Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 11-417504

Submit new inquiry for this project


Inquiry #1: On Sheet No. 38/THQ-1 under Construction Area Signs in the No. of Posts and Size column 4x10 and 4x12 are these sizes correct? Is there a Standard for these particular size wood posts?
Thank you

Inquiry submitted 03/27/2020

Response #1:Submitted for consideration.
Response posted 03/27/2020


Response #2:Please refer to Addendum No 1 dated April 10, 2020.
Response posted 04/10/2020




Inquiry #2: Following up on Question #1?

Thank you

Inquiry submitted 04/07/2020

Response #1:Your inquiry is being reviewed. Unless an addendum is issued addressing your concern, please bid per the contract bid documents.
Response posted 04/07/2020


Response #2:See bidders inquiry 1 for response.
Response posted 04/14/2020




Inquiry #3: Bid Item 66 Concrete Ditch Lining needs earthwork cut and fill per Drainage Profiles DP-3, but earthwork tablet on Summary of Quantities Q-1 does not show the earthwork quantity for the concrete ditch lining. Will this earthwork be paid under Item 25 Roadway Excavation?
Inquiry submitted 04/08/2020

Response #1:Submitted for consideration.
Response posted 04/08/2020


Response #2:Please refer to Standard Specifications section 72 Slope Protection and bid per the current contract documents.


Response posted 04/09/2020




Inquiry #4: Please clarify whether Bid Item 36 Wood Mulch should be shredded bark, gorilla hair or either of them.
Inquiry submitted 04/08/2020

Response #1:Submitted for consideration.
Response posted 04/08/2020


Response #2:Please refer to plan sheet number 46 and bid per the current contract documents.
Response posted 04/09/2020




Inquiry #5: There are approximately 34,000 SF of existing cellular confinement and class 2 AB that should be removed. Which item is this removal to be paid under?
Inquiry submitted 04/10/2020

Response #1:Submitted for consideration.
Response posted 04/10/2020


Response #2:It is paid under bid item 25 "Roadway Excavation"
Response posted 04/13/2020




Inquiry #6: What is the size for electric conduit for control and neutral conductors, 1" or 2"? IP-1 calls for 2" Elect-C for CNC, but Irrigation Quantities table on IQ-1 has 1" electrical conduit for CNC.
Inquiry submitted 04/11/2020

Response #1:Submitted for consideration.
Response posted 04/12/2020


Response #2:Please Bid per what is on the Irrigation Quantities table. 1" electrical conduit.
Response posted 04/13/2020


Response #3:Submitted for consideration.
Response posted 07/23/2020


Response #4:Submitted for consideration.
Response posted 07/30/2020


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.