Inquiry #1: Typically spec section 39 Asphalt Concrete will call out the following regarding any grind / paveback requirements:

"Replace the 3rd paragraph of section 39-3.04A with:
At the locations listed below, schedule cold planing activities such that the pavement is cold planed, the HMA is placed, and the area is open to traffic during the same work shift:
1. "X operations"

For locations not listed above, schedule cold planing activities such that not more than "X days" has elapsed between the time the pavement is cold planed and the time the HMA is placed. Items 2 and 3 of the last paragraph of section 39-3.04C(1) do not apply"

Please advise if there are any grind / paveback constraints'?

Inquiry submitted 04/08/2024

Response #1:(BI#1) - Your inquiry has been received and is being reviewed.
Response posted 04/08/2024


Response #2:(BI#1)-Please direct your attention to the 3rd paragraph in section 39-3.04A of the Standard Specifications. Please bid per the current contract documents.


Response posted 04/08/2024




Inquiry #2: Special provision spec section for Traffic Control System 12-4.02C(3)(k) Conventional Highway Lane Requirement Charts states:
Comply with the requirements for the conventional highway lane closures shown in the following chart:
Chart No. K1
Conventional Highway Lane Requirements
County: Sac Route/Direction: 160/NB & SB Post Mile: L1.4/L7.0
Closure limits: PM L1.4/L7.0

Chart K1 calls out a work window at night from PM 1.4/7.0 for 1 way reversing control along SR160. Is there a lane closure chart for the Antioch Bridge at approx. PM 1.3? With the current grind / pave limits at PM 1.4 on SR160, the contractor will have lane closures in place that divert traffic across the bridge in the opposite lane which would close toll booths and affect the West side of the bridge. Please advise?

Inquiry submitted 04/11/2024

Response #1:(BI#2)-Your inquiry has been received and is being reviewed.
Response posted 04/11/2024


Response #2:(BI#2)-Please refer to Addendum #1, dated April 17, 2024.


Response posted 04/17/2024




Inquiry #3: In accordance with Detail Sheet C-1, is it the intent for the contractor to actually grind 0.45' for the pavement repair, and only pave back 0.35' leaving it low by 0.10'??
Inquiry submitted 04/12/2024

Response #1:(BI#3)-Your inquiry has been received and is being reviewed.
Response posted 04/12/2024


Response #2:(BI#3)-Please direct your attention to sheet X-1. Cold planing 0.10’ to remove the 0.10’ of RHMA-O only applies to PM L1.40 through PM L4.20.

Response posted 04/17/2024




Inquiry #4: Does Cal Trans consider the current smoothness pay adjustment specification for OGFC Mill + Fill to be economically fair? There is currently not a max deduct for OGFC mill specification.

For Example, all Deducts start @ any MRI greater than 80 MRI regardless of the EXIST MRI.

If you have an EXIST MRI 300 and PAVE the MRI @ a 120 MRI , that is a 60% overall improvement.

The Deduct will be over $5,000 just for that one Segment. Was this Cal Trans intentions for this pay adjustment specification for OGFC Mill + Fill ?

Inquiry submitted 04/14/2024

Response #1:(BI#4)-Your inquiry has been received and is being reviewed.
Response posted 04/15/2024


Response #2:(BI#4)-Please bid per the current contract documents.
Response posted 04/17/2024




Inquiry #5: Addenda #2 changed bid item 20) Cold Plane AC Pavement from 89,370 sy to 71,060 sy. Please confirm this is correct as it appears from plan sheet Q-1, summary of quantities, cold plane ac pavement quantity should be 88,530 sy. Please advise?
Inquiry submitted 04/22/2024

Response #1:(BI#5) - Your inquiry has been received and is being reviewed.

Response posted 04/22/2024


Response #2: (BI#5)-Please refer to Addendum #3, dated April 22, 2024.
Response posted 04/22/2024


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.