Bidder Inquiries
Caltrans Bidding Connect Account:
Sign In (Sign in is required to access Project Plans)
Create Account (Click here to create a Caltrans Bidding Connect Account)
Viewing inquiries for 08-1N7404
Submit new inquiry for this projectInquiry #1: per Monitoring Table in Special Provisions 14-06.03A this project requires daily monitoring. However, Special Provisions 14-06.03D(1) Item 1 specifies weekly monitoring; which is correct?
Inquiry submitted 04/30/2024
Response #1:Please bid per current contract documents.
Response posted 04/30/2024
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.