Viewing inquiries for 04-155004

Submit new inquiry for this project


Inquiry #1: FYI-Caltrans to-All Bidders- How do I register for Mandatory Pre-Bid Meeting?
Inquiry submitted 05/12/2025

Response #1:Please do not use the Bidder Inquiry platform for Mandatory Pre-Bid Meeting registration; It is for inquiries related to bidding on the project contract. Register in advance of the Mandatory Pre-Bid Meeting, and no later than 1 hour before the meeting time, by sending an email with bidder information to D4.Construction.Duty.Senior@dot.ca.gov Please include the project number & "Mandatory Pre-Bid Meeting", within the subject of the email.
Response posted 05/12/2025




Inquiry #2: Is it possible to release the digital files for these plan sets?
Inquiry submitted 05/19/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025




Inquiry #3: Do the new bolts that connect the new MDCS Support Brackets to the Existing Steel Truss Bottom Chord Members utilize existing bolt holes in the Bottom Chord Members or are new bolt holes required in the Existing Steel Truss Bottom Chord Members.
Inquiry submitted 05/19/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025


Response #2:Please see Typical Details No. 1 on plan sheet 527 of 587, Typical Details No. 2 on plan sheet 528 of 587, and Typical Details No. 3 on plan sheet 529 of 587. Existing bolts are labelled “existing”. Please bid per the contract documents.
Response posted 05/22/2025




Inquiry #4: Please provide access details to the inside of the Existing Steel Truss Bottom Chord Members to allow connection of the new bolts for the MDCS Support Brackets within the Existing Steel Truss Bottom Chord Members (top and bottom sides of existing chords).
Inquiry submitted 05/19/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025




Inquiry #5: Please provide existing paint preparation and/or abatement requirements at the new MDCS Support Bracket locations
Inquiry submitted 05/19/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025


Response #2:Please refer to section 14-11.13 of the special provisions for specifications about disturbing existing paint systems
Response posted 05/22/2025




Inquiry #6: Please provide paint requirements on the faying surface between the new MDCS Support Brackets and the Existing Steel Truss Bottom Chord Members.
Inquiry submitted 05/19/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025




Inquiry #7: Is the Contractor allowed to use the existing Caltrans Access Travelers on both Carquinez Bridges?
Inquiry submitted 05/19/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025




Inquiry #8: There seems to be discrepancies between the quantities show on the Table beginning on Sheet C-1 and the line-work in the Modifying Existing Electrical Systems Layout sheets. For example; the table on C-1 indicates that Sheet E-3 has 810 LF of "Four 2-inch Fiber Optic Conduit (Trench in Pavement Method Travel Lane)" however, the notes indicated on sheet E-3 make no such reference and seem to indicate that there is only 50 LF of 3" new conduit is to be placed on that sheet. Can you please clarify?
Inquiry submitted 05/21/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/21/2025




Inquiry #9: Conduit Installation Details:

There are numerous locations of conduits shown on Drawings E-3 thru E-115 that reference the Project Notes on Drawings E-1 and E-2. Several Project Notes do not provide installation details of the conduit. I.e., is the conduit existing, is it to be installed in a new trench, is it to be directional drilled. Please provide installation details for the following Project Note Numbers: 2,21,22,23,24,39,40,57,58,75 shown on Drawings E-1 and E-2.

For example, Drawing E-61 shows conduits referencing Project Notes 2,21,23,24. These notes do not provide any conduit installation details.

Inquiry submitted 05/21/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/21/2025


Response #2:Wherever installation method is not specified, the default is trenching as per standard plans.
Response posted 06/03/2025




Inquiry #10: For Bid Item 11 MOBILE BARRIER SYSTEM, please clarify if the Daily Rate is for one system or all systems used each day.
Inquiry submitted 05/22/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025




Inquiry #11: For Bid Item 12 MOBILE BARRIER TRAILER, please clarify if the Monthly Rate is for one MBT or all MBT's used each month.
Inquiry submitted 05/22/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025




Inquiry #12: For Bid Item 8 STATIONARY IMPACT ATTENUATOR VEHICLE, please clarify if the Daily Rate is for one vehicle or all vehicles used each day.
Inquiry submitted 05/22/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025




Inquiry #13: Structure Plan Sheet 474 (80/580 EL CERRITO SEPERATION OH) shows the new MDCS attached to the bridge structure. Plans E-27 and E-28 show the same conduits as Type 77 and 74 (Trench and Directional Drill). Please clarity what method of installation is required at this location.
Inquiry submitted 05/22/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025




Inquiry #14: Given the highly variable nature of the existing pavement sections, it follows that the difficulty of trenching, potholing, and any other required excavation in pavement will also vary greatly. Can you please provide existing pavement sectional details?
Inquiry submitted 05/22/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025




Inquiry #15: Specification Section 12-3.24 MOBILE BARRIER SYSTEMS requires the use of Mobile Barrier Systems for most of the work on this project. Using Caltrans Mobile Barrier System Guidelines (dated December 2023), the estimated cost of one Mobile Barrier System is $2,000 per day. Per Section 12-3.24B, the rental cost for one Mobile Barrier Trailer is $25,000 per month. Additionally, the use of MBT’s will significantly impact production while installing the Multi Duct Conduit System trenches along the Caltrans ROW. These requirements will add substantial costs to the project. Please consider allowing the use of more typical Caltrans lane closures for this project (in particular for the new MDCS trenches).
Inquiry submitted 05/22/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025




Inquiry #16: Due to the high variability of paving section thickness and composition throughout the project area and the subsequent variable effect that it will have on all excavation activates, can you please release information on the existing paving sections?
Inquiry submitted 05/22/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025




Inquiry #17: On sheets E-3 to E-115 there are many contradicting instances where the lines and notes indicate a new length of conduit merging into an existing conduit with no notes indicating a continuation of the new conduit along the existing conduits or a method of installation were new conduits to be placed. Additionally, the provided Quantities tables contradict what is shown in the layouts.

For example: on E-9, near EB1 Line 174+75, there is a length of 137' of Note 77 (new 4-1.5" C) sweeping away from a run of notes 6 (Existing conduits, pull FO cables) & 78 (Existing, for reference only). The notes seem to imply that the 137' of note 77 is installed without continuing along with notes 6 & 78. Please clarify and/or correct what exact materials and methods are to be used.

Inquiry submitted 05/22/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025




Inquiry #18: Sheet 323 (E-34) shows conduits crossing Carlson Blvd at two locations. Please provide details of conduit installation at both crossings. I.e. trench or directional drill
Inquiry submitted 05/23/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/23/2025




Inquiry #19: The Mobile Barrier System that Caltrans is requiring is adding significant cost to this project and in the contractors view is unnecessary. Please consider removing this item and instead allowing standard lane closures in its place.
Inquiry submitted 05/23/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/23/2025


Response #2:There are no plans to remove the Mobile Barrier System at this time. Please bid per current contract documents.
Response posted 05/28/2025




Inquiry #20: Sheet 374 (E-85) shows a conduit run from Route 80 EB viaduct down to an existing cabinet (TV972) located adjacent to Dowrelio Drive at ground level. Please provide details of the conduit run down the viaduct column I.e. new conduit or existing conduit.
Inquiry submitted 05/23/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/23/2025




Inquiry #21: Addendum 2 replaced the thirteenth paragraph in the notice to bidders with a mandatory pre-bid on June 2, 2025. Do interested contractors need to request an updated Webex link from the link previously provided for May 29?
Inquiry submitted 05/23/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/23/2025


Response #2:When the Mandatory Pre-Bid Meeting date changes, the meeting link that the contractor receives when registering will also work for the new date.
Response posted 05/23/2025




Inquiry #22: Sheet 396 (E-107) shows new conduit being trenched across Route 980, please confirm this is a trench (Project Note 85) or should it be directional drill method?
Inquiry submitted 05/23/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/23/2025




Inquiry #23: Sheet 346 (E-57) shows new conduit installed with Directional Drilling Method under all EB Route 80, the median and about two lanes of WB Route 80, then continues across EB Route 80 with a detail described by Project Note No.58 on E-2. Please provide clear conduit routing details across Route 80 at Richmond Parkway.
Inquiry submitted 05/27/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/27/2025




Inquiry #24: Sheet 354 (E-65) shows new conduit crossing Pinole Valley Rd (south side of Route 80). Please confirm that this conduit is actually installed per Project Note 77 shown on E-2 (I.e. trench across Pinole Valley Road).
Inquiry submitted 05/27/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/27/2025


Response #2:Yes. Note 77 is confirmed, install conduit across Pinole Valley Road.
Response posted 05/30/2025




Inquiry #25: Sheet 358 (E-69) shows new conduit installed in a trench crossing Sycamore Ave, a railroad and Willow Ave (per Project Note 77). Table on Sheet 17 (C-2) shows 790LF of conduit "Attached to Structures" on Sheet E-69. Please confirm that the new conduit in this location is actually attached to the bridge structure (not trench) and please also provide structural details of this.
Inquiry submitted 05/27/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/27/2025




Inquiry #26: Sheet 359 (E-70) shows new conduit installed in a trench crossing Route 4 (per Project Note 77). Table on Sheet 15 (C-2) shows 545LF of conduit "Attached to Structures" on Sheet E-70. Please confirm that the new conduit in this location is actually attached to the bridge structure (not trench) and please also provide structural details of this.
Inquiry submitted 05/27/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/27/2025




Inquiry #27: Sheet 373 (E-84) shows new conduit installed in a new trench across the EB lanes of Route 80. Is this correct or should these conduits be installed with directional drill method?
Inquiry submitted 05/28/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/28/2025




Inquiry #28: Due to the absence of sufficient bore logs to determine the presence of ground water, and the design of the trenching and horizontal directional drilling details provided, we are assuming there will not be ground water present. Please confirm this is correct.
Inquiry submitted 05/28/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/28/2025




Inquiry #29: The geo technical reports have very few bore logs, can Caltrans please release additional bore logs for this project?
Inquiry submitted 05/28/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/28/2025




Inquiry #30: Sheet E-100 Calls out to Horizontal Directional Drill across 580 to a FVS110 on East Bound 580. There doesn't seem to be a Fiber vault in that area, is that are to be sawcut, jackhammer out to locate the existing conduit in the concrete overpass?
Inquiry submitted 05/28/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/28/2025




Inquiry #31: Notes 77 and 85 on Sheet E-2 describe (4) 1-1/2"C, see details on Sheet ED-23 and ED-55. Sheet ED-23 Type A detail shows a 4" steel conduit casing with (4) 1-1/4" innerducts inside of the 4" steel conduit. Is a 4" steel conduit required everywhere the Note 77 and 85 installations are shown or is PVC/HDPE conduit acceptable? Also, are we to install (4) 1-1/4" HDPE innerducts or (4) 1-1/2" HDPE innerducts inside of the 4" conduit?
Inquiry submitted 05/29/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025




Inquiry #32: Note 2 on Sheet E-1 describes a 3"C from splice vault to cabinet. Many of the Note 2 installations are associated with Note 74 on Sheet E-2, which states to install conduit by horizontal directional drilling method. Is steel conduit required for these installations or is PVC/HDPE acceptable?
Inquiry submitted 05/29/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025




Inquiry #33: Multiple Notes on Sheets E-1 and E-2 describe ethernet cables. In many instances, the distances of the ethernet cable runs exceed the 300' threshold, which is the maximum distance that they will test out at. Is fiber optic cabling required in these instances where the distance exceeds 300'?
Inquiry submitted 05/29/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025




Inquiry #34: Sheet E-4 shows existing fiber optic conduit runs, per notes 1, 78, 81, and 83. Sheet E-4 also shows what appears to be a new FOV and FSV003. Are the FOV and FSV003 new vaults? If so, please provide an installation detail showing how we are to intercept the existing fiber optic conduit runs (with existing innerducts and fiber optic cable installed inside the innerducts) and install the new FOV and FSV003. This is a typical installation that is shown on multiple plan sheets.
Inquiry submitted 05/29/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025




Inquiry #35: Sheet E-10 shows an existing fiber optic conduit run, per Notes 6 and 78. Sheet E-10 also shows new fiber optic conduit runs, per Note 77. How do the new fiber optic conduit runs with (4) 1-1/2" innerducts (Note 77) tie into the existing fiber optic conduit runs with (4) 1-1/2" innerducts (Notes 6 and 78)? Please provide an installation detail.
Inquiry submitted 05/29/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025




Inquiry #36: Notes 32, 76, 77, 85, and 88 all describe new conduit runs for the fiber optic trunk lines. These notes are shown on multiple plan sheets, but the dashed lines, which indicate the routing, do not appear to be very specific. For example, the dashed lines are shown at the edge of pavement, in lanes of traffic, in green space areas, under existing roads, crossing bridges, etc. Is it the contractors responsibility to determine the correct routing and installation methods for the fiber optic trunk line conduits or can more specific details be provided with more specific routing?
Inquiry submitted 05/29/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025




Inquiry #37: Sheet E-102 (Note 94) shows a new 4"C, containing (4) 1-1/4" innerduct, which is to be attached to the wall by using hangers/brackets/clamps. The routing of the Note 94 conduit on Sheet E-102 crosses 2 lanes of traffic, so this conduit is not able to be installed to the barrier wall. Please provide an installation detail or revised routing for the conduit.
Inquiry submitted 05/29/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025




Inquiry #38: Please provide the Caltrans standard for Ethernet cabling slack required at handholes and cabinets.
Inquiry submitted 05/29/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025




Inquiry #39: Sheet ED-23 shows a Trench in Dirt Detail, a Horizontal Boring Detail, and a Trench in Pavement Detail. The Trench in Pavement Detail references the Detail FC Type B Detail, which describes a 2" Type 3 (PVC) Schedule 80 conduit. Notes 77 and 85 on Sheet E-2 Describe (4) 1-1/2" conduits, but they also reference the Sheet ED-23 detail. Should the Trench in Pavement detail shown on ED-23 include a 4" conduit with (4) 1-1/2" innerducts or 2" Schedule 80 conduits?
Inquiry submitted 05/29/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025




Inquiry #40: Bid Item Number 390132 Hot Mix Asphalt (Type A) includes a quantity of 850 Tons. Given that every Trench in Pavement conduit installation includes a 4' wide asphalt removal (and subsequent 4' wide hot mix asphalt patch), this quantity of 850 tons does not appear to be enough to cover the entire project. Is this quantity of 850 tons related to the patching associated with the Trench in Pavement conduit installation? Or is the 4' wide asphalt removal and 4' wide patching incidental to the Modifying Existing Electrical Systems pay item?
Inquiry submitted 05/29/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025




Inquiry #41: Please provide Mandatory sign-in sheet
Inquiry submitted 05/30/2025

Response #1:The Mandatory Pre-Bid Meeting sign in sheet will be available after it takes place on Monday, 6/2.
Response posted 05/30/2025




Inquiry #42: Please provide Freeway Lane Requirement Charts for Sheets 355-558 (E-66 to E-69) in EB direction.
Please provide Freeway Lane Requirement Charts for Carquinez Bridges Sheets 375-379 (E-86 to E-90) in EB and WB directions.

Inquiry submitted 05/30/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025




Inquiry #43: Please provide Freeway Lane Requirement Charts for Sheets 355-558 (E-66 to E-69) in EB direction.
Please provide Freeway Lane Requirement Charts for Carquinez Bridges Sheets 375-379 (E-86 to E-90) in EB and WB directions.

Inquiry submitted 05/30/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025




Inquiry #44: Please provide Freeway Lane Requirement Charts for Sheets 387 to 400 (E-98 to E-111) in both directions.
Inquiry submitted 05/30/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025




Inquiry #45: E-107 calls out 85 which refers you to a trench detail. Most of the area is a freeway overpass which no excavation can happen in that area. There is also a large building against the freeway overpass. Is a portion of that work to be on the overpass in a steel casing? It also shows the trench to be crossing multiple lanes on Route 980. Please verify with more accurate details for this area.
Inquiry submitted 06/02/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025




Inquiry #46: Sheet 328 (E-39) shows new trench (Project Note 77) running between the EB 80 and Home Depot Building and Parking Lot. Please confirm exact location of new trench as it seems like there is no space for it.


Inquiry submitted 06/02/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025




Inquiry #47: Sheet 106 calls out #85 which is trench detail #23, but there is also a structural detail on page 572 Multi Duct Conduit system 27th St. UC. Which are we to follow?
Inquiry submitted 06/02/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025




Inquiry #48: Can we have the sign in from the job walk?
Inquiry submitted 06/03/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/04/2025




Inquiry #49: Sheet 386 (E-97) shows the new conduit trench crossing Route 780. The trench location when crossing Rt 780 (as shown on E-97) is located within the concrete bridge structure. Please clarify.
Inquiry submitted 06/03/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/04/2025




Inquiry #50: Sheet 299 (E-10) shows new conduit run crossing Route 80/580 (Type 2). Please confirm this will be directional drill method of installation.
Inquiry submitted 06/03/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/04/2025




Inquiry #51: Please provide a list of the Caltrans approved material suppliers for conduit materials as shown on detail sheet ED-1
Inquiry submitted 06/04/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025




Inquiry #52: An extensive estimating effort is needed for this project given it's overall length, the multiple types of underground raceway/trench sections, aboveground raceway/details for attaching to diverse concrete and steel structures, and providing traffic control for all the various work in a very complex urban transportation corridor.
The project's pricipal pay items, such as electrical systems, technology refresh, and traffic management, are lump sum items which means the bidders must pay much greater attention to the breadth and acccuracy of their material takeoffs (including fully vetting the table of quantities provided in the drawings) than would be necessary for unit price items, since the quantity risk for the lump sum items lies with the contractor.
Furthermore, another major Caltrans project similar in nature to this one has been postponed and is now bidding only one week prior to this project's bid date. The amount of estimating/bidding work crammed into such a short period of time is overloading not only our own estimators but those of our subcontractors and suppliers.
Considering all the above, we request that the bid opening date for this project be postponed by three weeks to allow bidders ample time to complete and review their estimates.

Inquiry submitted 06/04/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025


Response #2:The bid open is expected to be delayed at least two weeks. Official notice of bid open delay is provided through addendum only.
Response posted 06/05/2025




Inquiry #53: On Drawing E-5, the vault located at station “EB1” 123+50 lists fiber numbers 77 and 17. According to Drawing E-1 notes and ED-55, this conduit run is identified as the Bundle 3 fiber trunk line, consisting of 2 - 288 SM fiber optic cables, continuing along Route 880 from this vault. However, the electrical plans and cable assignment tables indicate that the Bundle 3 fiber trunk line is routed along Route 80/580 to the Route 80/780 junction, not along Route 880. Please confirm the correct bundle designation and routing of the fiber trunk line along Route 880.
Inquiry submitted 06/04/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025




Inquiry #54: Electrical Drawing E-106, north of station “FR” 96+50, denotes number 77 to a non-existing conduit run. There seems to be a drawing line missing at this location. Please clarify the intended connection point at this location.
Inquiry submitted 06/04/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025




Inquiry #55: 3. Fiber Optic Network Layout Drawing ED-15 shows the trunk line fiber running from HUB 1 to Vault SV119, the hub located at the office. However, based on the stationing of the laterals on ED-15 and the routing shown in the electrical plans, the fiber appears to terminate at DT408. Please clarify the intended routing from DT408 at station “FL” 36+00 to Vault SV119 at office on 22nd Street Oakland.
Inquiry submitted 06/04/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025




Inquiry #56: DT310, TV106, DT615, and E33V8 are shown on the fiber layout Drawing ED-4 but do not appear on the corresponding electrical plans. Please clarify the status and intended inclusion of DT310, TV106, DT615, and E33V8 on the electrical plans.
Inquiry submitted 06/04/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025




Inquiry #57: On the Fiber Optic Network Layout, CM604 appears twice on Drawing ED-7, and CM606 on Drawing ED-8 is a repeat of CM606 from ED-7. Please provide clarification on the correct labeling and placement of CM604 and CM606.
Inquiry submitted 06/04/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025




Inquiry #58: Upon review of both the Caltrans 2023 Standard Specifications and the Job Special Provisions, we cannot find any Equipment specifications or part numbers for the following:
a. Controller Server
b. Media Converter
c. Aggregate Ethernet Switch
d. Video Server
e. Computer Cabinet
f. FDU Unit

Inquiry submitted 06/04/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025




Inquiry #59: Section 13 Water Pollution Control states this project's risk level is 3. Please provide Caltrans' preliminary Risk Assessment so we can compare our calculations. We believe this project should be a Linear Underground/Overhead Project (LUP) Type 1 or 2.
Inquiry submitted 06/05/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/06/2025




Inquiry #60: I am trying to square up the cold plane, tack, and asphalt quantities associated with Bid Items 53, 54, and 55.

Summary of Quantities Sheet Q-1 points bidders to sheets C-1 to C-3 for these items.

Sheets C-1 to C-3 list tens of thousands of lineal feet of trenching in pavement.

The asphalt backfill shown on the ED plan sheets show a 4' wide pavement section.

350 SQYD of cold plane makes no sense when considering there are tens of thousands of lineal feet of trenching in pavement travel lanes. It is important to get these quantities as accurate as possible when bidders must also concern themselves with things like the 15% DBE goal.

Please confirm quantities for bit items 53, 54, and 55.

Inquiry submitted 06/06/2025

Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/06/2025


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.