Viewing inquiries for 11-2N0204

Submit new inquiry for this project


Inquiry #1: the bid book for this files is not on Bid Express. When will it be available?
Error
Could not find active letting '11-2N0204'

Inquiry submitted 04/02/2024

Response #1:The Bid book is available on Bid Express.
Response posted 04/30/2024




Inquiry #2: Section 7.2 of the Tribal Employment Rights Ordinance (TERO) of the La Jolla Band of Luiseno Indians states that a 4% TERO fee of the gross contract amount is required. In the Memorandum of Understanding (MOU) between Caltrans and the La Jolla Band of Luiseno Indians, Section 5 TERO FEE states that Caltrans will pay a TERO fee of 4.0%. Will the contractor be required to pay a 4.0% TERO fee in addition to the 4.0% TERO fee that Caltrans is paying?
Inquiry submitted 04/29/2024

Response #1:The inquiry has been received and submitted for consideration.
Response posted 04/30/2024


Response #2:Please bid per contract documents.
Response posted 04/30/2024




Inquiry #3: In the Memorandum of Understanding (MOU) between Caltrans and the Pala Band of Mission Indians, Section 5 TERO FEE states that Caltrans will pay a TERO fee of 2%. Will the contractor be required to pay a 2% TERO fee in addition to the 2% TERO fee that Caltrans is paying?
Inquiry submitted 04/29/2024

Response #1:The inquiry has been received and submitted for consideration.
Response posted 04/30/2024


Response #2:Please bid per contract documents.
Response posted 04/30/2024




Inquiry #4: There is 235,000 LF of Temporary Traffic Stripe and no bid item. Section 12-6.04 of the 2023 Standard Spec states that "Temporary traffic stripe is measured as specified for traffic stripe in section 84". Please provide a Temporary Traffic Stripe bid item measured by the LF for this work.
Inquiry submitted 04/29/2024

Response #1:The inquiry has been received and submitted for consideration.
Response posted 04/30/2024


Response #2:Please bid per contract documents.
Response posted 04/30/2024




Inquiry #5: Section 2-1.06B of the Special Provisions lists "3. Water Source Information form" as included in the Information Handout however this document is not included within the Information Handout document. Please provide.
Inquiry submitted 04/30/2024

Response #1:The inquiry has been received and submitted for consideration.
Response posted 04/30/2024


Response #2:Please bid per contract documents.
Response posted 04/30/2024


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.