Viewing inquiries for 03-4H0704

Submit new inquiry for this project


Inquiry #1: Why is the State requiring a bonded wearing course with an integrated spray paver for this project? It is not typical to require a bonded wearing course for a .2' thick RHMA-G structural section. What is the benefit of applying a polymer modified asphaltic emulsion under a .2' lift of 3/4" RHMA-G with an integrated spray paver vs. applying the emulsion with a distributor truck (Boot Truck) in front of a conventional paver?
The cost of using an integrated spray paver is much higher due to slower production and lack of availability.

Inquiry submitted 08/03/2023

Response #1:(BI#1)-Your inquiry has been received and is being reviewed.
Response posted 08/03/2023


Response #2:(BI#1)-Please bid per current contract documents.
Response posted 08/08/2023




Inquiry #2: Why is the State requiring a bonded wearing course with an integrated spray paver for this project? It is not typical to require a bonded wearing course for a .2' thick RHMA-G structural section. What is the benefit of applying a polymer modified asphaltic emulsion under a .2' lift of 3/4" RHMA-G with an integrated spray paver vs. applying the emulsion with a distributor truck (Boot Truck) in front of a conventional paver?
The cost of using an integrated spray paver is much higher due to slower production and lack of availability.

Inquiry submitted 08/03/2023

Response #1:(BI#2)-Your inquiry has been received and is being reviewed.
Response posted 08/04/2023


Response #2:(BI#2)-Please bid per current contract documents.
Response posted 08/08/2023




Inquiry #3: In reference to the 1.5' thick remove & replace digout locations (5,300 CY of road exc and replace with 5,300 CY of RBWC-G / HMA-A / AB), please provide traffic handling plans that include K-Rail / crash cushions along the Highway and traffic provisions that allow long-term closures and detouring for the Ramps. If these long-term stationary closures are not allowed, public safety and convenience is unnecessarily impacted and the cost for the work is significantly increased.
Inquiry submitted 08/04/2023

Response #1:(BI#3)-Your inquiry has been received and is being reviewed.
Response posted 08/04/2023


Response #2:(BI#3)-An addendum has been issued in response to this inquiry. Please see addendum #1, dated August 17, 2023.
Response posted 08/17/2023




Inquiry #4: There appears to be flowing water at DS-27 and no apparent water at DS-21 where the temporary creek diversions are to be installed. Please provide the flow rates and source of water for these two drainage systems.
Inquiry submitted 08/07/2023

Response #1:(BI#4)-Your inquiry has been received and is being reviewed.
Response posted 08/07/2023


Response #2:(BI#4) Your attention is direction to section 13-12 of Special Provisions. Please bid per current documents.
Response posted 08/18/2023




Inquiry #5: Please provide a closure chart for the WB 20 off-ramp to Mill Street.
Inquiry submitted 08/07/2023

Response #1:(BI#5)-Your inquiry has been received and is being reviewed.
Response posted 08/07/2023


Response #2:(BI#5)-An addendum has been issued in response to this inquiry. Please see addendum #1, dated August 17, 2023.
Response posted 08/17/2023




Inquiry #6: Please provide a detail for modifying gore paving per Note B on Sheet L-11 (Page 20 of 296) at the intersection of the J1 Line and R18 Line.
Inquiry submitted 08/07/2023

Response #1:(BI#6)-Your inquiry has been received and is being reviewed.
Response posted 08/07/2023


Response #2:(BI#6)-An addendum has been issued in response to this inquiry. Please see addendum #1, dated August 17, 2023.
Response posted 08/17/2023


Response #3:
Response posted 09/18/2023




Inquiry #7: Please check the bid item and summary of quantities for the ADA curb ramps. It appears that the structure concrete and minor concrete quantities do not match and may be duplicated.
Inquiry submitted 08/08/2023

Response #1:(BI#7)-Your inquiry has been received and is being reviewed.
Response posted 08/08/2023


Response #2:(BI#7)-Please bid per current contract documents.
Response posted 08/08/2023




Inquiry #8: The plan sheet summary of quantities (Q-sheets) show some irregularities between the ratio of tack to fog seal shown in the plan sheet summary of quantities. What specific areas will be fog sealed? Is the fog seal placed on the micro-milled surface or bonded wearing course? What is the spread rate?
Inquiry submitted 08/11/2023

Response #1:(BI#8)-Your inquiry has been received and is being reviewed.
Response posted 08/11/2023


Response #2:
Response posted 08/11/2023


Response #3:(BI#8)-An addendum has been issued in response to this inquiry. Please see addendum #1, dated August 17, 2023.
Response posted 08/17/2023


Response #4:
Response posted 09/18/2023




Inquiry #9: The response for inquiry #8 states the fog seal is sprayed in between cold planing and overlay operations. Shall the fog seal be applied before opening the cold planed surface to traffic or may it be applied sometime before the end of the week?
Inquiry submitted 08/11/2023

Response #1:(BI#9)-Your inquiry has been received and is being reviewed.
Response posted 08/14/2023


Response #2:(BI#9)-An addendum has been issued in response to this inquiry. Please see addendum #1, dated August 17, 2023.
Response posted 08/17/2023




Inquiry #10: Please identify all shoulder backing locations on the Layout Sheets. For example, the shoulder backing summary of quantities (Sheet Q-3) shows four separate alignments on Sheet L-1 to receive shoulder backing but the locations are not identified/noted.
Inquiry submitted 08/14/2023

Response #1:(BI#10)-Your inquiry has been received and is being reviewed.
Response posted 08/14/2023


Response #2:(BI#10)-An addendum has been issued in response to this inquiry. Please see addendum #1, dated August 17, 2023.
Response posted 08/17/2023




Inquiry #11: Please identify all trees to be removed (e.g. ditch excavation for Drainage System 32, etc.).
Inquiry submitted 08/14/2023

Response #1:(BI#11)-Your inquiry has been received and is being reviewed.
Response posted 08/14/2023


Response #2:(BI#11) Your attention is directed to section 17-2 of the Standard Specifications and section 17-2.03A of Special Provisions. Please bid per current contract documents.
Response posted 08/18/2023




Inquiry #12: It is understood that Caltrans includes all work codes associated with the bid items on this contract to identify DBE firms certified in the CUCP that could perform work on this project to help establish the 22% DBE goal. When Caltrans calculated the 22% DBE Goal for this project what work codes were identified as contributing to $4,202,000 value of potential DBE participation? What methodologies / calculations were employed to take into account the current capacity of those potential DBE’s to handle this much work in this geographic area?
Inquiry submitted 08/16/2023

Response #1:(BI#12)-Your inquiry has been received and is being reviewed.
Response posted 08/16/2023


Response #2:(BI#12)-A determination was made on what work may potentially be subbed out to DBEs. A review of all the bid items on the contract was performed and compared to DBE firms who are certified in the CUCP to perform those work items and indicated an interest to work in the district that this project is in. Nonetheless, bidders are required to select portions of work to be performed by DBEs in order to increase the likelihood that the DBE goals will be achieved. This includes, where appropriate, breaking out contract work items into economically feasible units (for example, smaller tasks or quantities), beyond those listed via these Work Codes, to facilitate DBE participation, even when the prime contractor might otherwise prefer to perform these work items with its own forces.

Please refer to the contract documents, special provisions, and Standard Specifications 2-1.12 for the DBE requirements on this contract. You may find 49 CFR Appendix A to Part 26 I. DBE Regulation on Guidance Concerning Good Faith Effort helpful.

Response posted 08/17/2023




Inquiry #13: Since this is a "Bonded Wearing Course" project, please specify which type of Asphaltic Emulsion is required for Bid Item 56 "Tack Coat".
Inquiry submitted 08/23/2023

Response #1:(BI#13)-Your inquiry has been received and is being reviewed.
Response posted 08/23/2023


Response #2:(BI#13)-An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on 09/06/2023.
Response posted 09/06/2023




Inquiry #14: THE FOLLOWING QUESTIONS PERTAIN TO THE RTE.20/BANNER LAVA CAP ROAD, CURB RAMP # 2 LOCATION, THE STRUCTURAL QUANTITIES ON SHEET Q-6, AND ITEM #108, CONCRETE BARRIER TRANSITION:

A. Plan C-2, 36 of 296, states "Exist. MBGR-Protect In-Place." This is not feasible for the Removal of Concrete Barrier or construction of the Concrete Barrier Transition (CBT). Will the Guardrail be removed?

B. Plan 5/26, 275 of 296 shows details for the CBT. Is the 32 LF Concrete Sidewalk (SW) included in this Item or paid separately?

C. What is the spacing of the #5 "L" dowels placed transversely from the CBT into the SW?

D. Section A-A indicates "Drill & Bond Dowels" horizontally into the Bridge Railing? There is no Bridge Barrier at the end of the CBT to drill into.

E. What is the spacing of the vertical #6 "Drill & Bond Dowels" shown on the Elevation and Section A-A?

F. Please review the Drill & Bond Dowels & Chemical Adhesive quantities shown on this chart. They appear to be very high for the work shown at this location.

Inquiry submitted 08/24/2023

Response #1:(BI#14)-Your inquiry has been received and is being reviewed.
Response posted 08/24/2023


Response #2:(BI#14)-
A. “Refer to Addendum #2, dated 9/6/23.”

B. “The sidewalk is paid separate using item Minor Concrete (Sidewalk).”

C. “Refer to Addendum #2, dated 9/6/23.”

D. “Refer to Addendum #2, dated 9/6/23.”

E. “Refer to Addendum #2, dated 9/6/23.”

F. “The quantities for Drill and Bond (Dowel Bar) and Drill and Bond Dowel (Chemical Adhesive) shown in the Structure Quantities table on Sheet Q-6 are for 14 locations.”

Response posted 09/06/2023




Inquiry #15: ITEM #110, REMOVE METAL RAILING:
This work is shown on 4/26, 274 of 296 at the Rte.20/Banner Lava Cap Road, Curb #2 location. There is no mention in Special Provisions Section 14-11 of potential asbestos shims in the Bridge Railing. May the Metal Railing be removed without "Asbestos" safeguards?

Inquiry submitted 08/24/2023

Response #1:(BI#15)-Your inquiry has been received and is being reviewed.
Response posted 08/24/2023


Response #2:(BI#15)-An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on 09/06/2023.
Response posted 09/06/2023




Inquiry #16: ADA Ramp on Sheet C-1 versus Sheets 272 & 273:
1. The limits of removal/replacement on Sheet C-1 do not match Sheets 272 & 273. Which is correct?
2. Sheet C-1 shows new PCC as 6 inches thick, Sheet 273 appears to show new PCC as 4" thick. Which is correct?
3. Sheet C-1 shows 6" AB under new PCC in some locations and sheet 273 does NOT show any AB under PCC. Is new AB required and what are the limits?

Inquiry submitted 08/29/2023

Response #1:(BI#16)-Your inquiry has been received and is being reviewed.

Response posted 08/30/2023


Response #2: (BI#16)-
1.“Please bid per the current contract documents.”

2.“Refer to Construction Details in Addendum #2 dated 9/6/23.”

3.“Refer to Construction Details in Addendum #2 dated 9/6/23.”


Response posted 09/06/2023




Inquiry #17: ADA Ramp on Sheet C-2 versus Sheets 274 & 275:
1. Sheet 274 shows removal of 10 inch thick PCC, but sheet C-1 only shows 6 inches of new PCC being placed back. Should the new PCC thickness match the thickness of the removal?
2. The demo limits on sheet 274 do not match the replacement limits on the same sheet.
Which is correct?

Inquiry submitted 08/29/2023

Response #1:(BI#17)-Your inquiry has been received and is being reviewed.

Response posted 08/30/2023


Response #2:(BI#17)-An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on 09/06/2023.
Response posted 09/06/2023




Inquiry #18: ADA Ramp on Sheet C-3 versus Sheets 276 & 277:
1. The limits of work shown on sheet C-3 do not match what is shown on sheet 276. Which is correct?
2. Sheet C-3 shows new PCC as 6 inches thick, sheets 276/277 show the removal and replacement of 10 inch thick PCC. Which is correct?
3. Sheet C-3 shows 6" AB under new PCC and sheet 277 does NOT show any AB under new PCC. Is new AB required and what are the limits?

Inquiry submitted 08/29/2023

Response #1:(BI#18)-Your inquiry has been received and is being reviewed.

Response posted 08/30/2023


Response #2:(BI#18)-
1.“Refer to Addendum #2 dated 9/6/23.”

2.“Refer to Construction Details in Addendum #2 dated 9/6/23.”

3.“Refer to Construction Details in Addendum #2 dated 9/6/23.”


Response posted 09/06/2023




Inquiry #19: ADA Ramp on Sheet C-4 versus Sheet 278:
1. The limits of work on Sheet C-4 do not match Sheet 278. Which is correct?
2. Sheet C-4 shows new PCC as 6 inches thick, Sheet 278 show 10 inch thick PCC removal and approximately 4 inch thick new PCC. Which is correct?
3. Sheet C-4 shows 6" AB under new PCC in some locations and sheet 278 does NOT show any AB under PCC. Is new AB required and what are the limits?

Inquiry submitted 08/29/2023

Response #1:(BI#19)-Your inquiry has been received and is being reviewed.

Response posted 08/30/2023


Response #2:(BI#19)-
1.“Please bid per the current contract documents.”

2.“Refer to Construction Details in Addendum #2 dated 9/6/23.”

3.“Refer to Construction Details in Addendum #2 dated 9/6/23.”


Response posted 09/06/2023




Inquiry #20: ADA Ramp on Sheet C-5 versus Sheets 279 & 280:
1. The limits of removal on sheet C-5 does not match sheets 279. Which is correct?
2. Sheet C-5 shows new PCC as 6 inches thick, sheet 279 shows removal of 10 inch thick PCC and sheet 280 shows appears to show new PCC as 4" thick. Which is correct?
3. Sheet C-5 shows 6" AB under new PCC in some locations and sheets 279 and 280 do NOT show any AB under PCC. Is new AB required and what are the limits?

Inquiry submitted 08/29/2023

Response #1:(BI#20)-Your inquiry has been received and is being reviewed.

Response posted 08/30/2023


Response #2:(BI#20)-
1.“Refer to Addendum #2 dated 9/6/23.”

2.“Refer to Construction Details in Addendum #2 dated 9/6/23.”

3.“Refer to Construction Details in Addendum #2 dated 9/6/23.”

Response posted 09/06/2023




Inquiry #21: ADA Ramp on Sheet C-6 versus Sheets 281 & 282:
1. Sheet C-6 shows new PCC as 6 inches thick, sheet 281 show the removal of 10 inch thick PCC and sheet 282 appears to show new PCC as 10 inches thick. Which is correct?
2. Sheet C-6 shows 6" AB under new PCC in some locations and sheets 281 282 do NOT show any AB under PCC. Is new AB required and what are the limits?

Inquiry submitted 08/29/2023

Response #1:(BI#21)-Your inquiry has been received and is being reviewed.
Response posted 08/30/2023


Response #2:(BI#21)-An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on 09/06/2023.
Response posted 09/06/2023




Inquiry #22: ADA Ramp on Sheet C-7 versus Sheet 283:
1. The layout limits of work on Sheet C-7 does not match what is shown on sheet 283. Which is correct?

Inquiry submitted 08/29/2023

Response #1:(BI#22)-Your inquiry has been received and is being reviewed.
Response posted 08/30/2023


Response #2:(BI#22)-An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on 09/06/2023.
Response posted 09/06/2023




Inquiry #23: ADA Ramp on Sheet C-8 versus Sheets 284 & 285:
1. Sheet C-8 shows new PCC as 6 inches thick, sheet 284 shows the removal of 10 inch thick PCC and sheet 285 appears to show new PCC as 10 inches thick. Which is correct?
2. Sheet C-8 shows 6" AB under new PCC and sheet 285 does NOT show any AB under PCC. Is new AB required and what are the limits?

Inquiry submitted 08/29/2023

Response #1:(BI#23)-Your inquiry has been received and is being reviewed.
Response posted 08/30/2023


Response #2:(BI#23)-An addendum has been issued to address this bidder inquiry. Please refer to Construction Details in Addendum #2 dated 9/6/23.
Response posted 09/06/2023




Inquiry #24: ADA Ramp on Sheet C-10 versus Sheets 287 & 288:
1. The limits of work shown on sheet C-10 does not match what is shown on sheet 287. Which is correct?
2. Sheet C-10 shows new PCC as 6 inches thick with 6 inch thick AB, sheet 287 shows the removal of 12 inch thick PCC and sheet 288 appears to show new PCC as 12 inches thick. Which is correct?

Inquiry submitted 08/29/2023

Response #1:(BI#24)-Your inquiry has been received and is being reviewed.
Response posted 08/30/2023


Response #2:(BI#24)-
1.“Refer to Addendum #2 dated 9/6/23.”

2.“Refer to Construction Details in Addendum #2 dated 9/6/23.”

Response posted 09/06/2023




Inquiry #25: ADA Ramp on Sheet C-11 versus Sheets 289 & 290:
1. The limits of work shown on sheet C-11 do not match what is shown on sheet 289. Which is correct?
2. Sheet C-11 shows new PCC as 6 inches thick with 6" thick AB, sheet 289 shows removing 10 inch thick PCC and sheet 290 appears to show new PCC as 10 inches thick. Which is correct?

Inquiry submitted 08/29/2023

Response #1:(BI#25)-Your inquiry has been received and is being reviewed.
Response posted 08/30/2023


Response #2:(BI#25)-
1.“Please bid per the current contract documents.”

2.“Refer to Construction Details in Addendum #2 dated 9/6/23.”


Response posted 09/06/2023




Inquiry #26: ADA Ramp on Sheet C-12 versus Sheets 291 & 292:
1. Sheet C-12 shows new PCC as 6 inches thick with 6 inches of AB, sheet 291 shows the removal of 10 inch thick PCC and sheet 292 appears to show new PCC as 10 inches thick. Which is correct?

Inquiry submitted 08/30/2023

Response #1:(BI#26)-Your inquiry has been received and is being reviewed.
Response posted 08/30/2023


Response #2:(BI#26)-Refer to Construction Details in Addendum #2 dated 9/6/23.
Response posted 09/06/2023




Inquiry #27: ADA Ramp on Sheet C-13 versus Sheets 293 & 294:
1. Sheet C-13 shows new PCC as 6 inches thick with 6 inch thick AB, sheet 293 shows the removal of 10 inch thick PCC and sheet 294 appears to show new PCC as thicker than 10 inches. Which is correct?

Inquiry submitted 08/30/2023

Response #1:(BI#27)-Your inquiry has been received and is being reviewed.
Response posted 08/30/2023


Response #2:(BI#27)-Refer to Construction Details in Addendum #2 dated 9/6/23.
Response posted 09/06/2023




Inquiry #28: ADA Ramp on Sheet C-14 versus Sheets 295 & 296:
1. Sheet C-14 shows new PCC as 6 inches thick with 6 inch thick AB in certain areas, sheet 295 shows the removal of 10 inch thick PCC and sheet 296 appears to show new PCC as 10 inches thick. Which is correct?

Inquiry submitted 08/30/2023

Response #1:(BI#28)-Your inquiry has been received and is being reviewed.
Response posted 08/30/2023


Response #2:(BI#28)-Refer to Construction Details in Addendum #2 dated 9/6/23.
Response posted 09/06/2023




Inquiry #29: Please confirm the following concerning Asphalt Binders on this project:
1. That Asphalt Binder Cost Index Adjustments will apply to payments for the bid items that use Asphalt Binder.
2. The specific bid item(s) that this Cost Index Adjustment(s) will apply.
3. The location of the specification section that addresses this cost index adjustment.

Inquiry submitted 08/30/2023

Response #1:(BI#29)-Your inquiry has been received and is being reviewed.
Response posted 08/30/2023


Response #2:(BI#29)-Please refer to section 9-1.07 of the 2022 Standard Specifications. Please bid per the current contract documents
Response posted 08/31/2023




Inquiry #30: Please confirm that only one 55 hour closure will be allowed per Chart No. G3 EB 20 between Sta 192+07 and Sta 211+35 and Chart No. G4 WB 20 between Sta 248+57 and Sta 255+42 and Chart No. J5 & J6 WB20 off-ramps at Brunswick Rd. And that all the remaining Digout Location outside of the above listed locations and stations will have to be completed during the allowed lane closure Chart No. G1 & G2?
Inquiry submitted 08/30/2023

Response #1:(BI#30) Your inquiry has been received and is being reviewed.
Response posted 08/30/2023


Response #2:(BI#30)-The only 55 hour closures allowed are per Chart No. G3, G4, J5 and J6. Please bid per the current contract documents.
Response posted 08/31/2023




Inquiry #31: Temporary Striping after Cold Planing and Fog Seal:
1. What temporary striping/marking is required and what specification section provides this information?
2. How is the temporary striping/marking measured for payment?
3. Under which bid item(s) is the temporary striping/marking paid for?

Inquiry submitted 09/06/2023

Response #1:(BI#31)-Your inquiry has been received and is being reviewed.
Response posted 09/06/2023


Response #2:(BI#31)-Please refer to section 12-6 of the 2022 Standard Specifications. Please bid per the current contract documents.
Response posted 09/11/2023


Response #3:(BI#31)-Addenda have been issued in response to this inquiry. Please see addendum #4, dated September 15, 2023, and addendum #5, dated September 18,2023.


Response posted 09/18/2023




Inquiry #32: Temporary Striping/Marking after Rubberized HMA-GG (Bonded Wearing Course) paving:
1. What temporary striping/marking is required and what specification section provides this information?
2. How is the temporary striping/marking measured for payment?
3. Under which bid item(s) is the temporary striping/marking paid for?

Inquiry submitted 09/06/2023

Response #1:(BI#32)-Your inquiry has been received and is being reviewed.
Response posted 09/06/2023


Response #2:(BI#32)-Please refer to section 12-6 of the 2022 Standard Specifications. Please bid per the current contract documents.
Response posted 09/11/2023




Inquiry #33: Bid Items 60 Drill and Bond (Dowel Bar) and 61 Drill and Bond Dowel (Chemical Adhesive):
1. Our understanding is that bid item 60 includes both drilling and bonding rebar dowel bar. We do not see any direction for "Chemical Adhesive" to be used in any locations. Please verify that bid item 61 is needed and where in the plans and/or specs it is required.
2. If item 61 is needed, why would item 60 also be needed? It seems that only one of the other would be needed. Please clarify.

Inquiry submitted 09/06/2023

Response #1:(BI#33)-Your inquiry has been received and is being reviewed.
Response posted 09/06/2023


Response #2:(BI#33)-An addendum has been issued in response to this inquiry. Please see addendum #4, dated September 15, 2023.
Response posted 09/15/2023




Inquiry #34: Please specify the bonded wearing course spread rate to be used for the Asphalt Emulsion (Bonded Wearing Course)? The Table in Section 39-2.05A(3)(c) of the 2022 Standard Specifications does not have a target rate for planed pavement.
Inquiry submitted 09/07/2023

Response #1:(BI#34)-Your inquiry has been received and is being reviewed.
Response posted 09/07/2023


Response #2:(BI#34)-An addendum has been issued in response to this inquiry. Please see addendum #4, dated September 15, 2023.
Response posted 09/18/2023




Inquiry #35: Addendum No. 4 replaced Note 2 on Plan Sheet 96 and 97. Note 2 previously stated that fog seal shall be applied before opening traffic to cold planed surface. Note 2 now states that temporary traffic stripe is placed on cold planed surface before opening to traffic. Is fog seal required? When is fog seal required?
Inquiry submitted 09/15/2023

Response #1:(BI#35)-Your inquiry has been received and is being reviewed.
Response posted 09/15/2023


Response #2:(BI#35)-An addendum has been issued in response to this inquiry. Please see addendum #5, dated September 18, 2023.


Response posted 09/18/2023


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.