Bidder Inquiries

Caltrans Bidding Connect Account:

Sign In (Sign in is required to access Project Plans)

Create Account (Click here to create a Caltrans Bidding Connect Account)


Viewing inquiries for 06-1F8304

Submit new inquiry for this project


Inquiry #1: The last time this project was out to bid, the State adjusted the working days from 45 to 65 due to the amount of work and coordination required at for the electrical and paving scopes. As this work is substantially the same between the old and new bids, please consider increasing the total working days for this project as 45 days is not enough.
Inquiry submitted 04/23/2024

Response #1:Please place your bid in accordance with the current contract bid documents.
Response posted 04/24/2024




Inquiry #2: Per Special Provision section 12-4.02C(7)(b):
"The maximum length of a single stationary one-way-reversing traffic-control lane closure is 2 miles between flaggers. The length of the lane closure may be extended to 1.5 miles between the hours of 2200 and 0600."

This statement seems to be in error, please advise.

Inquiry submitted 04/23/2024

Response #1:An addendum will be processed to address this issue. If an addendum is not released please place your bid in accordance with the current bid documents.
Response posted 04/24/2024


Response #2:Attention is directed to Addendum No. 1 dated April 25, 2024. Please place your bid in accordance with the current contract bid documents.
Response posted 04/25/2024


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.