Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 02-4H0704

Submit new inquiry for this project


Inquiry #1: Section "1" on Page X-1 calls out for AR Chip SAMI-R with Asphalt Rubber Binder, Asphaltic Emulsion (Flush Coat), Precoated Aggregate (Seal Coat). The bid schedule does not have bid items for the Flush Coat and per Caltrans Standard Specification Section 37-2.05 "37-2.05A General
Section 37-2.05 includes specifications for placing stress absorbing membrane interlayers (SAMI).
Comply with section 37-2.04 except a flush coat is not required.
Traffic must not be allowed on a SAMI."

Please clarify.

Inquiry submitted 10/21/2024

Response #1:(BI#1) - Your inquiry has been received and is being reviewed.
Response posted 10/21/2024




Inquiry #2: Plan sheet's C-1 through C-5 fail to identify the limits pay limits of Bid Item #86 (Minor Concrete Curb and Gutter), #87 (Minor Concrete Sidewalk), and #88 (Minor Concrete Curb Ramp). Can Caltrans please clarify where the limits are for these three items?
Inquiry submitted 11/08/2024

Response #1:(BI#2) - Your inquiry has been received and is being reviewed.
Response posted 11/08/2024




Inquiry #3: Plan sheet C-5 shows the Removal of the existing A2-6 Curb and Gutter as remove Concrete Curb, yet there is no quantity for the removal of curb at the intersection of Skyline and hwy 139 in the quantity sheets. Can Caltrans please clarify how the Removal of Curb and Gutter at the intersection of Skyline and hwy 139 is getting paid.
Inquiry submitted 11/08/2024

Response #1:(BI#3) - Your inquiry has been received and is being reviewed.
Response posted 11/08/2024




Inquiry #4: Plan Sheet 114 shows the limits for removing the existing concrete, as well as the limits for structure excavation and backfill. There is not a bid item for structure excavation or structure backfill. Can Caltrans please clarify how structure excavation and backfill is paid.
Inquiry submitted 11/08/2024

Response #1:(BI#4) - Your inquiry has been received and is being reviewed.
Response posted 11/08/2024


Response #2:(BI#4) - Structure response: Earthwork required for the installation of barrier slab concrete is included in the bid item STRUCTURAL CONCRETE, BARRIER SLAB.
Refer to the 6th paragraph of section 9-1.03 in the Standard Specifications, and list item 4 in the 2nd paragraph of Section 51-1.01A in the Standard Specifications which states that Earthwork for barrier slabs must comply with Section 19-3.

Response posted 11/14/2024




Inquiry #5: Section 37 of the Special Specifications modify's section 37-2.02B(2) and 37-2.02B(3) of the 2023 Caltrans Standard Specification's. Section 37-2.02 only applies to "CATIONIC ASPHALTIC EMULSION CHIP SEALS." Bid Item #45 and Bid Item #46 indicate that the Chip Seal on this project is a Asphalt Rubber Chip seal. Should these modifications to the Standard Specifications be applied to Section 37-2.04 "ASHPALT RUBBER BINDER CHIP SEAL" instead of section 37-2.02?
Inquiry submitted 11/20/2024

Response #1:(BI#5) - Your inquiry has been received and is being reviewed.
Response posted 11/20/2024


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.