Inquiry #1: The standard specifications for the polyester concrete overlay cure is 4 hours. Many times this is modified in the special provisions to allow for a 2 hour cure, as the material can cure out that fast, and is allowed by the manufacture. This project doesn't have the modified 2 hour cure for the polyester concrete overlay. Given the allowable lane closures are only 8 hours on this project, if a 2 hour cure was allowed it would allow for the project to be expedited lessening the impact to the traveling public. Will the department allow for a 2 hour cure for the polyester overlay?
Inquiry submitted 04/17/2024

Response #1:Please bid per the current contract bid documents.
Response posted 04/19/2024




Inquiry #2: Given the closure charts in the Special Provisions for the mainline locations (Charts G1 & G2) there is no way to pave the middle lanes, as there is 4 lanes on the roadway, and 2 must be kept open during the 8 hour closure. To pave the middle lanes, 3 lanes will need to be taken during a closure, given the current closure charts this is not constructible. Will the state update the charts to allow for a 3rd lane to be taken to allow for the overlays to be constructible?
Inquiry submitted 04/17/2024

Response #1:Please bid per current contract documents.
Response posted 04/23/2024


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.