Viewing inquiries for 04-1Q5814

Submit new inquiry for this project


Inquiry #1: FYI. Caltrans to All Bidders - How do I register for Mandatory Pre-Bid Meeting?
Inquiry submitted 10/24/2023

Response #1:Please do not use the Bidder Inquiry platform for Mandatory Pre-Bid Meeting registration; it is for inquiries related to bidding on the project contract. Register in advance of the Mandatory Pre-Bid Meeting, and no later than 1 hour before the meeting time, by sending an email with bidder information to D4.Construction.Duty.Senior@dot.ca.gov Please include the project number & "Mandatory Pre-Bid Meeting", within the subject of the email.
Response posted 10/24/2023


Response #2:The following companies attended the meeting:

• BAY CITIES PAVING & GRADING INC
• DESILVA GATES
• FBD VANGUARD CONSTRUCTION
• GHILOTTI BROS INC
• GRANITE CONSTRUCTION COMPANY
• GRANITEROCK
• LINDSAY
• OC JONES & SONS INC
• O'GRADY PAVING INC
Response posted 11/14/2023


Response #3:See below for the list of those attending.

http://website.dot.ca.gov/dist4/construction/contracts/04-1Q5814/04-1Q5814_MPBM_attended.pdf
Response posted 11/14/2023




Inquiry #2: Please change the time-related overhead bid item to 1 lump sum if this intended to be a cost + time proposal.
Inquiry submitted 10/24/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 10/24/2023


Response #2:Revision to this item was provided in addendum #2, issued 11/17/2023. Please refer to the revised bid item list for this item.
Response posted 11/28/2023




Inquiry #3: Please provide left and right median profiles/elevations for 60MGC Barrier Variables.
Inquiry submitted 11/02/2023

Response #1:The inquiry has been received and submitted for consideration.

Response posted 11/02/2023


Response #2:Median profiles are not available. Bid per current plans and specs.
Response posted 11/06/2023


Response #3:Partial slope stake notes for the median barrier have been provided as part of the Supplemental Info in Addendum 2. Please bid with the new information available.
Response posted 11/20/2023




Inquiry #4: After reviewing Lane Closure Charts G3/G4, is it Caltrans intent to remove and reconstruct the median barrier over 6 - 55 hour weekend closures? If this is Caltrans intention then the charts conflict with the Traffic Handling Plans for Stages 2-7 which states that the express lane must remain open during daytime traffic. Please clarify when the barrier can be constructed?
Inquiry submitted 11/06/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/06/2023


Response #2:Plan sheets 213, 241, 249, 256, 264, 271, and 279 have been modified where appropriate in Addendum 2, posted 11/17, to address this inquiry. The 55-hour closures can be used for the construction of the median barrier.
Response posted 11/28/2023




Inquiry #5: Bid Item 25 - Treated Wood Waste has a quantity of 9,270 LB. This does not seem to be shown anywhere in the Quantity Sheets. Please provide.
Inquiry submitted 11/09/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/09/2023


Response #2:This issue was addressed in Addendum #2, issued 11/17. See the revised quantity sheets and bid item list provided in this addendum for updated quantities for Treated Wood Waste.
Response posted 11/28/2023




Inquiry #6: Spec Section 12-3.25B Materials for the movable barrier systems provides a price of "...$2,020827.20, not including sales tax. The above price will be firm for orders placed on or before 10/27/2023, provided delivery is accepted within 90 days after the order is placed."

This quote is already outdated, please provide update and consider whether 90 days for delivery is sufficient from order placement to take delivery.

Inquiry submitted 11/13/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/13/2023


Response #2:The specifications have been updated in Addendum #2, addressing this concern. Lindsay Barrier has informed Caltrans that they will be providing all prospective bidders who attended the required Pre-Bid Meeting with the updated quote. Note that their quote does not include movable barrier crash cushions, while the quote in the specs does. Also note that the new quote provided in the updated specs does not include tax, as noted.
Response posted 11/20/2023




Inquiry #7: In the PDQ sheets it calls out certain details have a contrast option. What are the options for opt 1, and opt 2?
Inquiry submitted 11/13/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/13/2023


Response #2:These options are detailed on the 2023 Standard Plans, page A20E.
Response posted 11/13/2023




Inquiry #8: Bid Item 52 call out Concrete Barrier (Type 60S) - 460 LF
Bid Item 53 calls out Concrete Barrier (Type 60S MOD) - 120 LF

The Detail Plan Sheets and Quantity Sheets do not call out any Type 60S or Type 60S MOD Barrier, however they do call out for Type 60G and Type 60G MOD for which there are no bid items. Please confirm the Type 60S and Type 60SMOD is meant to be Type 60G and Type 60G MOD.

Inquiry submitted 11/13/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/13/2023


Response #2:You are correct. Please see Addendum 2, issued 11/17 for the updated bid item list, which addresses this inquiry.
Response posted 11/20/2023




Inquiry #9: Project special provisions Section 39 shows an LA Rattler change from the Standard Specifications from 40 to 25 for Type A, RHMA-G, & RHMA-O (OGFC). This is a significant change from the standards that has not been discussed at the Caltrans/Industry Pavement Materials & Partnering Committee (PMPC). What is the rationale for this change?
Inquiry submitted 11/14/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/14/2023


Response #2:This section's specs have been modified in Addendum 2, issued 11/17. The new specs address inquiries regarding this section.
Response posted 11/20/2023




Inquiry #10: Project special provisions Section 39 says to Replace 4.0 ± 1.5 in the row for Air voids content @ Ndesign in the table in item 2 in the list in the paragraph of section 39-2.03A(4)(e)(i) with 3.5 ± 1.5. In a different location it says to Replace 4.0 ± 1.5 in the row for Air voids content @ Ndesign in the table in item 2 in the list in the paragraph of section 39-2.03A(4)(e)(i) with 5.0 ± 1.5. These are contradictory. Should the 4.0 ± 1.5 be replaced with 3.5 ± 1.5 or 5.0 ± 1.5? Please provide clarification.
Inquiry submitted 11/14/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/14/2023


Response #2:This section's specs have been modified in Addendum 2, issued 11/17. The new specs address inquiries regarding this section.
Response posted 11/20/2023




Inquiry #11: Project special provisions Section 39 says to Replace Ndesign = 4.0 in the row for Air voids content in the table in the 1st paragraph of section 39-2.03B(2) with 3.5. In a different location it says to Replace Ndesign = 4.0 in the row for Air voids content in the table in the 1st paragraph of section 39-2.03B(2) with 5.0. These are contradictory. Should the 4.0 be replaced with 3.5 or 5.0? Please provide clarification.
Inquiry submitted 11/14/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/14/2023


Response #2:This section's specs have been modified in Addendum 2, issued 11/17. The new specs address inquiries regarding this section.
Response posted 11/20/2023




Inquiry #12: Cross Sections on Typical Cross Section Sheets X-1 and X-2 show the cold plane and pave limits in Lane 1 nearest the barrier as the existing ETW, while the limits appear to be abutting the barrier on the Layout Sheets. Please clarify which is correct.
Inquiry submitted 11/15/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/15/2023


Response #2:X-1 and X-2 show the cold plane and pave limits as the saw cut line minimum 1' from the face of the barrier. The proposed sections for the cold plane and pave extend to the saw cut line. This is consistent with the Layouts. The pay quantities include this.
Response posted 11/20/2023




Inquiry #13: Typical Cross Section on Sheet X-1 shows to sawcut a minimum of 1' outside the edge of the proposed concrete barrier:

1. Is this minimum 1' slot to be removed, and if so, how is to be paid?
2. If it is to be removed, what is to go back in this slot (aphalt/concrete) after construction of the barrier, and how is it to be paid?

Please clarify and provide details.

Inquiry submitted 11/15/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/15/2023


Response #2:The 1' slot between the saw cut line and the face of the barrier is not to be removed.
Response posted 11/28/2023




Inquiry #14: It was mentioned during the Pre Bid meeting on 11/14/23 that 6 EA 55-Hour Closures (of Lane 1 in each direction) have been approved for this project because it is believed there are some items of work that cannot be completed otherwise. There is nothing mentioned in the Special Provisions or in the Project Plans what items of work those are. Please provide information regarding what the potential work is for the 55-Hour Closures.
Inquiry submitted 11/15/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/15/2023


Response #2:The (up to 6) 55-hour closures (as shown in the lane closure charts) of lane #1 in both directions may be used for concrete barrier work for Stages 2-7, but their use is not prescribed in the plans or specs and is up to your means-and-methods. These are provided as an additional resource for the contractor to construct the project, and are not required to be used.
Response posted 11/15/2023




Inquiry #15: Bid Item 0076 - Concrete Barrier (Type 60G Mod) - On Plan sheet 57 (C-28) section D-D is calling for #9 @ 8" O.C could you please confirm that this is correct and #9 rebar required in the barrier.
Inquiry submitted 11/20/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/20/2023


Response #2:The detail on C-28 is correct. #9 rebar is required in the barrier.
Response posted 11/21/2023




Inquiry #16: As an example of other locations, what is the reason for approximately 8-feet of cold plane & overlay offset from face of existing median barrier (existing barrier not shown to be removed) in both directions between Sta. 335 and 350?
Inquiry submitted 11/28/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/28/2023


Response #2:The approximately 8' offset of the cold plane and overlay from the face of the median barrier at this location ("NE1" St 335 to 350) is to avoid existing drainage and concrete pavement. Other locations with an offset throughout the project limits are also to avoid damaging or paving over drainage, concrete pavement and other features.
Response posted 11/28/2023




Inquiry #17: The 6-55 hour closures allow for 1 lane in each direction, most of the work to be done during the closures will need 2 lanes in each direction. The removal and replacement of the barrier will be unsafe to move in a single lane. Can you change the 6 - 55 closures to allow for the #1 and 2 lanes in each direction to be closed?
Inquiry submitted 11/28/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/28/2023


Response #2:We cannot allow the closure of the #2 lane in either direction during the 55-hour closures. Note that you have two lanes total to remove the existing barrier and erect the new barrier, not one. Please bid appropriately.
Response posted 11/30/2023




Inquiry #18: Does note 7 on plan C-31 (sheet 60) apply to this contract? If yes, please provide a detail and bid item for the 4" dia. drain.
Inquiry submitted 11/28/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/28/2023


Response #2:Please ignore Note 7 on plan sheet C-31.
Response posted 11/30/2023




Inquiry #19: Does Provision 71-3 – Rehabilitate Drainage Structures apply to this contract? If yes, please provide linear feet (LF) bid items for each size of culvert type and identify each location on the Plans that this work pertains.
Inquiry submitted 11/28/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/28/2023


Response #2:Special Provision 71-3 only applies on this project if you damage existing drainage, and are required to rehabilitate the drainage at your cost. There is no planned drainage rehabilitation work on this project.
Response posted 11/28/2023




Inquiry #20: Please provide a bid item(s), scope of work, and construction detail for note 4 on plan SC-1 (sheet 213) which states "rehabilitate the pavement ETW to ETW after the median barrier replacement work". Bid item 26 (HMA, type A) for 1,300 tons only includes a 2' wide pavement and is substantially less than the 4' - 23' width between ETW and ETW shown on typical cross section X-1 (sheet 2).
Inquiry submitted 11/28/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/28/2023


Response #2:This note is only intended to identify that pavement rehabilitation should occur after barrier replacement to avoid damaging the new pavement during stage construction and barrier replacement work. See layout sheets L-1 to L-26 for scope of additional pavement rehabilitation work. See quantity sheet Q-5 for quantities for this pavement rehabilitation. HMA Type A is only to be used under the barrier per note 4 on X-1, the rest is RHMA-G and RHMA-O as shown in sheets X-1 and X-2.
Response posted 11/28/2023




Inquiry #21: Is a response to inquiry #13 forthcoming?
Inquiry submitted 11/28/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/28/2023


Response #2:Response provided 11/28/2023.
Response posted 11/28/2023




Inquiry #22: Per Existing Section 5 on Sheet X-1, there is an existing section of 1.2' of AC. After the removal of the existing barrier, there will still be existing asphalt under the proposed barrier. Note 4 on Sheet X-1 requires the placement of 0.33' minimum HMA under new barrier construction unless otherwise noted on the plans. Standard Plans for Concrete Barrier Type 60MGC in particular appear to show that the barrier is to be construction on either pavement or well compacted base. Please clarify if new HMA (0.33' Min.) will be required under the new barrier if the existing AC is still in place as detailed by Existing Section 5.
Inquiry submitted 11/28/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/28/2023


Response #2:A minimum of 0.33' of HMA under the barrier must be replaced with new HMA to account for damage to the pavement below during the concrete barrier removal process, and unknown condition of the existing HMA below the barrier. As shown, the toe elevation of the barrier should remain the same as existing.
Response posted 11/29/2023




Inquiry #23: In reference to note 4 on plan X-1 (sheet 2), please provide a roadway excavation bid item to remove the 4" of existing AC pavement for the proposed 4" HMA base under the new median barrier.
Inquiry submitted 11/29/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/30/2023


Response #2:Only HMA that is damaged needs to be replaced to at least 0.33', to meet requirements per the standard plans and specifications for the new barrier installation. Please ignore note 4 on X-1. No roadway excavation pay item is needed.
Response posted 11/30/2023




Inquiry #24: As an example, what is the offset dimension between cold planing & paving and face of barrier along southbound outside shoulder Sta 365 and Sta 408?
Inquiry submitted 11/30/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/30/2023


Response #2:Please refer to the Layout sheets of the plans to determine the approximate offset at any given location.
Response posted 11/30/2023




Inquiry #25: In the PDQ sheets it tells what option to be used for the contrast. I noticed that some of the details are in the wrong column and they repeat in thermoplastic and the tape columns. Please clarify.
Inquiry submitted 11/30/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/30/2023


Response #2:The inquiry has been received and submitted for consideration.
Response posted 11/30/2023


Response #3:Please bid for the quantities shown on the pavement delineation quantities.
Response posted 12/01/2023




Inquiry #26: Typical Cross Section on Sheet X-1 shows a new pavement section between the sawcut line and the face of concrete barrier on both North Bound and South Bound. This new pavement section is not identified in the Structural Sections.

1. Please clarify the type of material and the proposed thickness in this new section.
2. In what bid item does the demolition for the new pavement section get paid?
3. In what bid item does the new pavement improvement for this section get paid?

Inquiry submitted 11/30/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/30/2023


Response #2:There is no new section planned between the saw cut line and the new barrier, unless the existing HMA is damaged by the contractor. Please refer to the project layouts for the specific limits of cold plane and pave throughout the project limits.
Response posted 11/30/2023




Inquiry #27: Bid Item 14, and sheet SCQ-1 call out a quantity of 120 ea for the Lateral Shift of the Moveable Barrier. There is no information on how Caltrans arrived at this quantity.
Please confirm that payment for a lateral shift is 1 ea to move the barrier out at the start of the work shift, and 1 ea to move back the barrier at the end of shift. Also confirm that a Lateral Shift is per each direction -- Northbound and Southbound. Summary - if the moveable barrier is laterally shifted in the NB and SB direction, and shifted back -- this is 4 ea Lateral Shifts for the work day.

Inquiry submitted 11/30/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 11/30/2023


Response #2:Correct that each lateral shift is per direction and that each working period (including 55-hour closures and nightly closures for this project) would have four total lateral shifts utilized if both directions are closed. This item will be paid appropriately per the contractor's actual work schedule.
Response posted 12/01/2023




Inquiry #28: On 11/30/23 this response was posted for bidder inquiry #23

"Response #2: Only HMA that is damaged needs to be replaced to at least 0.33', to meet requirements per the standard plans and specifications for the new barrier installation. Please ignore note 4 on X-1. No roadway excavation pay item is needed. Response posted 11/30/2023"

We find the Response #2 to inquiry 23 to be contradictory. In the first sentence, we are directed to replace .33’ to meet the requirements of the standard plans & specification and in the second sentence, we are told to ignore note 4 on X-1. However, note 4 states: “Place .33’ minimum HMA (Type A) under the new concrete barriers, unless otherwise noted on the plans.” The two sentences in the response seem to conflict with each other.

Please consider issuing an addendum with a revised X-1 sheet showing/detailing clear direction to all the contractors the HMA needs under the new barriers.




Inquiry submitted 12/01/2023

Response #1:The inquiry has been received and submitted for consideration.
Response posted 12/01/2023


Response #2:As noted in the original response, please ignore Note 4 on X-1.
Response posted 12/01/2023


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.