Viewing inquiries for 12-0J34U4

Submit new inquiry for this project


Inquiry #1: Please provide XML file for Finished Grade NB Dyer Road 'DY Line' on ramp to NB structure approach at Edinger Ave 'ED Line' that also includes finished grade data for intermediate locations of 'PU2 Line', 'ED4 Line', and ' ED3 Line'.
Inquiry submitted 12/30/2021

Response #1:Pending
Response posted 12/30/2021


Response #2:The xml files can be found in the Project Information Handout folder
Response posted 01/04/2022




Inquiry #2: The CA High Design Manual Section 850-34 dated December 30th, 2015 warns against specifying plastic pipe in areas with a potential for fire. This project lists Alternative Pipe Culvert in the Bid Schedule. Will Caltrans still allow for plastic pipe to be used on this project?


Inquiry submitted 01/03/2022

Response #1:Pending
Response posted 01/03/2022


Response #2:Project is not located in a fire hazard; bid as you see it
Response posted 01/12/2022




Inquiry #3: The XML Files that were provided in the Project Information Handout Folder are missing proposed surface data on the NB Alignment from Dyer Road 'DY Line' on ramp to Edinger Ave 'ED Line'. The files are also missing proposed surface data for intermediate locations of 'PU2 Line', 'ED4 Line', and ' ED3 Line'. Please provide XML Files with the missing information.
Inquiry submitted 01/04/2022

Response #1:Pending
Response posted 01/04/2022


Response #2:Addendum will be issued
Response posted 01/05/2022




Inquiry #4: Reference is made to sheet 2029 of 2208, South Tustin OH (Widen) and the “Concrete Strength and Type Limits” that are shown. The legend uses “Vertical Hatching” to identify PC/PS Concrete I-Girders. However, the description used is “Structural Concrete, Bridge”. Based on the “Structural Concrete, Bridge” quantity of 347 cy as shown on sheet 2028 of 2208, this quantity appears to include the volume of the PC/PS Concrete I-Girders. Please adjust accordingly and delineate both the legend and description used within “Concrete Strength and Type Limits” similar to that which is shown on sheet 1873 of 2208, Macarthur Blvd UC (Widen). This question also applies to sheet 1899 of 2208, Dyer Road Undercrossing and the “Concrete Strength and Type Limits” that are shown.

Inquiry submitted 01/06/2022

Response #1:The concrete for the precast girders is not included in the Structural Concrete, Bridge quantity
Response posted 01/12/2022




Inquiry #5: Please confirm the Engineer's quantity for BI 191 - Welded steel Pipe Casing Bridge. Contractor's take-off includes 4 locations at Edinger Ave, which greatly exceeds the pay quantity.
Inquiry submitted 01/07/2022

Response #1:Pending
Response posted 01/12/2022


Response #2:Use a quantity of 156 ft for WELDED STEEL PIPE CASING (BRIDGE
Response posted 01/12/2022




Inquiry #6: Bid Item 14 description is "Portable Radar Speed Feedback Sign System Day" but unit of measure is 4 each. Please confirm the quantity, UOM and method of payment for this item.
Inquiry submitted 01/07/2022

Response #1:Addendum will be issued
Response posted 01/12/2022




Inquiry #7: Special Provisions Section 14-4.02C(12)(c) CONSTRUCTION prescribes locations for portable radar speed feedback systems and associated construction area signs and CMS boards, however they are not captured on any traffic handling plans or quantity sheets. Please provide traffic handling plans and quantities associated with placement of above referenced elements.
Inquiry submitted 01/07/2022

Response #1:Pending
Response posted 01/12/2022


Response #2:A Revised Standard Plan will be issued in an Addendum to accompany the specifications Section 12-4.02C(12)(c)
Response posted 01/12/2022




Inquiry #8: The Construction and Maintenance Agreement between Caltrans and SCRRA provided in the Information Handout appears to include 900 shifts of Flagging Services. Please confirm if the Contractor is responsible for paying for the cost of railroad flagging or if we are allotted these 900 shifts of flagging services.

Inquiry submitted 01/07/2022

Response #1:Agency will be responsible for the cost of the flagging services
Response posted 01/12/2022




Inquiry #9: Please provide requirements and locations associated with Bid Item 41 - Noise Monitoring. No specifications have been provided.
Inquiry submitted 01/10/2022

Response #1:Pending
Response posted 01/12/2022


Response #2:An addendum will be issued
Response posted 01/12/2022




Inquiry #10: Due to the recent surge in Covid cases which has affected 80% of our estimating department, we respectfully ask for a two-week postponement to the bid opening date.
Inquiry submitted 01/10/2022

Response #1:Pending
Response posted 01/12/2022


Response #2:Addendum will be issued
Response posted 02/01/2022




Inquiry #11: “Reference is made to the electronic files “12-0J34U4_Original_Ground_Data.dgn”, “12-0J34U4_Original_Ground_Survey_Caltrans.dgn”, “12-0J34U4_Original_Ground_Survey_Consultant.dgn” and Plan topo reflecting the existing surface, all issued as part of the project plans and reference documents. Upon running the earthwork calculations with the given data, Contractor take-off quantities for Roadway Excavation and Import Borrow do not match the quantities shown on the quantity plan sheets (sheet Q-33/sheet No 1146). In addition, quantities vary depending on which topography file is utilized. Please confirm which file/data should be used for existing surface in order to compute all the earthwork quantities.”
Inquiry submitted 01/10/2022

Response #1:Pending
Response posted 01/12/2022


Response #2:12-0J34U4_Original_Ground_Data.dgn: is for information only
12-0J34U4_Original_Ground_Survey_Caltrans.dgn: was used for earthwork calculation within pavement limits
12-0J34U4_Original_Ground_Survey_Consultant.dgn: was used for earthwork calculations outside the pavement limits

Response posted 01/13/2022




Inquiry #12: The box culvert in Drainage System 15, a Double 10 x 9, has a quantity listed on Sheet DQ – 30 of 6,402.4 CY. The box is shown on Sheet DP – 6 with a length of 106.53 LF. The table on Caltrans Standard Drawing D – 81 lists a quantity of 60.1 CF / LF, for a total of 237 CY. Please confirm the pay quantity for this location.
Inquiry submitted 01/11/2022

Response #1:Pending
Response posted 01/12/2022


Response #2:Please bid as you see it
Response posted 01/13/2022




Inquiry #13: The box culvert in Drainage System 108, a Single 6 x 3, has a quantity listed on Sheet DQ – 150 of 262 CY. The box is shown on Sheet DP – 39 with a length of 21 LF. The table on Caltrans Standard Drawing D – 80 lists a quantity of 13.1 CF / LF, for a total of 10.2 CY. Please confirm the pay quantity for this location.
Inquiry submitted 01/11/2022

Response #1:Pending
Response posted 01/12/2022


Response #2:
Response posted 01/13/2022


Response #3:An addendum will be issued
Response posted 01/13/2022




Inquiry #14: Lane Closure Charts G1 and G2 have time slots for both hour "00" and "24" which are both midnight. Info is conflicting for "00" and"24". Please advise.
Inquiry submitted 01/13/2022

Response #1:Pending
Response posted 01/13/2022


Response #2:For LCC G1 and G2, please use the “24” column for the midnight closure requirements.
Response posted 01/13/2022




Inquiry #15: Please provide as-built drawing for existing retaining walls in order for the Contractor to assess conflicts with new retaining walls and required excavation and shoring for removals.
Inquiry submitted 01/13/2022

Response #1:Pending
Response posted 01/13/2022


Response #2:Bid per the plans and current contract bid documents
Response posted 01/19/2022




Inquiry #16: E-2 through E-17 Removing Lighting Systems only shows note annotation 24 through out the drawings with the exception of a couple RC notes remove contractor. Can you please confirm or clarify what is getting removed and what existing equipment is to remain.
Inquiry submitted 01/17/2022

Response #1:Pending
Response posted 01/18/2022


Response #2:Bid per the plans and current contract bid documents
Response posted 01/19/2022




Inquiry #17: Special Provisions Section 14-6.03A states that within Species Protection Area 2, the Contractor shall install temporary exclusion measures or devices and alternative roosting habitat. Please confirm method of payment for this work.
Inquiry submitted 01/18/2022

Response #1:Pending
Response posted 01/18/2022


Response #2:Temporary exclusion measures or devices and alternative roosting habitat will be paid for as extra work
Response posted 01/24/2022




Inquiry #18: Some recent Caltrans projects have eliminated the sealing of the contraction joints in new Concrete Pavement. We will assume that the majority of the contraction joints in the JPCP will not be widened and sealed on this project and that Bid Item 91 – Joint Seal (Silicone) – 140 LF is only for the minimal locations as shown on the construction detail plan sheets. If it is the intent to widen and seal all contraction joints in the JPCP, please add a bid item for this work that will define whether the seal is to be Asphalt Rubber, Silicone, or Preformed Compression as shown on standard plan P20.
Inquiry submitted 01/18/2022

Response #1:Pending
Response posted 01/18/2022


Response #2:Please bid per plans
Response posted 01/26/2022




Inquiry #19: Please define limits and verify quantities for Bid Item 122, Clean Expansion Joints, at Edinger Ave UC and South Tustin OH.
Inquiry submitted 01/19/2022

Response #1:Pending
Response posted 01/19/2022


Response #2:Your inquiry is being reviewed. Unless an addendum is issued addressing your concern, please bid per the current contract documents
Response posted 02/16/2022




Inquiry #20: E-118 through E-125 Removing Ramp Metering Systems does not show any placement of removal notes through out the drawings. Can you please confirm or clarify what is getting removed and what existing equipment is to remain.
Inquiry submitted 01/19/2022

Response #1:Pending
Response posted 01/19/2022


Response #2:Notes 2 and 3 on the plan sheets provide the direction regarding removals and abandoning
Response posted 01/24/2022




Inquiry #21: Sheet C-56, C-57 and C-59 call out type B1-6 curb around the stamped concrete median on Dyer Rd but the quantity sheets quantify this as type B1-B curb. Please confirm which curb should be utilized.
Inquiry submitted 01/21/2022

Response #1:Pending
Response posted 01/21/2022


Response #2:Bid per Construction Detail Sheets
Response posted 01/26/2022




Inquiry #22: Drainage quantity sheet DQ-148 calls out 151 cy of Minor Concrete (Miscellaneous Construction) for DS107g. Please confirm this quantity reflects the walkway only, shown on sheets DD-23 and DD-24.
Inquiry submitted 01/21/2022

Response #1:Pending
Response posted 01/21/2022


Response #2:Bid as you see. Confirmed that the 151 cy of Minor Concrete (Miscellaneous Construction) on DQ-148 is for the walkway only
Response posted 01/24/2022




Inquiry #23: Please confirm walls A-H shown on sheet DD-32 and DD-33 are included in BI 114 - Structural Concrete, Lane Channel.
Inquiry submitted 01/21/2022

Response #1:Pending
Response posted 01/21/2022


Response #2:Bid as you see. - BI 114 - Structural Concrete, Lane Channel includes walls A-H are on sheets DD-32 and 33
Response posted 01/24/2022




Inquiry #24: Hello:

On page 1297 of the project drawings, SW1-3 "Sound Wall Details", Note #1 at the top, calls out for the CMU block and color to match exiting sound walls nearby. Going NB on the 55 from Willow Creek On-Ramp to the 5 SB Connector, the existing wall sound wall in the area is the following:

- 8x6x16 slumpstone (light tan color) (75%) - (field)
- 8x6x16 slumpstone (tan color) (25%) - (field)
- 8x8x16 4Score-Split-Face-2sides (dark tan color) (2-courses on top of wall)

Detail "A" of the plan sheet calls out all the units to be 8x8x16, but slumpstone is only available in 8x6x16 size. Please clarify if we are to match the slumpstone as I have listed for SW#514 and RW#506.

Thank you.



Inquiry submitted 01/21/2022

Response #1:Pending
Response posted 01/21/2022


Response #2:Addendum will be issued
Response posted 01/26/2022




Inquiry #25: Hello:

On sheet numbers 2168 & 2176 of the project plans, for RW#506, the CMU on retaining wall is shown with raked "cuts" required at the bottom & possibly at the top of the CMU wall to keep the elevation plumb, while the elrctrolier and other items are perpendicular.

This custom cutting for 550 L.F. is an expensive operation, please confirm this is the state's intent. Thank you.


Inquiry submitted 01/21/2022

Response #1:Pending
Response posted 01/24/2022


Response #2:Your inquiry is being reviewed. Unless an addendum is issued addressing your concern, please bid per the current contract documents
Response posted 02/16/2022




Inquiry #26: Reference is made to the quantities for Retaining Wall No. 355 as shown on sheet 1147 of 2208. What is Architectural Treatment & where is it on Retaining Wall No. 355? All surface treatment appears to be Fractured Rib.

Inquiry submitted 01/25/2022

Response #1:Pending
Response posted 01/25/2022


Response #2:Refer to Addendum No. 3, dated February 9, 2022. Retaining wall plans have been updated to include architectural details.


Response posted 01/26/2022




Inquiry #27: Where is the Fractured Rib Texture that is shown on various concrete barrier rails (for example, see p. 1162 of 2208) paid for? If it is to be paid for in Bid Item 119, please adjust Quantity and Unit of Measure.
Inquiry submitted 01/25/2022

Response #1:Pending
Response posted 01/25/2022


Response #2:Please bid as you see it
Response posted 01/26/2022




Inquiry #28: Retaining Wall #355 has am item "Fractured Rib Texture" as well as an item "Architectural Treatment". Please indicate where these two items are defined; there are multiple call outs for the Fractured Rib but none found for the Architectural Treatment. Clarification on this matter is greatly appreciated.
Inquiry submitted 01/25/2022

Response #1:Pending
Response posted 01/25/2022


Response #2:Refer to Addendum No. 3 dated February 9, 2022. Retaining wall plans have been updated to include architectural details
Response posted 01/26/2022




Inquiry #29: Hello:

In regards to our previous question, INQUIRY #25, if the state is looking for (2) courses of 4ScoredSplitface-2Sides to top off the CMU sound wall on RW#506, while also having raked cuts on both the bottom and top of wall, the aesthetics of 4Score CMU is not going to look right.

There will be small slices and slivers of 4score cut as the slope changes. Which will impact the look of the 4score aesthetics, and also possibly the designer's intention. We recommend building the CMU wall to follow the grade/top of retaining wall. And then making up the differences at expansions and or electroliers with 2"+ cuts that will never be seen. You would have a more uniform looking sound wall with out the need of cuts and slivers of 4score at the top.

If needed please reach out to us to discuss and/or explain. Thank you.


Inquiry submitted 01/25/2022

Response #1:Pending
Response posted 01/25/2022


Response #2:Reference plan sheet 2195 of 2208, RW 506 Details No. 2. CMU block for sound wall is split face both sides. Please bid per current contract documents. No additional information will be provided.
Response posted 01/27/2022




Inquiry #30: There are a couple existing structural sections on plan sheet X-17 that are shown in the typical sections but not given a detailed breakdown on X-1. Please provide existing structural section details for Existing Sections BR, BT, and CE.
Inquiry submitted 01/25/2022

Response #1:Pending
Response posted 01/25/2022


Response #2:Addendum will be issued
Response posted 02/04/2022




Inquiry #31: Per Special Provision section 15-1.03C salvaged material is to be hauled and stockpiled at the Caltrans Electrical Maintenance Yard. Is this the location we are supposed to haul bid Item 298 “Salvage Concrete Barrier (Type K)? Please confirm if this is the location and if it will be available to haul in K-Rail at night?
Inquiry submitted 01/25/2022

Response #1:Pending
Response posted 01/25/2022


Response #2:Addendum will be issued
Response posted 02/04/2022




Inquiry #32: Please review the quantities for Driven pile items #96 and #98 as they appear to be less than that which would be required to complete the work.
Inquiry submitted 01/27/2022

Response #1:Pending
Response posted 01/27/2022


Response #2:Your inquiry is being reviewed. Unless an addendum is issued addressing your concern, please bid per the current contract documents
Response posted 02/16/2022




Inquiry #33: Project plan sheet 223 (C-120), note 2, states to apply a concrete stain to the architectural treatment. What color is the concrete stain? Are the images all stained the same color? Please provide additional details.
Inquiry submitted 01/28/2022

Response #1:Pending
Response posted 01/28/2022


Response #2:Addendum will be issued
Response posted 01/28/2022




Inquiry #34: Refer to the electrical plans. There are several instances where the temporary plans indicate certain installations to be installed in the temporary stage for the final and permanent use, but the permanent plans indicate a different type of material type or size to be installed from what was referenced in temporary plans. Please clarify which one is the prevailing installation.
Inquiry submitted 01/31/2022

Response #1:Pending
Response posted 01/31/2022


Response #2:Please bid as you see it
Response posted 02/01/2022




Inquiry #35: Refer to plan sheet 1488 as typical. We have found several conflicting information on plan sheets where existing and new is unclear. The plan sheet has a note stating all conduit is new unless otherwise noted on the schedule. Yet the plan drawings show them as existing and not new per the schedule. Please clarify.
Inquiry submitted 02/01/2022

Response #1:Pending
Response posted 02/01/2022


Response #2:Please bid as you see it
Response posted 02/01/2022




Inquiry #36: Can you please let the bidders know if the bid date is going to be extended?
Inquiry submitted 02/01/2022

Response #1:Pending
Response posted 02/01/2022


Response #2:Addendum will be issued
Response posted 02/01/2022




Inquiry #37: Earthwork quantities are shown in the earthwork table on plan sheet 1146. Per this table there are 343,474 c.y. of roadway excavation, 87,062 c.y. of embankment and 89,237 c.y. of imported borrow. If the embankment is subtracted from the roadway excavation leaves a surplus of 256,412 c.y. of excavated material. Why is there a pay item for import borrow when there is a surplus of roadway excavation?
Inquiry submitted 02/01/2022

Response #1:Pending
Response posted 02/01/2022


Response #2:Please bid per contract documents
Response posted 02/01/2022




Inquiry #38: Special Provisions Section 19-2.03B states " Dispose of surplus material. Ensure enough material is available to complete the embankments before disposing of it." Special Provisions Section 19-7.02C states "Imported borrow placed within 4 feet of the finished grade must have an R-value of at least 40 and a Plasticity Index less than 12 percent." Based on topography and new structural sections, this project is an export project. However, based on Caltrans bid quantities, it appears that the Contractor is expected to excavate a minimum of 4' from finished grade in paved areas (even where structural sections are less) in order to place imported borrow material with the specified R-Value. Overexcavation is specifically shown in project plans at retaining wall footings, box culverts and Lane Channel, however no overexcavation is specified in the roadway section. Please confirm that it is Caltrans’ intent to overexcavate beneath the structural section in order to place R-Value 40 material within 4’ of finished grade.
Inquiry submitted 02/01/2022

Response #1:Pending
Response posted 02/01/2022


Response #2:Please bid per contract documents
Response posted 02/01/2022




Inquiry #39: 1. Will Caltrans accept GT-BBS Configuration in place of lead-acid based system specified on this project?
ZincBlue2 BBS system to fulfill the BBS requirements for this project using the Caltrans GT-BBS configuration.

2. If GT-BBS Configuration is acceptable would Caltrans issued an addendum deleting the required Nema enclosure?

3. If Caltrans intent is to stay with lead-acid base system, would it possible that Caltrans can provide product information of State furnished components of battery backup system, in order to provide the correct batteries that are capable with those components. Per Caltrans QPL there are (4) Manufactures to choose from.

Inquiry submitted 02/01/2022

Response #1:Pending
Response posted 02/01/2022


Response #2:Please refer to section 86 of the project specifications
Response posted 02/04/2022




Inquiry #40: Does the response to inquiry 36 mean the bid date is going to be extended?
Inquiry submitted 02/02/2022

Response #1:Addendum will be issued to postpone the date
Response posted 02/02/2022




Inquiry #41: Inquiries 37 and 38 relate to issues with the earthwork quantities, in particular why is there an item for import borrow when there is a surplus of roadway excavation. The State's response for both inquiries is to bid per contract documents. Two separate contractors are confused on this issue and would like a meaningful response. The State should review Section 19-7.01, Payment of the Standard Specifications, this section details how import borrow is to be calculated and paid for.
Inquiry submitted 02/02/2022

Response #1:Pending
Response posted 02/02/2022


Response #2:Addendum will be issued
Response posted 02/08/2022




Inquiry #42: Good morning. The permanent striping items need to be revised to reflect the different striping patterns, and line widths. that goes for the thermoplastic traffic striping , and the tape. if there is a large increase in quantity for a 8" stripe for example the current item pricing wont reflect the increase in cost to the striping contractor thank you!
Inquiry submitted 02/03/2022

Response #1:Pending
Response posted 02/03/2022


Response #2:Please bid per contract documents
Response posted 02/04/2022




Inquiry #43: At the South Tustin OH (Widen), please confirm that the "Pier Protection at Bent 3" wall is paid for in the Structure Concrete, Bridge item and that the volume has been accounted for in that item.
Inquiry submitted 02/03/2022

Response #1:Pending
Response posted 02/03/2022


Response #2:Your inquiry is being reviewed. Unless an addendum is issued addressing your concern, please bid per the current contract documents
Response posted 02/16/2022




Inquiry #44: Based on the response to inquiry number 40, an addendum is coming out with a new bid date. Can you tell us when this addendum will be coming out and what the new bid date will be?
Inquiry submitted 02/03/2022

Response #1:Pending
Response posted 02/03/2022


Response #2:Addendum #3 will be issued February 9th with a new Bid Opening of March 3rd
Response posted 02/04/2022




Inquiry #45: Reference special provisions, page 155, which lists "Vibration Monitoring" as a condition at MacArthur Blvd and Dyer Road. Please confirm if vibration monitoring is required on the existing structures or just at adjacent properties referenced in section 14-8.03A(2).
Inquiry submitted 02/04/2022

Response #1:Pending
Response posted 02/04/2022


Response #2:The spec section 14-8.03A(2) applies to the properties listed
Response posted 02/08/2022




Inquiry #46: Existing concrete barriers have chain link fencing mounted to the outside of the barriers. Can they state provide details on how the new chain link is to be installed in the concrete barriers type 60? Current Construction Details do not show the Concrete Barriers (type 60M/MS) as having pockets to place the fence posts. Please provide details.
Inquiry submitted 02/07/2022

Response #1:Pending
Response posted 02/07/2022


Response #2:Please refer Caltrans Standard Plans for Concrete Barrier and Chain Link Fence.
Response posted 02/08/2022




Inquiry #47: Typically, double extruded thermoplastic traffic stripe is measured as 2 traffic stripes. Contrast stripe consists of black striping on each side of a white stripe. Special Provisions Section 84-2.04 PAYMENT states that payment for contrast striping is the length measured along the line of the traffic stripe and is silent regarding thermoplastic for contrast stripe. Please confirm if Bid item 312 “Contrast Stripe Thermoplastic” is measured as a double stripe or a single stripe.
Inquiry submitted 02/09/2022

Response #1:Pending
Response posted 02/09/2022


Response #2:Bid per the plans and current contract bid documents
Response posted 02/16/2022




Inquiry #48: Bid Item 304 “Thermoplastic Traffic Stripe (Enhanced Wet Night Visibility)” and Bid Item 313 “Traffic Stripe (Warranty)” are both comprised of multiple striping details, including varying widths (6” – 8”) and various skip patterns (36-12, 17-7, 12-3, etc). Pricing for these different striping details varies greatly and bid items 304 and 313 are not final pay. In order to provide competitive pricing and the best value to Caltrans, Contractors should price each item at their respective value to generate a composite price, however we are concerned that if the quantity is increased for the most expensive striping detail but paid for at a composite unit price, we will not be fairly compensated. Please confirm method of compensation for additional striping. In addition, please consider adding bid items for the different striping details in order to fairly compensate Contractors for increases in quantities.
Inquiry submitted 02/09/2022

Response #1:Pending
Response posted 02/09/2022


Response #2:Please bid per contract documents
Response posted 02/09/2022




Inquiry #49: Response to Inquiry 5 states that the contractor shall use a quantity different than the bid quantity. This item is not final pay. Please revise pay quantity.
Inquiry submitted 02/09/2022

Response #1:Pending
Response posted 02/09/2022


Response #2:Your inquiry is being reviewed. Unless an addendum is issued addressing your concern, please bid per the current contract documents
Response posted 02/16/2022




Inquiry #50: Please clarify Notes on Sheet 665, SC-116. Note 1 refers to Sheet SCD-13 which we believe should be Sheet SCD-14. Note 3 refers to Sheet SCD-35 which believe should be Sheet SCD-40.
Inquiry submitted 02/09/2022

Response #1:Pending
Response posted 02/09/2022


Response #2:Addendum will be issued
Response posted 02/11/2022




Inquiry #51: Please clarify Note 2 on Sheet 665, SC-116 which references the construction of Drainage System 92. States that this portion of Drainage System 92 shall be constructed in Stage 2.1. This portion of Drainage System 92 in Stage 2.1 is under the active NB McFadden Off Ramp. When will this portion be constructed? Should this portion of Drainage System 92 be constructed after Traffic is moved to MF4T in Stage 2.2A?
Inquiry submitted 02/09/2022

Response #1:Pending
Response posted 02/09/2022


Response #2:Portion of Drainage System 92 can be constructed in stages where there is no traffic conflicts
Response posted 02/10/2022




Inquiry #52: Will Precast Reinforced Concrete Box Culverts be allowable as an alternative to the cast-in-place box culverts?
Inquiry submitted 02/15/2022

Response #1:Pending
Response posted 02/15/2022


Response #2:Please bid per contract documents
Response posted 02/16/2022




Inquiry #53: The quantities shown for Bid Item 175 in DQ-91 for the Drainage System 59a (31.9 CY), 59d (18.9 CY) and 59g (3.2 CY), seem to be short according to what detail 2 on sheet DD-19 and the length shown in profiles asks for, please review and/or clarify qty's mentioned above as well as the rest of what is shown Structural Backfill (Slurry Cement).

Also please clarify if for 42" Pipe Diameter and larger the wide envelope of 6" will be used on each side as requested by Detail 2 on sheet DD-19 or if 1' will be used on each side as quoted by Spec Section 19-3.03 F-Slurry Cement Backfill - if Spec Section 19-3.03 F applies QTY's will need to be adjusted.

Thanks.

Inquiry submitted 02/17/2022

Response #1:Pending
Response posted 02/17/2022


Response #2:
Response posted 02/17/2022


Response #3:Addendum will be issued
Response posted 02/22/2022




Inquiry #54: This project has 5,020LF of 60MC barrier and 9,050LF of 60MSC barrier. There are no elevations for the barrier in the plan set. Can the state provide elevations for both the high and low side of the conrete barriers in order to allow the contractor to estimate the materials and production times needed to build these bid items? These items cannot be bid without this information.
Inquiry submitted 02/17/2022

Response #1:Pending
Response posted 02/17/2022


Response #2:PDF and CADD files are provided in the Information Handout of the bid documents that shows the elevations on both sides of the barriers
Response posted 02/18/2022




Inquiry #55: Per Plan C-120 note 2 states that the architectural treatment on the barrier is to be sandblast finish with color concrete stain applied. What color is the concrete stain supposed to be?
Inquiry submitted 02/17/2022

Response #1:Pending
Response posted 02/17/2022


Response #2:Addendum #3 was issued to edit Note 2 as "All images shall be a heavy sandblast finish". Hence no concrete stain is required
Response posted 02/28/2022




Inquiry #56: Per Plan C-120, how thick is the concrete barrier architectural treatment required to be?
Inquiry submitted 02/17/2022

Response #1:Pending
Response posted 02/17/2022


Response #2:The architectural treatment on sheet C-120 is to be heavy sandblasted.
Response posted 02/18/2022




Inquiry #57: The quantities on plans Q-24 through Q-32 for Drill and Bond Dowel and Drill and Bond Tie Bar match totals required for all joints shown on plans C-109 through C-115. Is it Caltrans intent to pay for all dowels and ties bars placed by the basket method, as well as bars placed using drill and bond?
Inquiry submitted 02/17/2022

Response #1:Pending
Response posted 02/17/2022


Response #2:Dowel bars and baskets within the concrete pavement are paid for as Concrete Pavement per the Caltrans Standard Specifications section 40. Drill and Bond Dowel and Drill and Bond Tie Bar quantities were for the joints shown on plans C-109 through C-115
Response posted 02/28/2022




Inquiry #58: Section 10-1.02C(1)(a)Cost Breakdown states, “Attention is directed to "Time-Related Overhead" of these special provisions regarding compensation for time-related overhead.” However, there is no Time-Related Overhead section in the Special Provisions. Please clarify.
Inquiry submitted 02/17/2022

Response #1:Pending
Response posted 02/17/2022


Response #2:Pending
Response posted 02/18/2022


Response #3:Addendum issued
Response posted 02/28/2022




Inquiry #59: Section 7-1.02K(6)(j)(iii) contemplates unregulated earth materials containing lead and advises unregulated earth materials containing lead have been detected to a depth of 5ft, if Contractor discovers and disposes of these materials at a commercial landfill, will Owner be considered the Generator and listed as such on any manifest?
Inquiry submitted 02/17/2022

Response #1:Pending
Response posted 02/17/2022


Response #2:Disposal of these materials at a commercial landfill is not required
Response posted 02/22/2022




Inquiry #60: Bidder Inquiry #46 asked about Chain Link details for the concrete barriers. However, there is no standard plan showing how to place chain link fence in concrete barrier. Can the state list the exact standard plan they are refering to in their response? Exisiting barrier has the chain link mounted to the backside of the barrier rail. Please advise


"Response #2:Please refer Caltrans Standard Plans for Concrete Barrier and Chain Link Fence"

Inquiry submitted 02/17/2022

Response #1:Pending
Response posted 02/17/2022


Response #2:RSP B11-52 shows an example of mounting a fence into a concrete barrier
Response posted 02/18/2022




Inquiry #61: CMS Signs: Sheet 971 (SD-34) CMS Model 700C, OS10-4 & OS11-1, calls out 66" x 32' CIDH Foundations for each of the CMS Signs. Sheet 1071 (SQ-54) Lists them under the 60" CIDH as 31'. Are these foundations 60" or 66" and what Bid Item will they be paid under? Please clarify.
Inquiry submitted 02/18/2022

Response #1:Pending
Response posted 02/18/2022


Response #2:Addendum #4 will be issued to address the inquiry
Response posted 02/18/2022




Inquiry #62: We are unable to locate the details for the "Special Logo" as referenced on sheet 1872, 1895 and 1959. Please provide the details or direct us to the location of the detail in the "Roadway Plans".
Inquiry submitted 02/22/2022

Response #1:Pending
Response posted 02/22/2022


Response #2:" Special Logo" is a circular logo shown on sheet 974 (SD-37). It is the City of Santa Ana's seal and the logo details will be coordinated with the City during construction".
Response posted 02/28/2022




Inquiry #63: Please review the volume quantity for Item 114, "Structural Concrete, Lane Channel" as it appears to be less than needed to complete the work.
Inquiry submitted 02/23/2022

Response #1:Pending
Response posted 02/23/2022


Response #2:Please bid per plans
Response posted 02/24/2022




Inquiry #64: With reference to bidder's question #56; it is still unclear whether or not the initial pattern is made using a standard form-liner or if the design is strictly created using sandblast equipment. Please Clarify.
Inquiry submitted 02/23/2022

Response #1:Pending
Response posted 02/23/2022


Response #2:Bid as you see it
Response posted 02/28/2022




Inquiry #65: DS-15bp (double 10x9 RCB) appears to require existing RCB and channel removals, but those are not called out on D-3 nor the Q sheets. Please advise if there is additional removal quantities for bid items 202 and 209 for DS-15.
Inquiry submitted 02/23/2022

Response #1:Pending
Response posted 02/23/2022


Response #2:DS-15bp (double 10x9 RCB) should be quantified to be removed
Response posted 02/28/2022




Inquiry #66: Please confirm if Standard Specification 71-3.01A(4)( c) (ii) "CCTV Recording" applies to existing pipe that we will be tying into on this project.
Inquiry submitted 02/23/2022

Response #1:Pending
Response posted 02/23/2022


Response #2:Section 71 of the Standard Specification is for REHABILIATE DRAINAGE STRUCTURES
Response posted 02/24/2022




Inquiry #67: Will the Contractor be required to CCTV new storm drain?
Inquiry submitted 02/23/2022

Response #1:Pending
Response posted 02/23/2022


Response #2:CCTV for new culverts is not required
Response posted 02/24/2022




Inquiry #68: REFER TO PLAN SHEET 1660 "NON-PAVED AREAS" DETAIL AND SPEC PAGE 203. PLEASE CONFIRM THE CONTRACT ONLY REQUIRES IT APPLY TO NON-PAVED AREA INSTALLATIONS.
Inquiry submitted 02/24/2022

Response #1:Pending
Response posted 02/24/2022


Response #2:Please bid per plan
Response posted 02/28/2022




Inquiry #69: Per response 3 issued on the 22nd of Feb on inquiry 53 when will the addendum be issued?
Inquiry submitted 02/25/2022

Response #1:Pending
Response posted 02/25/2022


Response #2:Addendum will be posted today
Response posted 02/25/2022




Inquiry #70: Can you let us know if the bid date for this project is going to be pushed?
Inquiry submitted 02/25/2022

Response #1:Pending
Response posted 02/25/2022


Response #2:Addendum will be issued
Response posted 02/25/2022




Inquiry #71: In order to bid this job realisticly and the most accurate, our enginners did their own takeoff for Roadway Excavation, Embankment and Import Borrow, and compared with the quantities that you provided. As the differences in quantities are worryingly large, we would like to asky you to specify and explain what data and corresponding drawings, methods, CAD programs and formulas you used for your takeoff of the above mention items?
Inquiry submitted 02/25/2022

Response #1:Pending
Response posted 02/25/2022


Response #2:Inquiry 11 addresses the files used for earthwork calculations using end area method; Cross Sections are provided in the bid documents; and Addendum #3 provides revised Typical Cross Sections to clarify Imported Borrow
Response posted 02/28/2022




Inquiry #72: Addendum 4 just pushed the bid date to March 10 but due to previous commitments, our estimating department will be out of state for a design-build pursuit, can the bid date be moved another week or at least to Tuesday, March 15?
Inquiry submitted 02/25/2022

Response #1:Pending
Response posted 02/28/2022


Response #2:The bid opening date will be remain as March 10
Response posted 02/28/2022


Response #3:The bid opening date will be remain as March 10
Response posted 02/28/2022


Response #4:The bid opening date will be remain as March 10
Response posted 02/28/2022


Response #5:The bid opening date will be remain as March 10
Response posted 02/28/2022




Inquiry #73: Reference response to Inquiry 71 which states that revised Typical Cross Sections were issued in Addendum 3 to clarify Imported Borrow. We have not been able to locate the referenced, revised typical cross sections. Please confirm if revised sections were issued in PDF as revised X-sheets as part of Addendum 3. If so, please confirm sheet numbers.
Inquiry submitted 02/28/2022

Response #1:Pending
Response posted 02/28/2022


Response #2:Please refer to note 8 in typical section sheet X-1 of the addendum #4 for the imported borrow clarifications
Response posted 02/28/2022




Inquiry #74: Please confirm that Caltrans will be performing the settlement survey of the settlement platform devices at the Bridge Approaches.
Inquiry submitted 03/02/2022

Response #1:Pending
Response posted 03/02/2022


Response #2:Please refer to Section 19-6.03D of the Standard Specifications and contract special provisions
Response posted 03/10/2022




Inquiry #75: Can you please confirm how the traffic tape is being paid for? in the specs page 200 84-6.04 not used. Are you paying for the total distance of broken lines including the gaps?
Inquiry submitted 03/03/2022

Response #1:Pending
Response posted 03/03/2022


Response #2:The specs page 198 refers the Traffic Stripe Tape Warranty to comply with Caltrans Standard Specifications Section 84-2
Response posted 03/03/2022




Inquiry #76: For Bid Item 68 - Lightweight Fill (EPS Block), will Caltrans allow a 27 PCF, 50+ psi Lightweight Cellular Concrete material to be used as an alternate material?
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Refer to section 4-1.07B "Value Engineering Change Proposal," of the Standard Specifications. Proposals for modifications to the contract documents may be submitted to the Engineer after contract award.
Response posted 03/10/2022




Inquiry #77: Provide the pay item descriptions for bid item #70 - planting lump sum and item #73 - Irrigation lump sum to define the scope of works that shall be part of these two items.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Please see Project Specifications Section 10-1.02C(1) of Addendum #4
Response posted 03/07/2022




Inquiry #78: Refer to drainage details on sheet DD-11. Please provide a specification for biofiltration swale and biofiltration strip layers and a depth for biofiltration strip. Also, clarify the bid item that biofiltration strip and biofiltration swale costs shall be allocated to.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Please see Erosion Control Plans, and bid per plan
Response posted 03/07/2022




Inquiry #79: Refer to bid item list, items no. 71 & 72 are for 2" & 3" galvanized steel pipe (supply line on bridge). However, the 2" & 3" galvanized steel pipes are also shown on irrigation lump sum cost break down table in section 10-1.02C(1) (a) as part of item 73. Please clarify.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:The bid item # 71 & 72 (2" & 3" galvanized steel pipe (supply line on bridge)) are separate from the 2" & 3" galvanized steel pipes shown on irrigation lump sum cost break down table in section 10-1.02C(1)(a)
Response posted 03/07/2022




Inquiry #80: Refer to Irrigation plans, there are multiple locations that irrigation conduits are shown for supply pipe under gravel mulch. Clarify the size and material for the specified irrigation conduit as these are not defined by the schedule of the quantities or the other bid documents.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Irrigation conduit sizes and materials are shown on the Irrigating Plans and Quantity Sheets. Please bid per plan
Response posted 03/07/2022




Inquiry #81: Refer to irrigation removal plans sheet IR-6, IR-8, IR-11, IR-12, there are four existing controllers to be relocated and the new locations supposed to be shown on sheets, IP-5, IP-7, IP-10, IP-11 per the notes. However, the specified sheets shown new 96-station (2-wire) controllers in existing irrigation cabinets. Please clarify.
Also confirm that all related valves that previously were connected to relocated controllers to be removed and do not need to be reconnected to relocated controllers at their new locations.

Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Controller on sheet IR-6 to be removed.
Controller on sheet IR-8 to be relocated.
Controller on sheet IR-11 to be removed.
Controller on sheet IR-12 to be removed.
All new controllers to be replaced with 96 stations 2-wire controllers. All existing remote control valves to be removed

Response posted 03/08/2022




Inquiry #82: Per irrigation sprinkler schedule on sheet ISS-1, no swing joint is required for riser and pop-up sprinkler assembly. However, specification section 20-2.09B(2) and 20-2.09B(3) shows swing joint required for pop-up and riser sprinkler assembly. Please clarify.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Swing joint shall be type I per Caltrans standard plans H5"


Response posted 03/08/2022




Inquiry #83: Per irrigation sprinkler schedule on sheet ISS-1, the second symbol from the bottom " riser sprinkler assembly" indicates riser sprinkler assembly is plastic. However, type of riser and height are missing. Please clarify.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Riser sprinkler assembly shall be plastic at 12" height. Type riser shall be type IV per Caltrans standard plans H4
Response posted 03/08/2022




Inquiry #84: Refer to irrigation sprinkler schedule on sheet ISS-1, the 5th symbol from the bottom " is pop-up sprinkler assembly" with remark note no.5 precast concrete sprinkler head protector. Please provide the type of sprinkler protector shall be used.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Sprinkler protector shall be type I per Caltrans standard plans H5
Response posted 03/08/2022




Inquiry #85: Per sheet IR-2,a call-out is shown as "maintain existing irrigation system - bubbler for 6 palms. The remote control valve A-7 connects to 6 existing bubblers still remain. However, the existing controller A to be removed. Please advise if battery controller need to be installed at valve A-7 to keep this valve functional.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Please bid per plan
Response posted 03/08/2022




Inquiry #86: Refer to sheet IR-3, no symbols are shown for irrigation components removals. However, the removal call outs are supposed to be shown on this sheet since the areas are continued to sheets IR-1 and IR-4 at the match line and removal symbols are shown on those sheets. Also the new irrigation system is to be installed at the same area per sheet IP-2. Please clarify.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022




Inquiry #87: Refer to irrigation plan sheet IP-1, the symbol of conduit at "A line" at approximate station 370+ 20 is shown with a call-out for 10" CSP, 3" PVC PR 315 & 2" WSP. However, the continued symbol on sheet IP-2 has only a call-out for 3"GSP (supply line on bridge), 2" WSP. Please clarify.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:On sheet IP-2, the following applies: Piping at "A" Line, STA 370+20 shall be 10" CSP, 3" PVC PR 315, and 2" WSP. Piping at "MA" Line (Macarthur Blvd) shall 3" GSP (supply line on bridge) and 2" WSP. See bridge plans for Macarthur Blvd
Response posted 03/08/2022




Inquiry #88: Refer to sheet PP-3, there is a call-out for 6,525 CAR EDU at approximate station 373 - "A" Line NB Route 55. However, there is no symbol or limit for this type of ground cover. Please clarify.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Please bid using the 6,528 CAR EDU quantity for the infield area of the SE quadrant.
Response posted 03/08/2022




Inquiry #89: Refer to sheet PP-6 and PP-7, the area at match-line between PP-6 and PP-7, approximately located at station 110 - DY2 line supposed to show MUH RIG shrub at this area since this type of shrub is shown for the continuous area on sheet PP-7 at the match-line with no symbol or limit. Please clarify.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Please bid per the quantities shown on the bid documents
Response posted 03/08/2022




Inquiry #90: Refer to sheet PP-7, two planting areas are shown with no symbol or limit. One area is located at station 113 DY5 Line Dyer Rd and the other area is located at station 76 GR Line Grand Ave. Please advise.

Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Please bid per the quantities shown on the bid documents
Response posted 03/08/2022




Inquiry #91: Refer to sheet PP-9, provide a symbol or limit for 343 MYO PAR at station 87 ED1 Line - SB on-ramp Route 55.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Please bid per the quantities shown on the bid documents
Response posted 03/08/2022




Inquiry #92: Refer to sheet PP-11, provide a symbol or limit for 2,154 CAR EDU at station 503 A Line - NB Route 55 and 16,507 CAR EDU at station 510 A Line - NB Route 55.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Please bid per the quantities shown on the bid documents
Response posted 03/08/2022




Inquiry #93: Per plant legend on sheet PL-1, "wood mulch" shall be installed. However, per the revised standard specifications section 20-5.04B(6), "Pine needle mulch" to be installed. Clarify the type of mulch shall be used for this project.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Please bid as "wood mulch" as shown in the bid documents
Response posted 03/08/2022




Inquiry #94: Per sheet IP-2, a call-out is shown for 10'' CSP, 3'' PVC PR315, 2'' WSP crossing under existing surface at station 33 'MA' Line MacArthur Blvd. However, 10" CSP type pipe cannot be bored as required per specification. Confirm that saw-cutting and installation through the open trench will be permitted at this location. Otherwise, please advise.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:Please bid per plan
Response posted 03/08/2022




Inquiry #95: Per the revised standard specification section 20-2.01B(7), valve box covers shall be "Traffic graded plastic". Confirm if the intent was to use either concrete or cast iron cover since the suppliers have difficulties to provide a cost for the specified material. Otherwise provide a model/manufacturer for this type of cover for bidding purpose.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:The intent is to use concrete covers
Response posted 03/08/2022




Inquiry #96: Bid item #11 Type II barricades quantities shown on plan sheet THQ-4 does not match the quantities listed on THQ-5, please advise if there are additional barricade quantities for bid item 11.
Inquiry submitted 03/07/2022

Response #1:Pending
Response posted 03/07/2022


Response #2:THQ-4 quantifies the number and type of signs placed on the barricades, while THQ-5 quantifies the barricades. Each sheet quantifies a different item and therefore, would not match. Please bid per plan
Response posted 03/08/2022


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.