Inquiry #1: As there is no traffic control chart provided for Winters Road, could a temporary traffic control signal be installed and used continuously for the duration of the project instead of flaggers/Automated Flagger Assistance Device (AFAD) to eliminate moving k-rail back and forth every workday?

If temporary traffic control signals are allowed, does note 1 on sheet THD-1 still apply?

Inquiry submitted 01/17/2023

Response #1:Submitted for consideration.
Response posted 01/20/2023


Response #2:The bidders should bid according to the plans and specifications. Sheet THD-1 requires traffic handling 24/7 on Winters Road.
Temporary traffic signal system is not a bid item in this contract.

Response posted 01/23/2023




Inquiry #2: Is there a typo in the specials 10-1.03 Time Constraints regarding when this project can be completed or is the intent of this project to occur starting in September 2023?
Inquiry submitted 01/21/2023

Response #1:Submitted for consideration.
Response posted 01/23/2023


Response #2:The intent of this project is to begin construction in September 2023. Construction may be allowed to begin before September 15, 2023, if approved by the Resident Engineer.
Response posted 01/25/2023




Inquiry #3: On Sheet Q-1, Embankment (N) is shown at 650 CY. Is it the State's intent that all excavation remain on site?
Inquiry submitted 01/24/2023

Response #1:Submitted for consideration.
Response posted 01/24/2023


Response #2:It is not the State's intent that all excavation remain at the site. Per Section 19, Earthwork, of the Special Provisions, dispose of the surplus material.
Response posted 01/25/2023




Inquiry #4: Per Question #3, Does the State have an idea of how much dirt they would like to stay on site / offhaul? Q-1 Summary of Quantities is misleading regarding the roadway excavation / embankment quantities being equal.
Inquiry submitted 01/27/2023

Response #1:Submitted for consideration.
Response posted 01/27/2023


Response #2:The Engineer may authorize to use a small amount of the excavated dirt to fill embankment. The quantity is unknown.
Response posted 01/30/2023


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.