Inquiry #1: Traditionally, for Bonded Wearing Course projects, a Bid Item for ASPHALTIC EMULSION (BONDED WEARING COURSE) is created and paid for by the TN of liquid used and QC Tested. This existing schedule of values seems to have overlooked that bid item needed to be included. Can you review and issue an addendum with this bid item added at approximately 150 TNs or whatever the engineer determines is the appropriate quantity?

Also, I don't believe that a bid item for TACK COAT is needed due to the bonded wearing course application of the RHMA-G (BWC). The existing bid item 27 for Tack Coat should be deleted.

Inquiry submitted 03/16/2020

Response #1:Submitted for consideration.
Response posted 03/16/2020


Response #2:Please refer to Addendum No 1 dated March 26, 2020.
Response posted 03/26/2020




Inquiry #2: The existing IP Data (ProVAL) provided in section 2 of the special provisions and available for download online only has the ramps located at Birch Road and Rte 125. The balance of the ramps at Olympic, Otay Lakes and East H are missing. Please issue an addendum to address and upload the remaining ProVAL files to the Caltrans website. Bid Item 22 - Full Width Segment Correction requires that all the remaining files be reviewed in order to provide an accurate price.
Inquiry submitted 03/19/2020

Response #1:Submitted for response.
Response posted 03/19/2020


Response #2:Please refer to Addendum No 1 dated March 26, 2020.
Response posted 03/26/2020




Inquiry #3: The following Electronic Files for H Street Existing ProVAL data from addendum 1 will not allow download from the Caltrans website:
NB_1_B_ONR from WB East H Street
NB_1_B_ONR from EB East H Street
NB_2_B_ONR from EB East H Street

Please remedy

Inquiry submitted 03/27/2020

Response #1:Submitted for consideration.
Response posted 03/27/2020


Response #2:You can download all the project files now.
Response posted 03/30/2020




Inquiry #4: Please provide a traffic chart for the Eastlake Parkway Overcrossing of SR 125 location.
Inquiry submitted 04/07/2020

Response #1:Submitted for consideration.
Response posted 04/07/2020


Response #2:Please bid per the current contract documents.
Response posted 04/07/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.