Submit new inquiry for this projectInquiry #1: Can other alternative pipeliners that conform to DIB 83-4 per section 71-3-09 be used in place of CIPP? These liners have many advantages including environment as well as can be installed in live flow without the need for by-passing.
Inquiry submitted 10/14/2024
Response #1:Your inquiry is submitted for review.
Response posted 10/15/2024
Response #2:Other alternative pipeliners are not allowed. Please bid per advertised contract documents and refer to Special Provisions Section 71-3.08 “CURED-IN-PLACE PIPELINERS”.
Response posted 10/16/2024
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.