Bidder Inquiries
Caltrans Bidding Connect Account:
Sign In (Sign in is required to access Project Plans)
Create Account (Click here to create a Caltrans Bidding Connect Account)
Viewing inquiries for 06-0U2904
Submit new inquiry for this projectInquiry #1: The plans to not provide existing grades, or proposed grades for the roadway. Can the State provide cross sections for take-off purposes?
Inquiry submitted 05/06/2025
Response #1:Your inquiry has been submitted for review.
Response posted 05/06/2025
Response #2:This project has a cold plane and overlay strategy so no cross sections are required. Roadway profile will be consistent with existing grade and typical cross sections sheets X-1 to X-12 are adequate for take-off purposes. Please place your bid in accordance with the current contract bid documents.
Response posted 05/10/2025
Inquiry #2: What bid item of work is the removal of the outside shoulders outside the limits of the cold plane area paid under? The plans require the contractor to place HMA in this area, but where is the removal paid?
Inquiry submitted 05/12/2025
Response #1:Your inquiry has been submitted for review.
Response posted 05/13/2025
Response #2:An addendum is forthcoming.
Response posted 05/16/2025
Inquiry #3: Is there a re-compaction spec requirement for the area under the shoulder construction, and what is that requirement if there is one?
If there is a recompact spec, how will the contractor get paid for it? If so, is the requirement to recompact the existing aggregate base?
Inquiry submitted 05/12/2025
Response #1:Your inquiry has been submitted for review.
Response posted 05/13/2025
Response #2:Compaction of material under structural section is covered in the Standard Specification; 19 Earthwork and 26 Aggregate Bases. Please place your bid in accordance with the current contract bid documents.
Response posted 05/16/2025
Inquiry #4: Is the contractor held to a re-compaction spec under or within the HMA path ? If yes, how will the contractor get paid for this work?
Inquiry submitted 05/12/2025
Response #1:Your inquiry has been submitted for review.
Response posted 05/13/2025
Response #2:Compaction of material under structural section is covered in the Standard Specification; 19 Earthwork and 39 Asphalt Concrete. Please place your bid in accordance with the current contract bid documents.
Response posted 05/16/2025
Inquiry #5: How will the contractor get paid for the removal of the existing HMA bike path since it is not called out as Roadway Excavation on the plans or any of the cross sections of the plans?
Inquiry submitted 05/14/2025
Response #1:Your inquiry has been submitted for review.
Response posted 05/14/2025
Response #2:The existing HMA bike path is shown on the typical cross section sheets X-3 and X-4. The removal is covered under roadway excavation (Section 19-2 in Standard Specifications). An addendum will be provided that will cover the removal of existing HMA bike path under an updated roadway excavation quantity.
Response posted 05/19/2025
Inquiry #6: How is the removal of the existing roadway 0.9’ HMA section next to the new concrete median paid for? And is there a requirement to process the underlying material to get compaction? If there is a re-compaction spec, how will it be paid for?
Inquiry submitted 05/14/2025
Response #1:Your inquiry has been submitted for review.
Response posted 05/14/2025
Response #2:Removal of roadway will be covered under Roadway Excavation. An Addendum is forthcoming to depict the quantities in those locations. Compaction of material under structural section is covered in the Standard Specification - Section 19 Earthwork.
Response posted 05/19/2025
Inquiry #7: How will Caltrans pay for the embankment areas called for on the cross sections of the project plans? And how is this embankment to be measured and quantified if no scale is provided on the cross sections?
Inquiry submitted 05/14/2025
Response #1:Your inquiry has been submitted for review.
Response posted 05/14/2025
Response #2:Embankment quantity is not a pay item and informational only. The roadway excavation will provide excess soil that can be used for the embankment. Caltrans utilized MicroStation to calculate the embankment amount that is shown on the Quantities sheet Q-1 and Q-8. Based on MicroStation details, survey information, and relatively flat terrain throughout the project limits – an average depth was used to quantify the embankment amount.
Response posted 06/04/2025
Inquiry #8: Will Caltrans provide CAD files and cross sections for take-off purposes of basin excavation?
Inquiry submitted 05/14/2025
Response #1:Your inquiry has been submitted for review.
Response posted 05/14/2025
Response #2:The basins were within the Roadway Excavation portion from an earlier inquiry. Due to the significant changes in Roadway Excavation, we will provide Cad files for the basins’ volume take-offs, instead of utilizing basin calculation formulas.
Response posted 06/04/2025
Inquiry #9: The Class II Aggregate Base Item appears to be substantially overstated. Sheet Q-1 shows 2,526.9 CY of Class II Aggregate Base from STA 185+60 - STA 230+47, however, the only Class II Aggregate Base being placed in that area is quantified in areas shown on Sheets Q-4, Q-7 and Q-8. Sheet Q-1 also shows 2,653 CY of Class II Aggregate Base from STA 247+98 - STA 338+04; the only Class II Aggregate Base being placed in that stationing is on the Driveways which is quantified on Sheet Q-7. Please review and advise where the additional base shown on Q-1 is being placed.
Inquiry submitted 05/30/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/02/2025
Response #2:An addendum is forthcoming.
Response posted 06/04/2025
Inquiry #10: The HMA Paving Item (No. 43) appears to be substantially understated. The HMA Paving for the CPAC areas alone exceeds the bid item quantity. Another example is on Sheet Q-8. HMA Paths 1 & 2 are shown on the typical cross sections to be paved at 0.50' HMA (Misc), the HMA quantity shown on sheet Q-8 is less than half of what would be needed to pave those areas per the plan section. Please review and advise.
Inquiry submitted 06/04/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/04/2025
Response #2:An addendum is forthcoming.
Response posted 06/11/2025
Inquiry #11: When does the State plan to release Addendum 1 that was referenced in the response to Inquiries 2, 5 & 6? With the bid date less than a week out, will the State consider pushing the bid date to allow contractors sufficient time to review the changes?
Inquiry submitted 06/04/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/04/2025
Response #2:Addendum 1 was released on June 5th and is included in the Bid Documents link. Bid opening is now delayed to June 17th.
UPDATE: Addendum 2 was issued 6/11/2025. This addendum will delay bid opening to June 24,2025.
Addendum #3 is being prepared to address many of the bidder inquiries on qtys.
Response posted 06/11/2025
Inquiry #12: Clarify whether the 18” and 16” welded steel pipes require any internal lining and/or external coating.
Inquiry submitted 06/04/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/04/2025
Response #2:Internal and External lining/coating will be required for WSP as it is a drainage pipe.
Response posted 06/12/2025
Inquiry #13: For Bid Item 67 Modify Inlet, provide a depth for the dry well and the size/length of the RCP riser.
Inquiry submitted 06/04/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/04/2025
Response #2:Dry well depth of 10ft which includes the 24in RCP pipe length of 5ft. This is typical dimensions for all “Modify Inlet” bid item locations.
Response posted 06/11/2025
Inquiry #14: Special Provisions Section 12-4.04C states that "A Pedestrian facility closure on the same side of the highway is limited to no more than 1 block.
When working on one side of the highway, the pedestrian facility on opposite side of the highway within the same block must be open"
Concurrent pedestrian facility closures on the same side of the highway must be speced at least 2 blocks apart".
This restriction does not allow for the completion within 10 calendar days for each stage 1A, 1B, 2A, and 2B, as per the requirement on
section 8-1.09 Disincentive for late completion" It does not provide enough time for the contractor to demo, grade, base and pour all the minor concrete, while being restricted to a closure on no more than 1 block.
Would Caltrans reconsider extending the Calendar day duration allowed per stage, or eliminate section 12-4.04C of the Special Provisions for this project?
Inquiry submitted 06/05/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/05/2025
Response #2:Please follow stage plans sheet SC-1 to SC-14 for construction staging in the City of Lamont area (Stage 1A, 1B, 1C, 2A, 2B, 2C) where the disincentive clause section 8-1.09 applies. Section 12-4.04C applies when work is outside of the staging plans strategy. Stage 1A, 1B, 1C, 2A, 2B, 2C limits extend further than 1 block so that the calendar day duration for construction is achievable. Place your bid in accordance with the current contract bid documents.
Response posted 06/13/2025
Inquiry #15: Cross sections on Sheet X-11 of the project plans indicate the following:
STA 347+53 to STA 376+04 shows an existing structural section of 0.2' of AC over 0.85' CTB on the shoulders.
The plans call for a new shoulder structural section of 0.15' RHMA-G over 0.45' HMA Type A, which will require breaking through the CTB section.
STA 376+04 to STA 385+52 shows an existing structural section of 0.2' of AC over 0.85' CTB on the shoulders.
Plans require to cold plane 0.3', and pave back 0.15' RHMA-G over 0.2' HMA Type A, which will also require breaking through the CTB section.
How will Caltrans pay for the removal of the CTB, and the additional embankment needed to replace the void as the contractor will also need to recompact subgrade, and all of this will increase the depth of the shoulder section?
Inquiry submitted 06/05/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/05/2025
Response #2:Sta 347+53 to 376+04, the removal of CTB is covered under “Roadway Excavation” Section 19 in the Standard Specifications.
Sta 376+04 to 385+52, CTB removal for shoulder section is covered under Cold Plane Asphalt Concrete (CPAC) activity. During CPAC, subgrade should not be disturbed by the contractor. If subgrade is disturbed by the contractor, re-compaction spec will apply, and contractor is responsible for this work without any extra payment.
As far as depth, Cross section sheet X-11 shows 0.30ft of CPAC and placing back 0.35ft of pavement (0.20ft HMA and 0.15ft RHMA). No increase in depth.
Response posted 06/13/2025
Inquiry #16: Special Provision Section 39-2.01B(2)(b) calls to treat aggregates with dry lime or lime slurry. Do aggregates need to be treated if Hamburg wheel track and Moisture susceptibility meet section 39 specification and have a zero plasticity index?
Inquiry submitted 06/06/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/06/2025
Response #2:Please place your bid in accordance with the current contract bid documents.
Response posted 06/13/2025
Inquiry #17: Special Provision Section 39-2.01B(2)(b) calls to treat aggregates with dry lime or lime slurry. Do aggregates need to be treated if Hamburg wheel track and Moisture susceptibility meet section 39 specification and have a zero plasticity index?
Inquiry submitted 06/06/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/06/2025
Response #2:Please place your bid in accordance with the current contract bid documents.
Response posted 06/13/2025
Inquiry #18: 82-3.02F Enhanced Conspicuity Retroreflective Treatment On Sign Posts.
With ~508ea Sign Posts this item needs to be quantified and provided to the Contractor. This is a significant cost that requires a bid item.
Please quantify this scope and add a separate bid item.
Inquiry submitted 06/09/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/09/2025
Response #2:Payment for signage is specified in section 82-3.04. Please place your bid in accordance with the current contract bid documents.
Response posted 06/13/2025
Inquiry #19: Will the State please answer Inquiry #14.
As it sits:
Section 12-4.04C; the Contractor is limited to 1 block of work at a time.
Section 8-1.09; the Contractor gets Deducted $5000/Day over 10 Days.
You have limited the production in 12-4.04C then fine the Contractor in 8-1.09. This is not constructible within the arbitrary time frame you have set. Please address this constructability issues with time for us to bid this work.
Inquiry submitted 06/10/2025
Response #1:Your inquiry has been submitted for review.
Response posted 06/10/2025
Response #2:Please follow stage plans sheet SC-1 to SC-14 for construction staging in the City of Lamont area (Stage 1A, 1B, 1C, 2A, 2B, 2C) where the disincentive clause section 8-1.09 applies. Section 12-4.04C applies when work is outside of the staging plans strategy. Stage 1A, 1B, 1C, 2A, 2B, 2C limits extend further than 1 block so that the calendar day duration for construction is achievable. Place your bid in accordance with the current contract bid documents.
Response posted 06/13/2025
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.