Inquiry #1: - Please consider providing a bid item for Impact Attenuator Vehicle since a large amount of this work will require the use of two IAV’s for traffic control.
Inquiry submitted 01/16/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/17/2023


Response #2:The use of any Impact Attenuator Vehicle is included in the Bid Item for “120100 Traffic Control”. No separate item is used.
Response posted 01/19/2023




Inquiry #2: Will temporary traffic screen be required on any of the k-rail?
Inquiry submitted 01/17/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/17/2023


Response #2:Temporary Traffic Screen is not required for this project.
Response posted 01/26/2023




Inquiry #3: Please consider providing a bid item for the temporary automated end of queue warning system per specification section 12-3.
Inquiry submitted 01/17/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/17/2023


Response #2:Please refer to addendum #1 dated 2/3/2023.
Response posted 02/09/2023




Inquiry #4: In regards to Layout sheet L-5, is the southbound shoulder supposed to be replaced with 0.25’ HMA-A and then slurry sealed? The limits of pavement sections [4] & [5] aren’t indicated. Please clarify.
Inquiry submitted 01/17/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/17/2023


Response #2:The southbound freeway shoulder is only slurry seal as shown on L-5. It is pavement section 5.
Response posted 01/26/2023




Inquiry #5: On sheet X-1, sections 2 and 7 calls for "SUBGRADE ENHANCEMENT GEOTEXTILE, CLASS B2". There is no pay item. How will this be paid?
Inquiry submitted 01/18/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/18/2023


Response #2:"SUBGRADE ENHANCEMENT GEOTEXTILE, CLASS B2" has been added to the project. See Plan Sheet Q-1 for Addendum #1 dated 2/3/2023.
Response posted 02/09/2023




Inquiry #6: Where is the removal of concrete paid for construction note 4? On the typical X-sections it doesn't show existing concrete pavement but the construction note mentions removing concrete. Should we assume the .25 remove concrete is asphalt concrete? Please advise.
Inquiry submitted 01/19/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/20/2023


Response #2:Yes, “remove concrete” means removal of the asphalt pavement.
Response posted 01/30/2023




Inquiry #7: It seems as though the JPCP quantities are missing a few callouts. On the quantity sheet it shows JPCP on Layout Sheet 15 but i dont see a construction note #2 on that sheet. Please advise should there be a construction note #2 on Layout Sheet 15? The same instance happens for Layout 13 on the Quantity Sheet it references JPCP and I do not see a construction note. Please advise should there be a construction note #2 on Layout Sheet 13?
Inquiry submitted 01/19/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/20/2023


Response #2:Note 2 has been added to L-13 and L-15 by Addendum #1 dated 2/3/2023
Response posted 02/09/2023




Inquiry #8: On sheet C-30 is shows the MVP section as being Type Z-2 (ADL) soil. On the quantity sheet Q-1 the roadway excavation it shows quantities corresponding with the MVP as regular roadway excavation. Please confirm that the MVP excavation shall be considered ADL Z-2?
Inquiry submitted 01/19/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/20/2023


Response #2:MVP excavation is considered ADL (type Z-2). Such quantities are on Q-1.
Response posted 02/09/2023




Inquiry #9: Under the Special Provisions , Section 39 Asphalt Concrete (39-2.03B(3)(a), it refers the grade of asphalt binder for the RHMA-G must meet a grade of 70-10, is this the correct asphalt grade for the RHMA-G?
Inquiry submitted 01/20/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/20/2023


Response #2:The correct binder is 70-10 as shown on Special Provisions.
Response posted 02/27/2023




Inquiry #10: On sheet D-1 it shows for the BST section see Sht PP-1 for details. I haven't seen sheet PP-1 as apart of the bid package. Please advise if this is a typo?

Inquiry submitted 01/23/2023

Response #1:There is a PP-1 sheet on the Bid Package. It is Plan Sheet 250.
Response posted 01/23/2023




Inquiry #11: It seems as if there are TC Closure charts missing for the SB Individual Slab Replacement between EB 210 off connectors to Live Oak On Ramp. Please advise on if the chart will mirror an existing chart that was provided? If so which one?
Inquiry submitted 01/23/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/23/2023


Response #2:This question needs to be rephrase since E/B 210 is not close to Live Oak On Ramp and the slab work closest to E/B 210 is covered by Chart 13.
Response posted 01/26/2023




Inquiry #12: There is a MVP that is shown at Sta 1091+78.43 to Sta 1090+93.43 that is not explicitly called out. Please confirm that is a part of the scope of work?
Inquiry submitted 01/25/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/26/2023


Response #2:The MVP that is shown at Sta 1091+78.43 to Sta 1090+93.43 is part of the scope of work.
Response posted 01/26/2023




Inquiry #13: For the configuration shown on sheet TH-4. How long can we keep the partial ramp closed?
Inquiry submitted 01/25/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/26/2023


Response #2:Please refer to Plan TH-4 on addendum No.2 issued on 2/15/2023.
Response posted 02/27/2023




Inquiry #14: There is a shoulder backing detail on sheet X-2. Where is that backing material and placement paid?
Inquiry submitted 01/26/2023

Response #1:
Shoulder Backing is not part of the scope of this project. Shoulder Backing is not a pay item for this project.

The detail on X-2 is a general detail of where we place the new dike. If Shoulder Backing is needed, it will be paid as a Contract Change Order.

Response posted 01/26/2023


Response #2:
Response posted 02/27/2023




Inquiry #15: For Individual slab replacements there is no chart covering SB direction between the 210 connector and Live Oak on ramp. There are 8 charts:

Table A - NB 605 from EB 10 connector to Rte 10 on connectors
Table B - NB 605 from Rte 10 on connectors to Ramona Blvd on ramp
Table C - NB 605 from Ramona on ramp to Lower Azusa Rd on-ramp
Table D - NB 605 from Lower Azusa Rd on-ramp to EB Arrow Hwy on-ramp
Table E - NB 605 from EB Arrow Hwy on-ramp to Rte 210 off-connector
*Missing SB 605 span from - 210 connector to Live Oak*
Table F - SB 605 from Live Oak on ramp to Lower Azusa Rd on-ramp
Table G - SB 605 from Lower Azusa Rd on-ramp to Ramona Blvd on-ramp
Table H - SB 605 from Ramona Blvd on-ramp to Rte 10 off-connector

Please help with the missing span of the SB 605?

Inquiry submitted 01/27/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/27/2023


Response #2:Please refer to addendum No.2 issued on 2/15/2023.
Response posted 02/27/2023




Inquiry #16: Base on Sheet Q-2 there is JPCP on sheet L-13 and L-15. I do not see callouts for said JPCP section. Please advise if there is an addendum coming to address the variance in quantity for JPCP?
Inquiry submitted 01/27/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/27/2023


Response #2:Please refer to addendum No.2 issued on 2/15/2023.
Response posted 02/27/2023




Inquiry #17: Construction Details Sheet C-30 provides a typical section for BMP (DPPIA/RSP) which indicates excavated material to be (Type Z-2) (ADL). This work does not appear to be accounted for in the quantities. Please confirm that this work is incidental to the DPPIA / RSP items.
Inquiry submitted 01/27/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/30/2023


Response #2:Excavated material for DPPIAs to be paid under Bid Item “Roadway Excavation (Type Z-2) (Aerially Deposited Lead)”
Response posted 02/27/2023




Inquiry #18: Please provide an applicable traffic table for the individual slab replacement work on SB 605 from the Route 210 connectors to Live Oak on-ramp.
Inquiry submitted 01/30/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/30/2023


Response #2:See Addendum #2 for New Table.
Response posted 02/27/2023




Inquiry #19: Please review sheets L-19 and L-20. The plans are currently calling for individual slab replacement work to be performed on bridge decks.
Inquiry submitted 01/30/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/30/2023


Response #2:There is no work on bridge. See Addendum #2.
Response posted 02/27/2023




Inquiry #20: There are numerous locations in the construction layout sheets where the shoulder or ramp paving work does not match on either side of the provided match lines. For instance, NB shoulder work between sheets L-1 and L-2, both directions of shoulders and ramps between sheets L-3 and L-4, and the NB shoulder and ramp work between L-12 and L-13. Please provide corrected layout sheets so that bidders may accurately verify the quantities and locations of work to be performed.
Inquiry submitted 01/30/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/30/2023


Response #2:Bid per quantities shown on plans.
Response posted 03/03/2023




Inquiry #21: Regarding response #2 to inquiry #11: numbered traffic charts are never applicable to individual slab replacement. Individual slab replacement work is governed by the tables provided in special provisions section 12-4.02C(3)(n) which states "Comply with the lane closure requirements for concrete slab and approach slab replacement work shown in the following tables:".
Inquiry submitted 01/30/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/30/2023


Response #2:Please refer to addendum No.2 issued on 2/15/2023.
Response posted 03/03/2023




Inquiry #22: Please advise what construction note Bid Item 76 Remove Asphalt Concrete Pavement applies to for quantity verification?
Inquiry submitted 01/31/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/31/2023


Response #2:It applies to the removal of asphalt shoulder at the on and off ramps as shown on X-1. Refer to addendum #1 dated 2/3/2023.
Response posted 02/09/2023




Inquiry #23: What is the Bid Item for Detectable warning surface?
Inquiry submitted 02/03/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/03/2023


Response #2:See Addendum #2 for Bid Item.
Response posted 02/27/2023




Inquiry #24: Summary of quantities sheet Q-2 indicates paving work to be performed on the NB 605 Loop Off-Ramp to Live Oak Ave, yet there is no construction callout for any structural section on the layout sheet L-13. Please advise if the summary of quantities is correct, or the layout sheet. If the summary of quantities is correct, please provide a revised layout sheet to show the correct paving limits.
Inquiry submitted 02/03/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/03/2023


Response #2:The Layout is correct. There is no work on this loop on ramp. A revised Q-2 was provided by Addendum #2.
Response posted 02/27/2023




Inquiry #25: • Summary of Quantity Plansheet Q-2 shows 361 CY of JPCP on L-15 at the SB off-ramp to arrow highway, but the layout sheets do not indicate JPCP pavement sections at this location. Please provide clarification.
Inquiry submitted 02/03/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/06/2023


Response #2:L-15 has been revised per Addendum #2.
Response posted 02/27/2023




Inquiry #26: According to pavement section # 1, ISR depth for Lanes 1 & 2 shall be 0.70’ and the existing pavement in these areas is shown as 0.67’ concrete pavement / 0.35’ CTB. Is the intent that during an ISR closure we are to excavate 0.03’ of the existing CTB for the new 0.70’ ISR section? Please confirm.
Inquiry submitted 02/03/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/06/2023


Response #2:Please bid per contract documents.
Response posted 02/09/2023




Inquiry #27: Please provide a callout or construction detail for ramp termini joints.
Inquiry submitted 02/03/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/06/2023


Response #2:Please bid per contract documents.
Response posted 02/09/2023




Inquiry #28: Please provide detail of the work for bid items 69 – MINOR CONCRETE and 28 – REMOVE CONRETE. Summary of Quantities plan sheet Q-3 indicates the volumes and locations of these areas but no where on the layout sheets or construction details does it identify where this work is or what it looks like.
Inquiry submitted 02/08/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/08/2023


Response #2:There is existing concrete at the base of proposed MGS to be removed and replaced. Bid per plan.
Response posted 02/24/2023




Inquiry #29: The department has answered various bidders questions by referring bidders to addendum #1. Addendum #1 made no changes to the bid documents other than the bid date change. Is there additional information that Caltrans has yet to post online?
Inquiry submitted 02/10/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/10/2023


Response #2:Please refer to addendum No.2 issued on 2/15/2023.
Response posted 02/24/2023




Inquiry #30: The special provisions for this project mention Standard Spec and Standard Plan dated 2022 but the project plans state to be supplemented by standard plans dated 2018. Which standard plans should we follow? Please advise.
Inquiry submitted 02/10/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/10/2023


Response #2:Please refer to addendum No.2 issued on 2/15/2023.
Response posted 03/03/2023




Inquiry #31: Will this project be indexed?
Inquiry submitted 02/10/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/10/2023


Response #2:Can you rephrase the question? Does not understand what “indexed” means
Response posted 03/03/2023




Inquiry #32: Customarily the RHMA uses binder 64-16 per the special provisions on this project it is called to have PG 70-10. Please confirm that PG 70-10 is required?

Inquiry submitted 02/10/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/10/2023


Response #2:Bid on Binder 64-16.
Response posted 02/24/2023


Response #3:The correct binder is 70-10 as shown on Special Provisions.
Response posted 02/27/2023




Inquiry #33: When will the addendum plans be posted? Please advise.
Inquiry submitted 02/10/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/10/2023


Response #2:Addendum has been posted.
Response posted 02/24/2023




Inquiry #34: Based on the addenda changes will the quantities be updated to match or should we use the previous bid quantities? Please advise at your convenience.


Inquiry submitted 02/16/2023

Response #1:The quantity changes in addendum #2 is reflected in the bid book.
Response posted 02/16/2023




Inquiry #35: There are different types of guardrail on the existing hwy. For example, Double Guardrail and 8"x8" wood post guardrail. Please provide quantities and bid items for the different locations and types of guardrail to price accordingly.
Inquiry submitted 02/16/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/16/2023


Response #2:Existing Double Guardrail and 8x8 posts are not part of the project.
Bid on quantities shown on Bid Book and Plans

Response posted 02/27/2023




Inquiry #36: Please confirm the Contractor is not responsible for pre & post survey at the ADA ramps and this will be provided by the State.
Thank You

Inquiry submitted 02/21/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/21/2023


Response #2:Yes, contractor is not responsible for Pre & Post Surveys.
Response posted 02/23/2023




Inquiry #37: Good afternoon the striping summary doesn't show any 8", or 12" striping. How are you going to pay for these items if we are required to install striping other than 6 "?
Inquiry submitted 02/23/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/23/2023


Response #2:On this project there is no 8” or 12” striping to be paid per linear foot. There is no need for such items. If required during construction, payment will be per Contract Change Order.
Response posted 02/24/2023




Inquiry #38: Regarding response #2 to inquiry #32, please provide an addendum to reflect the correct oil type. As Caltrans is aware, bidders questions and answers are "not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract."
Inquiry submitted 02/24/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/24/2023


Response #2:The correct binder is 70-10 as shown on Special Provisions.
Response posted 02/27/2023




Inquiry #39: Addendum 2 made changes to the quantities shown on Summary of Quantities Sheet Q-2, yet none of these changes were reflected in the bid book. Please advise.
Inquiry submitted 02/24/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/24/2023


Response #2:Please check updated Bid Book.
Response posted 03/07/2023




Inquiry #40: Addendum 2 added 3,420 SY of Subgrade Enhancement Geotextile Class B2 on summary of quantities sheet Q-2, yet there was no relevant pay item added to the bid schedule. Please advise how the contractor is to be compensated for this work.
Inquiry submitted 02/24/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/24/2023


Response #2:Contractor will be compensated for a new item to cover Subgrade Enhancement Geotextile Class B2
Response posted 03/07/2023




Inquiry #41: The detail for DPPIA on sheet C-30 shows ADL in the excavated material. Drainage Quantities sheet Q-1 indicates this work to be standard Roadway Excavation. Is this material contaminated, and if so, how is it's excavation and disposal paid for?
Inquiry submitted 02/24/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/24/2023


Response #2:Excavated material for DPPIAs to be paid under Bid Item “Roadway Excavation (Type Z-2) (Aerially Deposited Lead)”
Response posted 02/27/2023




Inquiry #42: There appears to be a major quantity bust for bid item 58 HOT MIX ASPHALT (TYPE A). Sheet Q-1 includes 1,624 T of HMA for the Type A Dike, however when calculated based on standard dimensions, the quantity of HMA needed should be just over 500 T. Please advise what the additional 1,000 + Tons of HMA is used for.
Inquiry submitted 02/26/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/27/2023


Response #2:Please refer to addendum No.5 issued on 3/2/2023.
Response posted 03/03/2023




Inquiry #43: Bid Item No. 0057, Slurry Seal, indicates a bid quantity of 21 tons, and the Summary of Quantities (Q-1) indicates 20.6 tons. After further review of the Typical Cross Sections (X-1), it appears we are applying slurry seal to the outside and inside shoulders. Using the stationing from X-1 with the average widths of the outside and inside shoulders shown on the x-section plans, the quantity of Slurry Seal will be approximately 1,000 tons. We request Caltrans for more information regarding this over-run in quantity. Please advise.
Inquiry submitted 02/27/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 02/27/2023


Response #2:Please refer to addendum No.5 issued on 3/2/2023.
Response posted 03/03/2023




Inquiry #44: Per Layout Sheet L-20, L-21 and L-22 calls for a type 15A Layout, which consists of a Median Crash Cushion, if the intent is to use Median Cushions please provide separate bid item quantity for this scope.
Inquiry submitted 02/28/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 03/01/2023


Response #2:Please refer to addendum No.5 issued on 3/2/2023.
Response posted 03/03/2023




Inquiry #45: After review of Addendum #5, we are still showing a significant difference in the Hot Mix Asphalt Type A quantity. In reference to the Summary of Quantity Tables it looks like the discrepancy stems from the volume of HMA-A that is being accounted for Pavement Structure Section 4 – 0.25’ HMA-A on the ramp shoulders. We believe it is this quantity that is significantly undervalued in the quantity of summary table thus making the bid item quantity much lower than what we believe will be reflected on the project according to what is proposed in the layout plans.
Inquiry submitted 03/03/2023

Response #1:Please bid per contract documents.
Response posted 03/03/2023




Inquiry #46: How is the contractor compensated for the HMA material needed to construct the Maintenance Vehicle Pullouts and where is this material accounted for in the quantities? It appears that the Department may have overlooked this work in the Summary of Quantities sheets. Please advise.
Inquiry submitted 03/03/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 03/03/2023


Response #2:Bid on quantities shown on contract documents.
Response posted 03/06/2023




Inquiry #47: The department has indicated that material excavated with the DPPIAs, Rock Slope Protection, and Maintenance Vehicle Pullouts will be considered ADL. However, the sum of these three items is greater than the ADL item. The DPPIA quantity alone is greater than the ADL item. Please confirm that the quantity for item 30 ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD) is correct.
Inquiry submitted 03/03/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 03/03/2023


Response #2:For ADL, Bid on quantities shown on contract plans.
Response posted 03/06/2023




Inquiry #48: If the material excavated with the Maintenance Vehicle Pullouts is considered ADL as indicated in response 2 to inquiry 8, then please explain what the 597 CY of Roadway Excavation shown on summary of quantities sheet Q-1 is used for. Shouldn't this quantity be removed if it is being paid for under another item?
Inquiry submitted 03/03/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 03/03/2023


Response #2:597 CY of Roadway excavation is for excavation to be done for vegetation control (minor concrete).
Response posted 03/06/2023


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.