Inquiry #1: per Monitoring Table in Special Provisions 14-06.03A this project requires daily monitoring. However, Special Provisions 14-06.03D(1) Item 1 specifies weekly monitoring; which is correct?
Inquiry submitted 04/30/2024

Response #1:Please bid per current contract documents.
Response posted 04/30/2024


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.