Submit new inquiry for this projectInquiry #1: There does not appear to be a K-Rail item for the installation of the barrier transition on the EB off-ramp. Will Caltrans allow us to leave our forms adjacent to traffic prior to pouring the concrete barrier?
Inquiry submitted 04/22/2024
Response #1:Your inquiry has been submitted for review.
Response posted 04/23/2024
Response #2:A closure chart (J3) is included in special provision page #36 that indicates all three project ramps will be completely closed for 55 hour for each ramp utilizing Type III Barricade and detour plans (MI-1, 2 & 3) to facilitate construction. No K-rail is necessary.
Response posted 04/23/2024
Inquiry #2: The plans do not show the use of krail for the installation of barrier on the EB off-ramp. How do we protect our work when the road is open to traffic?
Inquiry submitted 04/23/2024
Response #1:Your inquiry has been submitted for review.
Response posted 04/23/2024
Response #2:A closure chart (J3) is included in special provision page #36 that indicates all three project ramps will be completely closed for 55 hour for each ramp utilizing Type III Barricade and detour plans (MI-1, 2 & 3) to facilitate construction. No K-rail is necessary.
Response posted 04/23/2024
Inquiry #3: Are there liquidated damages associated with this project? I have not found any in the specifications provided.
Inquiry submitted 04/30/2024
Response #1:Your inquiry has been submitted for review.
Response posted 04/30/2024
Response #2:Please refer to Standard Specification Section 8-1.10 for liquidated damages for this contract.
Response posted 05/01/2024
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.