Viewing inquiries for 07-357304

Submit new inquiry for this project


Inquiry #1: The Temporary Railing (Type K) Quantities on page 147 of the Plans do not seem to match the linear footage of what is shown on the Traffic Handling Plan Pages. Please advise.
Inquiry submitted 11/30/2022

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 12/02/2022


Response #2:Please refer to addendum No.1 issued on 12/30/2022.
Response posted 01/04/2023




Inquiry #2: The summary of quantities states there should be 270' and 240' of 60MF. However, when takeoffs are preformed, this amount is hugely overstated. Please confirm these quantites are correct for bid item 83 - 60MF.
Inquiry submitted 12/12/2022

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 12/13/2022


Response #2:Please refer to addendum No.1 issued on 12/30/2022.
Response posted 01/04/2023




Inquiry #3: Plan sheet L-6 at station 414+02.61 has concrete barrier type 60R. There is no bid item for this barrier. Please advise.
Inquiry submitted 12/12/2022

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 12/13/2022


Response #2:Concrete Barrier Type 60R has been changed to Type 60MF on plan sheet L-6. Please refer to addendum No.1 issued on 12/30/2022.
Response posted 01/04/2023




Inquiry #4: The majority of the asphalt overlay work is not constructable in the #2 and #3 lanes as the traffic charts do not allow for a buffer lane. Please provide updated traffic charts to allow for 1 through traffic lane in order to accommodate for paving in the #2 and #3 lanes with a buffer lane between the paving operations and the traveled way. If updated traffic charts will not be provided, please describe how the contractor is to safely pave the #2 and #3 lanes. Page 110 of the Special Provisions ONLY allows us to work in a lane adjacent to traffic for grinding, grooving, saw cutting, and installing loop detectors.
Inquiry submitted 01/03/2023

Response #1:Please refer to standard plans H4 for further information and the installation.
Response posted 01/03/2023


Response #2:Lane Closure Charts have been updated. Addendum No. 3 was issued on January 09, 2023.
Response posted 01/09/2023




Inquiry #5: With this project bidding in approximately one week, will Caltrans be addressing any of the 4 unanswered bidder inquiries?
Inquiry submitted 01/03/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/04/2023


Response #2:Answers to Q#1, Q#2, Q#3, Q#4 have been addressed.
Response posted 01/09/2023




Inquiry #6: Please provide an applicable standard specification or special provision for item 390025 SEGMENT CORRECTION. Revised Standard Specifications Section 39-2.10C(3)(e)(i) "applies to existing asphalt concrete surfaces". Summary of quantities sheets Q-4 and Q-5 indicate segment corrections in areas where there is no existing asphalt concrete, only pcc pavement.
Inquiry submitted 01/06/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/06/2023


Response #2:Addendum No. 5 was issued on January 18, 2023.
Response posted 01/20/2023




Inquiry #7: Construction Details sheet C-21 shows an architectural surface treatment specific to "Concrete Barrier Type 60G (Mod)", yet this concrete barrier type is not used on this project.

Is architectural surface treatment required on all type 60 barrier? If so, could the department provide a detail for the various barrier types (60M, 60MC, 60MF, 60MG, and the transitions)?

Inquiry submitted 01/06/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/06/2023


Response #2:Addendum No. 5 was issued on January 18, 2023.
Response posted 01/20/2023




Inquiry #8: Regarding the response to inquiry #4: Standard Plan H4 is for sprinkler riser installation and has nothing to do with asphalt paving or lane closure restrictions. Please review the question and answer.
Inquiry submitted 01/08/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/09/2023


Response #2:Addendum No. 3 was issued on January 9, 2023
Response posted 01/20/2023




Inquiry #9: Construction Details sheet C-17 shows a detail for tapering into existing pavement at structure approaches. The material type is shown as HMA (Type A). Please confirm that this is correct. Typically, the material type matches the the top lift of the 0.25' overlay that we are tying in to, meaning the material type would be RHMA-GG.
Inquiry submitted 01/08/2023

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 01/09/2023


Response #2:Addendum No. 5 was issued on January 18, 2023.
Response posted 01/20/2023


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.