Viewing inquiries for 01-0H6404

Submit new inquiry for this project


Inquiry #1: There are no profiles or otherwise in the plans for Drainage Systems 34 and 35. Will these be made available or are these not being included in this project?
Inquiry submitted 10/09/2024

Response #1:(BI#1) - Your inquiry has been received and is being reviewed.
Response posted 10/09/2024


Response #2:(BI#1) - Please direct your attention to the response for BI# 2.
Response posted 10/11/2024




Inquiry #2: CORRECTION TO PREVIOUS INQUIRY: There are no profiles or otherwise in the plans for Drainage Systems 33 and 34. Will these be made available or are these not being included in this project?
Inquiry submitted 10/09/2024

Response #1:(BI#2) - Your inquiry has been received and is being reviewed.
Response posted 10/09/2024


Response #2:(BI#2) - “Location numbers of construction do not necessarily correspond to Drainage Systems. This project does not have Drainage System 33 and 34. Bid per current bid package.”
Response posted 10/10/2024




Inquiry #3: Pertaining to Drainage Systems No. 17 and No. 26: Per the plans, these locations call for 42" and 60" WSP - Trenchless Installation Method. In order to carry these out, large jacking pits will be required in order to get the WSP into and through the borehole. Currently (at each drainage system's inlet) there are two large clusters of Redwood Trees with very broad lateral root systems that would interfere with the excavation of these jacking pits. Other than the concerns of digging through the "structural root zone" and compromising the trees, there is also the safety hazard of literally pushing the trees over given the jacking forces required at each of these locations, even with a drilled backstop. Since the work cannot be done from the outlet side due to the topography, does Caltrans anticipate the contractor being allowed to remove these trees in order to complete the work? Or does Caltrans anticipate altering the alignments away from the trees in order to install the WSP?

Related to the Question Above: The "Tree Protection Plan" notes say many things including: manual grading within the root zones, prohibiting the storing of equipment within the root zones along with the usage of temporary construction mats (detailed in the erosion control pages). Does Caltrans anticipate the contractor to dig these jacking pits and install the necessary piling to support the jacking forces of these pipes (specifically No. 17 and 26 detailed above) by hand, or will there be engineer discretion when it comes to dealing with the large redwoods and their lateral root systems located adjacent to the culvert inlets?

Inquiry submitted 10/28/2024

Response #1:(BI#3) - Your inquiry has been received and is being reviewed.
Response posted 10/28/2024


Response #2:(BI#3) - Bid per current bid package.
Response posted 10/30/2024


Response #3:(BI#3) - Revised Response: Please refer to Addendum #2, special provision section 14-6.03A, and bid per contract document.
Response posted 11/12/2024




Inquiry #4: The headwall detail on page DD-4 shows the headwalls have a keyed footing but the 2023 standard plan D89A show the footing as flat on the bottom. Are the straight headwalls on this project required to have a keyed footing?
Inquiry submitted 11/11/2024

Response #1:(BI#4) - Your inquiry has been received and is being reviewed.
Response posted 11/12/2024


Response #2:(BI#4) - “See Addenda #2. Refer to Standard Plans for details associated with headwalls. The headwall detail on DD-4 is titled “HEADWALL DIMENSION FROM TOP TO FG” and gives a dimension for instances where the parapet height differs from the Standard Plans. Bid per current contract documents.”
Response posted 11/13/2024




Inquiry #5: Where are we setting 50 each crash cushions? Item 12.
Inquiry submitted 11/11/2024

Response #1:(BI#5) - Your inquiry has been received and is being reviewed.
Response posted 11/12/2024


Response #2:(BI#5) - See Addenda #2. Bid per current contract documents.
Response posted 11/13/2024


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.