Viewing inquiries for 05-1G9504
Submit new inquiry for this projectInquiry #1: Please let us know the date/time of the mandatory pre-bid meeting, and how to RSVP.
Inquiry submitted 10/14/2024
Response #1:Mandatory pre-bid meeting is not required. The project advertisement has been revised.
Response posted 10/15/2024
Inquiry #2: The engineers estimate of $7,800,000.00 is inadequate for this project. We have material and subcontractor numbers in hand and they don’t align close to this figure.
Does the District have the additional funds available to move forward with the project?
Inquiry submitted 11/15/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/18/2024
Response #2:Please bid per current contract documents.
Response posted 11/20/2024
Inquiry #3: Refer to the Information Handout. The various permits and agreements have stated durations for the nightwork required for the drainage scope. The stated durations aren’t sufficient to complete the work either in the roadway or at the respective area. As an example for work at Project Location 8 the permitting authority states ‘The Project will require 1 night of nightwork. Nightwork will include working on the outlet of the culvert.’ Given the traffic lane restrictions, nightwork restrictions and scope of work it is more likely to take 10 days to complete the majority of work at this location. Given the statements of the permitting authority will the need for additional working time be an issue/problem?
Please advise.
Inquiry submitted 11/15/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/18/2024
Response #2:The restriction of 1 night of nightwork at Location 8 mentioned in the Information Handout only applies to the Species Protection Area (SPA 2), cross hatching area near the flared end section. Contractor can choose to perform that work either during the day or night as long as it complies with the Highway Lane Requirement Chart in Special Provisions Section 12. If night work is performed at Location 8 in SPA 2 area, it is limited to one night as specified in the Streambed Alteration Agreement.
Response posted 11/20/2024
Inquiry #4: Refer to the Information Handout. The various permits and agreements note the requirement for the services of a biologist. Please confirm that the District, not the Contractor, is providing the biologist.
Inquiry submitted 11/15/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/18/2024
Response #2:The biologist is Department-supplied.
Response posted 11/20/2024
Inquiry #5: Given that the majority of the work on this project is to occur at night, will the District permit the use of precast drainage inlets and headwalls in lieu of the contractor forming/pouring in place? Please advise.
Inquiry submitted 11/15/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/18/2024
Response #2:Please refer to Standard Specifications Section 51-1.03B, "Methods and Equipment", you may use PC drainage inlets as an alternative to CIP drainage inlets.
Response posted 11/20/2024
Inquiry #6: Refer to the Information Handout.
One of the permits states that there is only a single Redwood tree which is to be removed as part of this project. Please confirm that this is correct. We could not find any information of call outs related to tree removal and want to ensure we carry the correct quantity in our bid. Our visual review of the job indicates numerous trees - Redwood trees that need to be trimmed and/or removed. What is the procedure with the permitting agency if we need to remove more Redwood trees?
Inquiry submitted 11/15/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/18/2024
Response #2:There are no trees identified to be removed by the contractor. Please bid per contract documents.
Response posted 11/20/2024
Inquiry #7: Refer Location 15 where the 120” RCP is to be installed. We have reviewed the site and have no idea how we are going to stage/handle the pipe at this location or how this section of the job gets built. The pipe weighs roughly 4500lb/ft and we can’t see how we will stage the appropriately sized crane or stage the trucks required to haul the pipe in – this is big, heavy pipe. The lane restrictions are also too restrictive, the road needs to be closed and detoured while work is underway. Can an alternate trenchless method and pipe material be used here? – liner plate and then steel or CMP drainage pipe or even two much smaller diameter trenchless crossings. We aren’t clear what type of drainage conditions would require installing a 120” diameter pipe. We also noted overhead wire interference which is an issue for the crane and hoisting bore equipment and pipe, are there any agreements in place for de-energizing those lines? Please review & advise on design/construction intent at this location. We can’t see how a crane will be staged, how the pipe will be hoisted. We also need to remove up to 24ea trees which doesn’t align with the statements made by the permitting agencies.
Inquiry submitted 11/15/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/18/2024
Response #2:Your inquiry is being reviewed.
Response posted 11/20/2024
Response #3:Your inquiry is being reviewed.
Response posted 11/24/2024
Response #4:Your inquiry is being reviewed.
Response posted 11/26/2024
Response #5: Your inquiry is being reviewed.
Response posted 12/02/2024
Response #6:Your inquiry is under review.
Response posted 12/06/2024
Response #7:Your inquiry is under review.
Response posted 12/09/2024
Response #8:Your inquiry is under review.
Response posted 12/11/2024
Response #9:Your inquiry is under review.
Response posted 12/19/2024
Response #10:Your inquiry is under review.
Response posted 12/27/2024
Response #11:Your inquiry is under review. The bid opening for this contract will be postponed to Feb 13, 2025. Addendum No. 3 will be posted to reflect that change.
Response posted 01/06/2025
Response #12:Your inquiry is under review.
Response posted 01/31/2025
Response #13:Your inquiry is under review.
Response posted 02/06/2025
Response #14:Your inquiry is under review.
Response posted 02/10/2025
Response #15:The bid opening is postponed to a future date. Your inquiry is under review.
Response posted 02/12/2025
Response #16:Your inquiry is being reviewed.
Response posted 02/26/2025
Response #17:Culvert at Loc 15 shall be built via Jack and Bore per advertised contract.
Please refer to Addendum No. 4 posted on Feb 12, 2025 that allows complete highway closure with motorist information plan for Location 15.
For utilities, please refer to Special Provisions Section 5-1.36C(2) Nonhighway Facility Protection to protect and make arrangements with utility owner if temporary deactivation is needed. There is no pre-agreement in-place.
Please also refer to Addendum No. 6 posted on Feb 27, 2025 for additional tree removal and temporary construction easement for Location 15.
Response posted 03/04/2025
Inquiry #8: There are numerous overhead wire interferences at the work locations, are there any agreements in place for de-energizing those lines? Who pays for this cost, the Contractor or the District? Can the District create an allowance item for this work?
Inquiry submitted 11/15/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/18/2024
Response #2:Your inquiry is being reviewed.
Response posted 11/20/2024
Response #3:Your inquiry is being reviewed.
Response posted 11/24/2024
Response #4:Your inquiry is being reviewed.
Response posted 11/26/2024
Response #5:Your inquiry is being reviewed.
Response posted 12/02/2024
Response #6:Your inquiry is under review.
Response posted 12/06/2024
Response #7:Your inquiry is under review.
Response posted 12/09/2024
Response #8:Your inquiry is under review.
Response posted 12/11/2024
Response #9:Your inquiry is under review.
Response posted 12/19/2024
Response #10:Your inquiry is under review.
Response posted 12/27/2024
Response #11:Your inquiry is under review. The bid opening for this contract will be postponed to Feb 13, 2025. Addendum No. 3 will be posted to reflect that change.
Response posted 01/06/2025
Response #12:Your inquiry is under review.
Response posted 01/31/2025
Response #13:Your inquiry is under review.
Response posted 02/06/2025
Response #14:No agreements were put in place to de-energize the lines for this project. Please refer to Special Provisions Section 5-1.36C(2) and make arrangement with the utility owner.
Response posted 02/06/2025
Inquiry #9: Refer to Section 13-12 Temporary Creek Diversion Systems. Can you provide historical water flow information for the creeks where the work will occur? We need this information in order to correctly figure the size requirements of the diversion components and pumps. If this information is not available, then provide anticipated flows so we at least have some information to work with. Please advise.
Inquiry submitted 11/18/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/18/2024
Response #2:Your attention is directed to Section 13-12, “Temporary Creek Diversion Systems” of the Special Provisions and Section 2-1.07, “Job Site and Document Examination” of the Standard Specifications. The contractor is responsible to submit the Temporary Creek Diversion System Plan that includes anticipated flow rate.
Please bid per current contract documents.
Response posted 11/20/2024
Inquiry #10: Refer Drainage Details Sheet DD-4. Please confirm that the ‘Concrete Backfill (Pipe Trench)’ detail is the detail we are to use for all open cut trench backfill work – we want to confirm that it is the intent that all open cut trenches are backfilled with concrete material around the pipe. Please advise.
Inquiry submitted 11/18/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/18/2024
Response #2:The Concrete Backfill (Pipe Trench) detail on DD-4 is for drainage locations specified in the Contract Plan Drainage Quantities DQ-6, in the Culvert Protection Quantities Table, under Concrete Backfill column.
Response posted 11/20/2024
Inquiry #11: Please confirm that dirt spoils associated with the excavation work can remain onsite. We want to confirm that we can loose some of this dirt material within the ROW and will not need to pay for off-haul & dump fees. Please advise.
Inquiry submitted 11/18/2024
Response #1:Your inquiry is submitted for review.
Response posted 11/18/2024
Response #2:Dirt spoils need to be removed and disposed of for trenchless construction as specified under Special Provisions Section 19-16.01C(5) under the second bullet item. Work plan must include description of the trenchless construction method, sequence of operations, type of excavated face support, and spoil removal. Refer to Standard Specification Section 1-1.07 Definition of remove is remove and dispose of.
Response posted 11/20/2024
Inquiry #12: Please provide the Geotechnical Report and/or Tunnel Engineering Evaluation Report for this project. We need a copy of this report to evaluate soils/ground conditions, specifically for the work at Location No.07 (Retaining Wall), No.15 (Large Diameter Pipe Jacking), Location No.22 (Pipe Jacking), Location No.25 (Pipe Jacking).
If a geotechnical report or tunnel engineering evaluation has not been published, then please provide direction on the soils/ground conditions we should anticipate encountering in our bid.
Inquiry submitted 11/20/2024
Response #1:An addendum will be issued to provide additional information to address this inquiry.
Response posted 11/20/2024
Response #2:An addendum will be issued to provide additional information to address this inquiry.
Response posted 11/24/2024
Response #3:Please refer to Geotech Report for Location 15, 22 and 25 in the Information Handout.
An addendum will be issued to provide the foundation report for Location 7 retaining wall.
Response posted 11/26/2024
Response #4:An addendum will be issued to provide the foundation report for Location 7 retaining wall.
Response posted 12/02/2024
Response #5:Please refer to Geotech Report for Location 15, 22 and 25 in the Information Handout. An addendum will be issued to provide the foundation report for Location 7 retaining wall.
Response posted 12/06/2024
Response #6:Please refer to Geotech Report for Location 15, 22 and 25 in the Information Handout. An addendum will be issued to provide the foundation report for Location 7 retaining wall.
Response posted 12/09/2024
Response #7:Please refer to Geotech Report for Location 15, 22 and 25 in the Information Handout. An addendum will be issued to provide the foundation report for Location 7 retaining wall.
Response posted 12/11/2024
Response #8:Please refer to Geotech Report for Location 15, 22 and 25 in the Information Handout. An addendum will be issued to provide the foundation report for Location 7 retaining wall.
Response posted 12/19/2024
Response #9:Please refer to Addendum No. 2 dated December 23, 2024. The foundation report for retaining wall location 7 is included in the Information Handout.
Response posted 12/27/2024
Inquiry #13: Please provide the Arborist Report.
Inquiry submitted 11/20/2024
Response #1:Arborist Report is not available. Contractor is responsible to supply the arborist to monitor work within Species Protection Area 3 (SPA 3). Refer to Bid Item 29 CONTRACTOR SUPPLIED ARBORIST and Special Provisions Section 14.
Response posted 11/20/2024
Inquiry #14: What is the duration of the Plant Establishment Period?
Inquiry submitted 11/20/2024
Response #1:An addendum will be issued to provide the plant establishment period.
Response posted 11/20/2024
Response #2:An addendum will be issued to provide the information.
Response posted 11/24/2024
Response #3:An addendum will be issued to provide the information.
Response posted 11/26/2024
Response #4:An addendum will be issued to provide the information.
Response posted 12/02/2024
Response #5:An addendum will be issued to provide the information.
Response posted 12/06/2024
Response #6:The Plant Establishment is 250 days. An addendum will be issued to provide the information.
Response posted 12/09/2024
Response #7:The Plant Establishment is 250 days. An addendum will be issued to provide the information.
Response posted 12/11/2024
Response #8:The Plant Establishment is 250 days. An addendum will be issued to provide the information.
Response posted 12/19/2024
Response #9:Please refer to Addendum No. 2 dated December 23, 2024.
Response posted 12/27/2024
Inquiry #15: The CA High Design Manual Section 850-34 dated December 30th, 2015 warns against specifying plastic pipe in areas with a potential for fire. This project lists Alternative Pipe Culvert in the Bid Schedule. Will Caltrans still allow for plastic pipe to be used on this project?
Inquiry submitted 01/09/2025
Response #1:Please refer to Contract Plan Sheet (Drainage Quantities DQ-6) for allowable material to be used for Alternative Pipe Culvert.
Response posted 01/13/2025
Inquiry #16: Is plant establishment maintenance required in locations with erosion control and hydroseeding only (no container planting)? If so, what tasks are to be performed?
Inquiry submitted 01/23/2025
Response #1:Plant Establishment work to occur within limits shown on Contract Plans PP-1 and PP-2, as well as associated Notes. Refer to Standard Specifications and Special Provisions Section 20-4 for Plant Establishment requirements.
Response posted 01/24/2025
Inquiry #17: Is the Contractor required to provide Builders Risk Insurance coverage for this project? Please advise.
Inquiry submitted 01/28/2025
Response #1:Your inquiry is received and being reviewed.
Response posted 01/28/2025
Response #2:The term for Builder Risk Insurance does not come up in our contract documents. Please refer to the contract documents on insurance requirements.
Response posted 01/31/2025
Inquiry #18: For the temporary Shoring and Jacked Concrete Reinforced Pipe please clarify or confirm the following:
1. Length and Shored Heights
2. Surcharge Loading
3. Desired deflection for Shoring System
4. Are soil nails or tiebacks allowed to be installed past Caltrans property line?
Inquiry submitted 01/31/2025
Response #1:Your inquiry is submitted for review.
Response posted 01/31/2025
Response #2:Your inquiry is submitted for review.
Response posted 02/04/2025
Response #3:1. Length and Shored Heights
Refer to Section 7-1.02K(6) and Section 48 of the Standard Specifications for temporary structure and protective system requirements. The contractor shall submit the shop drawings of protective system designed and signed by a registered civil engineer.
2. Surcharge Loading
Surcharge loading applied to your proposed protective system should be identified in the submitted shop drawings / calculations referenced in (1.) and reviewed by the Engineer.
3. Desired deflection for Shoring System
Deflection of your proposed protective system should be identified in the submitted shop drawings / calculations referenced in (1.) and reviewed by the Engineer.
4. Are soil nails or tiebacks allowed to be installed past Caltrans property line?
Work shall be completed with the State right of way and/or acquired easements.
Response posted 02/06/2025
Inquiry #19: Please provide the DWG of Sheet 150 of 156. We need the contours from this sheet to do our earthwork calculations.
Inquiry submitted 02/06/2025
Response #1:Your inquiry is submitted for review.
Response posted 02/10/2025
Response #2:An addendum will be issued to provide the dwg file.
Response posted 02/11/2025
Response #3:Please refer to Addendum No. 4, dated February 12, 2025 for Location 7 dwg file.
Response posted 02/13/2025
Inquiry #20: Would like to confirm that the grade of asphalt binder for Type A HMA is PG 70-10. It is very rare to have this mix approved by Caltrans as per suppliers. Please advise.
Inquiry submitted 02/10/2025
Response #1:An addendum will be issued to revise the binder grade to 64-10.
Response posted 02/11/2025
Response #2:Please refer to Addendum No. 4, dated February 12, 2025. The grade of asphalt binder for Type A HMA must be PG 64-10.
Response posted 02/13/2025
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.