response #3:Fog Seal Inquiry: Attention is directed to section 9-1.03, "Payment Scope" of the Standard Specifications.

Stipe inquiry: Attention is directed to Addendum No. 2, dated October 24, 2022.

Please place you bid in accordance with the current contract documents.
Response posted 10/24/2022




Inquiry #2: The existing pavement at locations 4-6 is distressed and raveling. In some locations large portions of the top most layer are gone, exposing lower lifts and this is especially true at pavement joints. If rumble strip layout encounters 'potholes' or failed areas, will the State consider any patching or repairs extra work?
Inquiry submitted 10/18/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 10/19/2022


Response #2:Attention is directed to 1-1.01, "GENERAL" of the Standard Specifications. After Contract approval, submit documents and direct questions to the Engineer. Place you bids in accordance to the current contract documents.
Response posted 11/07/2022




Inquiry #3: In regard to the "Traffic Tape" items; The Tape Manufacturer will not warranty tape that is placed in, or on rumble strip. It appears that Caltrans originaly planned on having the yellow skip details (Details 6 & 19) on location 2a placed in tape! That will not work. The white skip lines are fine, but these yellow lines are on newly cut rumble strip.
Please advise so that all bidders are aware of these issues.
Than you

Inquiry submitted 10/18/2022

Response #1:Your inquiry has been received and is currently under review.
Response posted 10/19/2022


Response #2:Attention is directed to addendum #2 dated October 24, 2022.
Response posted 11/01/2022




Inquiry #4: Do you plan to address inquiry #3? There are valid points with the yellow tape stripe installation on a ground in rumble strip. The tape stripe will fail on a rumble strip. Please make a change prior to bid, so there is not any confusion in the bidding process.
Inquiry submitted 10/31/2022

Response #1:Attention is directed to addendum #2 dated October 24, 2022.
Response posted 11/01/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.