Inquiry #1: On project sheet No. 349, the CMU sound wall aesthetics call out to use an 8X2X16 "Split-Face" beveled cap on top of an 8x8x16 split-2face Caltrans unit. I was unfamiliar with this sizing so I called Angelus Block Co. and they confirmed that they cannot make a split-2face unit, 2" in height, beveled. They stated that there is not enough material (on the unit) available to withstand the splitting of the unit, w/o severe breakage. Angelus Block noted that they can make an 8x2x16 solid precision cap, no bevel, but it would be 7-5/8" wide over a 8x8x16 Caltrans Split-face unit that is 8" wide, which would leave 3/16" on each side if used.

They also mentioned they can make an 8x4x16 solid unit split-2face w/ a precision top, but it would not be beveled, just flush w/ the 8x8x16 split-2face unit below. Or they could make an 8x4x16 solid precision beveled cap as well, but it would still be 7-5/8" wide.

Angelus Block Co. is available to confirm, if need be, from the their main office in Tuxford, Ca.

Please clarify what type of "available" unit the state would like to use as a cap block w/o having to manufacture custom parts and molds which could easily reach $10,000+ or more.

Thanks.

Inquiry submitted 06/25/2024

Response #1:Bid as is.
Response posted 07/08/2024




Inquiry #2: On project plan sheet No. 349, the CMU aesthetics legend at the top, call out to use a 8x2x16 split-face beveled cap.

Angelus Block Co. does not manufacture any type of split-face sided beveled cap that is 2" in height. The next closest they can produce that is beveled would be a 8x4x16 precision solid cap, which would be 7-5/8" in width. This dimension would not be as wide as a Caltrans 8x8x16 configuration split-face-2sided unit, that is approximately 8" wide.

Angelus Block, can also produce an 8x4x16 Splitface-2sided solid cap, (precision on top), but it will not be beveled.

Please clarify which type of cap and size to use for this project, after reaching out to Angelus Block Co., to confirm availability.

Thanks.

Inquiry submitted 07/01/2024

Response #1:Bid as is.
Response posted 07/08/2024




Inquiry #3: Are the existing CMS500 signs Amber or Color? Are the CMS500 signs going to be only relocated or is district 12 going to also replace these old CMS500 signs to either new CMS500 signs or new CMS800 signs?
Inquiry submitted 07/02/2024

Response #1:Bid as is.
Response posted 07/02/2024




Inquiry #4: Due to an emergency, the estimator for this project was unable to attend the prebid meeting for this project. Our office did not have a representative to fill in due to various personnel being on vacation because of the holiday. We are requesting that the State hold a second prebid meeting to allow for increased participation from prime contractors and subcontractors. If a second prebid meeting is not possible, we are requesting a recording and for the meeting to be changed to non-mandatory, like other Districts and Agencies. Each of these options would help increase DBE participation on the project and the number of prime bidders submitting a bid.
Inquiry submitted 07/11/2024

Response #1:Bid as is.
Response posted 07/12/2024




Inquiry #5: _Please confirm Owner is generator of pre-existing haz mat and will sign all transportation manifests for disposal of pre-existing haz mat.
Inquiry submitted 07/15/2024

Response #1:Bid as is.
Response posted 07/24/2024




Inquiry #6: _Will owner waiver consequential Damages?
Inquiry submitted 07/15/2024

Response #1:Owner waiver of consequential damages will be handled case by case. Bid as is.
Response posted 07/25/2024




Inquiry #7: _Is there a cap on liquidated damages?
Inquiry submitted 07/15/2024

Response #1:Bid as is.
Response posted 07/24/2024




Inquiry #8: _Will owner provide waiver of subrogation?
Inquiry submitted 07/15/2024

Response #1:Bid as is.
Response posted 07/24/2024




Inquiry #9: _Please consider extending the bid due date due to schedule conflicts.
Inquiry submitted 07/15/2024

Response #1:Bid date will not be extended at this time. Bid as is.
Response posted 07/18/2024




Inquiry #10: _Per Plan Sheet X-1, base bond breaker is included in Pavement Structure Section Nos. 1 & 5 between JPCP and LCB, however it is missing from Structure Section Nos. 10 & 11 between JPCP-RSC and LCB-RS. A base bond breaker will be required per Specification. Please add a base bond breaker to Structure Section Nos. 10 & 11 and update Bid Item quantities, as needed.
Inquiry submitted 07/15/2024

Response #1:An addendum will be issued.
Response posted 07/25/2024




Inquiry #11: _Plan Sheets L-1 thru L-3 identify 12" Rumble Strip (Concrete Pavement), however, no bid item can be found for this work. Please add bid item for 12" Rumble Strip (Concrete Pavement).
Inquiry submitted 07/15/2024

Response #1:Bid as is.
Response posted 07/22/2024




Inquiry #12: _Plan Sheets L-3 & L-5 shows Pavement Structure Section No. 2 - Slope Paving (Concrete) between WB-91 and both Lakeview WB On Ramps. Plan Sheet C-34 Slope Paving Typical Section states to "Match Slope", however these are not existing slopes. Please specify the slope for this new Section 2 Slope Paving.
Inquiry submitted 07/15/2024

Response #1:Bid as is.
Response posted 07/24/2024




Inquiry #13: _Plan Sheet L-3 shows Pavement Structure Section No. 2 - Slope Paving (Concrete) between WB-91 and RW No. 13 from approx "LK3" STA 8+79 to 21+55. Plan Sheet C-34 Slope Paving Typical Section states to "Match Slope", however this is not an existing slope. Please specify the slope for this new Section 2 Slope Paving.
Inquiry submitted 07/15/2024

Response #1:Bid as is.
Response posted 07/24/2024




Inquiry #14: _Please specify width of preformed compression isolation joint seal.
Inquiry submitted 07/15/2024

Response #1:Bid as is.
Response posted 07/22/2024




Inquiry #15: _Various staging plans identify the use of temporary pavement, however, no information is provided for the temp pavement section. Please specify the temp pavement section to be located at each of these staging plan callouts.
Inquiry submitted 07/16/2024

Response #1:Note 11 on sheet SC-1 indicates the temporary pavement section.
Response posted 07/25/2024




Inquiry #16: _Construction Notes on Stage 1B, 2 & 3 staging plans state to "construct tie-in during weekend/night closure" and are referring to new sections of JPCP pavement. The Layout Sheets refer to these new pavement sections as JPCP (Structure Sections #1 and #5), which cannot be constructed during a weekend/night closures due to specified cure period requirements. Per Caltrans Specifications, please specify a JPCP-RSC pavement section for these locations identified to be constructed during weekend/night closures, and confirm the revised quantity of JPCP-RSC pavement is to be paid under the applicable pay item for JPCP-RSC.
Inquiry submitted 07/16/2024

Response #1:An addendum will be issued.
Response posted 07/25/2024




Inquiry #17: _Referring to locations of new Section 4 pavement on along Lakeview Ave north and south of the bridge, there appears to be stage construction areas omitted for completing the middle ~1/3rd of the roadway. Stages 1A, 2 & 3 each show staged construction areas for completing the outside portions of roadway but there is no stage that exists for the middle ~1/3rd between these areas. As this pavement section #4 is not simply a mill & overlay that can be completed during nightly closure, and rather a full section pavement, a staged work area with temporary barrier will be required in order to delineate traffic for the prolonged duration of the work. Please provide staged construction plans for completing these areas of work.
Inquiry submitted 07/16/2024

Response #1:An addendum will be issued.
Response posted 07/25/2024




Inquiry #18: As a follow up to bidder inquiry #4, we do not believe it is in the best interest of the taxpayer to prevent contractors from bidding on this contract. Changing the prebid meeting to non-mandatory would encourage more General contractor participation, which in turn leads to more DBE subcontractor participation. As a result, this would increase competition and lower the bid prices. It is in the taxpayer’s best interest to encourage competitive pricing by allowing increased competition. Caltrans, in general, including other agencies Districts and agencies, do not hold mandatory prebid meetings. If they do hold a prebid meeting, it is usually non-mandatory. We ask that the prebid meeting be changed to non-mandatory.
Inquiry submitted 07/16/2024

Response #1:No additional pre-bid meetings will be provided. Bid as is.
Response posted 07/18/2024




Inquiry #19: In response to bidder inquiry #4, we do not feel it is in the best interest of the taxpayer to prevent contractors from bidding on this project. We are requesting that the State change the prebid meeting to non-mandatory. Usually Caltrans (Agencies and Districts) do not hold mandatory prebid meetings. If they do, the prebid meetings are optional. Changing the prebid meeting to non-mandatory would encourage more Prime contractors to participate which in turn, would increase DBE subcontractor participation. Increased participation on this project would result in competitive pricing, which is in the best interest of the taxpayers.
Inquiry submitted 07/17/2024

Response #1:No additional pre-bid meetings will be provided. Bid as is.
Response posted 07/18/2024




Inquiry #20: _Please provide missing WB traffic chart from Lakeview to SR-55 and missing EB traffic chart from Lakeview to Imperial Highway.
Inquiry submitted 07/19/2024

Response #1:Bid as is.
Response posted 07/30/2024




Inquiry #21: _Please provide missing traffic chart for EB-91 connector for paving work shown on C-46.
Inquiry submitted 07/19/2024

Response #1:An addendum will be issued.
Response posted 07/30/2024




Inquiry #22: Retaining Wall No. 199 concrete quantities appear to be understated. Please review and revise.
Item 125, 16" CIDH Piling (Soundwall) quantity appears to be considerably overstated. Please review and revise.
Where are the "He"s for Soundwall No. 191 shown? This information is typically provided.

Inquiry submitted 07/21/2024

Response #1:Bid as is for retaining wall no. 199 and bid item 125.
An addendum will be issued to show the “He”s for SW 191.

Response posted 07/30/2024


Response #2:Correction to previous response, an addendum will be issued for bid item 125.
Response posted 08/07/2024




Inquiry #23: Will a list of Pre-Bid attendees be distributed?
Inquiry submitted 07/22/2024

Response #1:We have a list of companies in attendance of the pre-bid meeting that need to get posted. Per the specifications, they will be made available at the website shown on the Notice to Bidders for bidder inquiries.
Response posted 07/24/2024


Response #2:12-0K91U4 - Mandatory Pre-Bid Meeting Attendees List
July 10, 2024

AYCE Inc.
Beador Construction Company, Inc.
Crescendo Strategies Group
Flatiron West, Inc.
Geostructural Engineering Inc
Granite Construction
Griffin Engineering Management
Guy F Atkinson Construction
J1S & Associates Security Services
MCM Construction, Inc
OHLA-USA
Prime Point Contracting Inc.
Santolucito Dore Group, Inc., DBA SD Group
Sema Construction, Inc.
Skanska USA Civil
Stacy & Witbeck Inc
Steve P. Rados, Inc.
Structural Technologies
Walsh Construction
Response posted 08/01/2024


Response #3:12-0K91U4 - Mandatory Pre-Bid Meeting Attendees List
July 10, 2024

Atkinson Construction
AYCE Inc.
Beador Construction Company, Inc.
Coffman Specialties Inc
Crescendo Strategies Group
Flairon West, Inc.
Geostructural Engineering Inc
Granite Construction
Griffin Engineering Management
Guy F Atkinson Construction
J1S & Associates Security Services
MCM Construction, Inc
OHLA-USA
Prime Point Contracting Inc.
rcrtraffic.com
Santolucito Dore Group, Inc., DBA SD Group
Sema Construction, Inc.
Skanska USA Civil
Stacy & Witbeck Inc
Steve P. Rados, Inc.
Structural Technologies
Walsh Construction
Response posted 08/05/2024




Inquiry #24: Per Notice to Bidders,
"Complete the work, excluding plant establishment work, within 575 working days.
Complete the work, including plant establishment work, within 917 working days.
Complete the plant establishment work within 500 working days. "

Can you confirm Plant Establishment is 500 Working Days, the total working days are not adding up.

Inquiry submitted 07/22/2024

Response #1:Complete the plant establishment work within 500 working days per notice to bidders. Plant establishment can begin prior to completing the work. Bid as is.
Response posted 07/25/2024




Inquiry #25: _Please provide as-built drawings for Lakeview Ave OC and retaining walls. This request has also been made per section 2-1.06B of the Standard Specifications.
Inquiry submitted 07/23/2024

Response #1:Bridge as-builts requests are to be submitted per section 2-1.06B of the Standard Specifications.
Response posted 07/31/2024




Inquiry #26: _Please provide the callouts per the legend found on sheet C-1 (Removal Plan) for the existing Structural Section No. This information is needed for accurate quantities of the underlying materials.
Inquiry submitted 07/23/2024

Response #1:Existing pavement structural sections are identified on the typical cross section plans X-1 to X-19. Bid as is.
Response posted 07/31/2024




Inquiry #27: _Please clarify the removal of base and subbase material is included in BI 0109, 0117, and 0118. Confirm that the hardscape and underlying base and subbase material is not to be included in BI 0043 "Roadway Excavation).
Inquiry submitted 07/23/2024

Response #1:Bid as is. Refer to construction details removal sheets for bid items 109, 117, and 118 which show whether base is included in the pavement removal. All other removals not included in construction details are handled through roadway excavation.
Response posted 08/19/2024




Inquiry #28: _Please provide Typical Cross Sections for "LK" Sta 98+29.58 to "LK" Sta 103+24.17
Inquiry submitted 07/23/2024

Response #1:Refer to the structural plans for the typical cross section on Lakeview Avenue OC Bridge. Bid as is.
Response posted 08/05/2024




Inquiry #29: _The Bid Item List provides BI# 42 Clear and Grub (LS) and BI# 66 Maintain Existing Planted Areas (LS). The plans do not identify areas to Clear and Grub nor plants/trees to be protected in place. There are a number of large trees that require to be removed for the realignment. Please identify the number of trees that need to be removed under a separate Bid Item and identify locations to clear and grub and maintain existing planted areas.
Inquiry submitted 07/23/2024

Response #1:Bid as is.
Response posted 08/05/2024




Inquiry #30: This project bids on the same day as a major Heavy/Highway contractor annual event in Napa. This conflict may result in the project not receiving adequate attention. Please consider moving the bid date to resolve this conflict which will more than likely increase bidder participation.
Thank you.

Inquiry submitted 07/24/2024

Response #1:Bid date will not be extended at this time. Bid as is.
Response posted 07/25/2024




Inquiry #31: Please show/account for roadway work (section/replacement limits) for work at Retaining Walls 110 & 110 (Modify). A section is shown on Sheet 340 that does not appear to include the total area to be excavated that would accommodate the footing. The RW 110 (Modify) and Roadway Drawings do not show any roadway section. As the work at RW 110 (Modified) includes subexcavation, additional roadway work (details) will be required.
Inquiry submitted 07/25/2024

Response #1:No scale is provided in section on sheet 340. Bid as is.
Response posted 08/05/2024




Inquiry #32: Please show/account for roadway work (section/replacement limits) for work at Retaining Walls 110 & 110 (Modify). A section is shown on Sheet 340 that does not appear to include the total area to be excavated that would accommodate the footing. The RW 110 (Modify) and Roadway Drawings do not show any roadway section. As the work at RW 110 (Modified) includes subexcavation, additional roadway work (details) will be required.
Inquiry submitted 07/25/2024

Response #1:No scale is provided in section on sheet 340. Bid as is.
Response posted 08/05/2024




Inquiry #33: Please confirm quantity for BI 125, 16" CIDH Concrete Piling (Sound Wall). Plans for SW 191 do not account for the full BI quantity, however soundwall quantity sheet (Q-5) shows all 16" CIDH quantity on SW 191.

Inquiry submitted 07/25/2024

Response #1:Bid as is.
Response posted 08/05/2024




Inquiry #34: Please confirm retaining walls coming off Lakeview Ave OC (replace) bridge abutment 3 will be paid under bid item 130, structural concrete, bridge. Please confirm the quantity shown on plan sheet 701 out of 817 for BI 130 includes the retaining wall quantities coming off of abutment 3. "

Inquiry submitted 07/25/2024

Response #1:The retaining wall concrete at Abutment 3 of the Lakeview Ave OC is paid for as Structural Concrete, Bridge and Structural Concrete, Bridge Footing as shown in the Concrete Strength and Type Limits diagram on sheet 701 of 817. Bid as is.
Response posted 08/05/2024




Inquiry #35: Please confirm ALL Concrete Barrier callouts/ quantities as there are many mistakes.

Construction details do not all line up correctly with the callouts. i.e showing MS in CD when calling for M on Layouts.

MD and MD Mod callouts contradict each other between structure plans and layouts.

Confirm that it was the states intent to include all the 60 MG barrier within the 60MGF pay item as they are very different in price.

Inquiry submitted 07/25/2024

Response #1:An addendum will be issued to remove 60 MD as it is duplicated with item 60 MD Mod. An addendum will be issued to separate CB 60MG and CB 60MGF quantities into two bid items. Bid as is for the remainder of inquiry.
Response posted 08/19/2024




Inquiry #36: Can the Plant Establishment period begin prior to the completion of the planting?
Inquiry submitted 07/26/2024

Response #1:Bid as is.
Response posted 08/19/2024




Inquiry #37: Please confirm receipt of questions made about Soundwall CIDH quantity and He of Type 836SV barrier made on July 21 and respond.
Inquiry submitted 07/29/2024

Response #1:A bidder inquiry regarding Soundwall CIDH quantity and He of Type 836SV barrier was not received on July 21. Please submit the inquiry.
Response posted 07/31/2024




Inquiry #38: In reference to Inquiry #23, the Notice to Bidders does not indicate a website to visit in order to obtain a copy of the Pre-Bid Meeting attendees list. Please provide.
Inquiry submitted 07/30/2024

Response #1:12-0K91U4 - Mandatory Pre-Bid Meeting Attendees List
July 10, 2024

Atkinson Construction
AYCE Inc.
Beador Construction Company, Inc.
Coffman Specialties Inc
Crescendo Strategies Group
Flairon West, Inc.
Geostructural Engineering Inc
Granite Construction
Griffin Engineering Management
Guy F Atkinson Construction
J1S & Associates Security Services
MCM Construction, Inc
OHLA-USA
Prime Point Contracting Inc.
rcrtraffic.com
Santolucito Dore Group, Inc., DBA SD Group
Sema Construction, Inc.
Skanska USA Civil
Stacy & Witbeck Inc
Steve P. Rados, Inc.
Structural Technologies
Walsh Construction
Response posted 08/05/2024




Inquiry #39: In Lane Closure Chart M1, please clarify the "N-No work allowed" designation. If Remark 1 calls out that this chart is applicable for bridge demolition, and erection and removal of falsework, what chart applies to other work (shoring, excavation, pile driving, bridge foundation, backfill)?
Inquiry submitted 07/31/2024

Response #1:Bid as is. See remainder of closure charts for work not in chart M1.
Response posted 08/19/2024




Inquiry #40: Please provide Mandatory sign-in sheet.
Inquiry submitted 07/31/2024

Response #1:12-0K91U4 - Mandatory Pre-Bid Meeting Attendees List
July 10, 2024

Atkinson Construction
AYCE Inc.
Beador Construction Company, Inc.
Coffman Specialties Inc
Crescendo Strategies Group
Flairon West, Inc.
Geostructural Engineering Inc
Granite Construction
Griffin Engineering Management
Guy F Atkinson Construction
J1S & Associates Security Services
MCM Construction, Inc
OHLA-USA
Prime Point Contracting Inc.
rcrtraffic.com
Santolucito Dore Group, Inc., DBA SD Group
Sema Construction, Inc.
Skanska USA Civil
Stacy & Witbeck Inc
Steve P. Rados, Inc.
Structural Technologies
Walsh Construction
Response posted 08/05/2024




Inquiry #41: Besides providing openings and coordinating, is the contractor required to furnish/install/provide traffic control for any of the work associated with the 6-4" diameter Communications Conduits shown on the Lakeview Ave OC Structure Plans?
Inquiry submitted 07/31/2024

Response #1:Bid as is.

Contractor to furnish and install (AT&T, Crown, and Extenet) associated with 6 - 4" diameter communication conduits as shown on plans.
Response posted 08/19/2024




Inquiry #42: Besides providing openings and coordinating, is the contractor required to furnish/install/provide traffic control for any of the work associated with the 6-4" diameter Communications Conduits shown on the Lakeview Ave OC Structure Plans?
Inquiry submitted 07/31/2024

Response #1:Bid as is.

Contractor to furnish and install (AT&T, Crown, and Extenet) associated with 6 - 4" diameter communication conduits as shown on plans.
Response posted 08/19/2024




Inquiry #43: _Layout Sheets L-2 and L-3 calls out TCE limits from C-LINE Sta 188+72 +/- to Sta 199+50 +/- . There is currently a chain link fence between the TCE line and the new retaining wall/ sound wall LOL lines that will need to be removed for construction. Please consider adding the additional quantity to bid item 212 Remove Chain Link Fence
Inquiry submitted 08/01/2024

Response #1:An addendum will be issued to revise bid item 212 quantity.
Response posted 08/19/2024




Inquiry #44: Bid item 125 quantities are not adding up. There has been 2 inquiries and they have not been answered. There are Case 1 & Case 2 sections which change the CIDH Pile cage designs and it is unclear how many cages of each design is needed to add up to the Bid Item quantity.

Bid Item 138 has a quantity of 61 CY but there are only a total of 41.5 shown on the quantity pages. Where are the remaining 19.5 CY?

Inquiry submitted 08/03/2024

Response #1:An addendum will be issued to update CIDH pile quantity.

Bid item 138 includes the 19.5 CY minor concrete shown on structure plan sheet 814 of 817.
Response posted 08/19/2024




Inquiry #45: Please confirm quantities of 60MD and 60MD Mod. These quantities are not matching up to the bid item quantities. 824' of wall is called out on the Layouts as 60MD, but in the structure plans they are called out as 60MD Mod and counted as duplicates in the quantities. Please revise barrier quantities, and confirm that only 190' of the 60MD Mod requires the water pattern architectural treatment.
Inquiry submitted 08/05/2024

Response #1:An addendum will be issued to remove 60 MD as it is duplicated with item 60 MD Mod.

The 60MD Mod on RW 110 has a water pattern architectural treatment. See sheet 79 of 817 for the details.
Response posted 08/19/2024




Inquiry #46: Where is the thickness of the Polyester Concrete shown?
Inquiry submitted 08/05/2024

Response #1:An addendum will be issued.
Response posted 08/19/2024


Response #2:Correction to the previous response, an addendum will not be issued for this bidder inquiry, bid as is.
Response posted 08/28/2024




Inquiry #47: Inquiry # 32 and #34 are requesting clarity for the BI quantities as the plans do not add up to this quantity. There are 2 cases used which changes the design of the CIDH Rebar cages. It is not possible to declare the quantity of each design with the information provided.
Bid Item 138 shows a grand total of 41.5 CY on sheet 314 (Q9) of the contract drawings. Where are the other 19.5 CY located?

Inquiry submitted 08/06/2024

Response #1:An addendum will be issued to update CIDH pile quantity.

Bid item 138 includes the 19.5 CY minor concrete shown on structure plan sheet 814 of 817.

Response posted 08/19/2024




Inquiry #48: What Rebar is intended to be paid for in Item 154?
Inquiry submitted 08/06/2024

Response #1:See sound wall no. 193 on plan sheet 814 for bid item 154.
Response posted 08/21/2024




Inquiry #49: _Section 51.-1.04 of the Special Provisions states, "The payment quantity for concrete surface texture (fractured rib) does not include the area of concrete surface texture (fractured rib) on the concrete barrier and mechanically stabilized embankment facing panels." It appears the Owners quantity for Bid Item 0139 - Concrete Surface Texture (Fractured Rib), only accounts for Lakeview Ave OC and Lakeview Ave/SB Rte 55 On- Ramp. Please update Owners quantities to account for the retaining walls.
Inquiry submitted 08/06/2024

Response #1:Bid as is.
Response posted 08/21/2024




Inquiry #50: _Concrete Barriers callouts along "D" per drawing No. L-5 starting from station "D-110+93.79" to "D-120+61.41", in order of SW to NE include a)Transition section b)60MG c)60MGF d)60MG and e)Transition. However, there is no bid item for Barrier Type "60MG" and per plan Q-4, it appears that this item's quantity as well as two transition sections (mentioned above) are included in total quantity of 60MGF line item for L-4/L-5 (1,032.60 LF). Please clarify if new bid item for Barrier 60MG will be added. Also provide revised plan No. Q-4 with correct quantity for Type 60MG, 60MGF AND BARRIER TRANSITION.
Inquiry submitted 08/06/2024

Response #1:An addendum will be issued to add CB 60MG.
Response posted 08/21/2024




Inquiry #51: _Concrete Barriers in L-3 & L-5 as listed in Q-4, along with C- 204+18 to C-208+70.83 and LK-3 17+20.11 to C 214+25.36 are Type "60 MD". However, in Retaining wall plans these 2 barriers are identified as "60 MD Modified" including 340 LF along RW-12 starting approx. at LK3-17+20 and in RW-13, 472 LF starting approx. C-204+18. It appears call-outs for these 2 location on L-3 & L-4 are 60 MD where in retaining wall plans are listed as "60 MD Modified" at the same location. Please confirm what type barrier to be installed alongside Lower side of retaining walls. Also confirm the table for 60MD & 60 MD Modified in Q-4 are accurate or provide list and location for these types.
Inquiry submitted 08/06/2024

Response #1:An addendum will be issued to remove the duplicate quantities (60MD).
Response posted 08/21/2024




Inquiry #52: _Please clarify the height for Junction Structure #6 at Drainage System 22i. Profile sheets reflect a 10.88' structure however, quantity sheets call for 13' of 36" precast concrete pipe manhole.
Inquiry submitted 08/06/2024

Response #1:An addendum will be issued to update the quantity. Structure height is 5.5’ per standard plans.
Response posted 08/21/2024




Inquiry #53: _Plan sheet 814 of 817 calls out the Owner's quantity for Bid Item 0154 - (F) - Bar Reinforcing Steel (Sound Wall). Please identify the bid item that will be used for payment for the remaining reinforcing steel in CMU sound walls 183, 191, and 199.
Inquiry submitted 08/06/2024

Response #1:Bid as is. Bid item 154 is applicable to sound wall no. 193. All other sound walls will follow the standard bid items as shown on the Caltrans standard plan.
Response posted 08/21/2024




Inquiry #54: _Typical cross sections X-3 (pg 4 of 817) and X-4 (pg 5 of 817) call out "REMOVE SW/RW" in various locations. The "REMOVE RETAINING WALL" quantity on plan sheet Q-5 (pg 310 of 817) does not accurately reflect the removal limits on plan sheets X-3 and X-4. Likewise, the "Construction Details (Removal Plan)" sheets are missing the retaining wall removal limits. Please update the "REMOVE RETAINING WALL" quantity and the corresponding plans to clarify the limits of retaining wall removal (LF).
Inquiry submitted 08/06/2024

Response #1:An addendum will be issued.
Response posted 08/21/2024




Inquiry #55: Per sheet ISS-1, please provide pipe sizing chart for the Pop Up Sprinkler Assembly labeled 'C-1'
Inquiry submitted 08/06/2024

Response #1:Bid as is.
Response posted 08/22/2024




Inquiry #56: Reference Bidder Inquiry #15. Various staging plans identify the use of temporary pavement, however, no information is provided for the temp pavement section. Please specify the temp pavement section to be located at each of these staging plan callouts.

Under what bid item is the temporary AB and HMA paid? Under what bid item is the removal of the temporary AB and HMA paid?

Inquiry submitted 08/06/2024

Response #1:The temporary pavement section is specified on sheet SC-1 in note 11. The quantity for this item is listed on sheet SCQ-2 and is included in the Summary of Quantities on sheet Q-2.
Response posted 08/22/2024




Inquiry #57: Please provide a bid item for what appears to be a new master valve located at POC A on sheet IP-1.
Inquiry submitted 08/06/2024

Response #1:An addendum will be issued.
Response posted 08/22/2024




Inquiry #58: Please confirm backflow preventer size. Bid item shows it as 2" but POC A note on IP-1 shows it as 3".
Inquiry submitted 08/06/2024

Response #1:An addendum will be issued.
Response posted 08/22/2024




Inquiry #59: During the review of the project schedule. The construction duration seems extremely short and will likely result in a large number of liquidated damages.

Please advise

Inquiry submitted 08/06/2024

Response #1:Bid as is.
Response posted 08/22/2024




Inquiry #60: 60MD and 60MD Mod quantities appear to be duplicated. Layout sheet will callout for 60MD, while the structure plans show MD mod in those same locations. Please confirm only 190' of the MD mod (RW 110 Modify) gets architectural treatment.

Please review and revise concrete barrier quantities to not count duplicates.

Inquiry submitted 08/06/2024

Response #1:An addendum will be issued to remove 60 MD as it is duplicated with item 60 MD Mod.

The 60MD Mod on RW 110 has a water pattern architectural treatment. See sheet 79 of 817 for the details..

Response posted 08/22/2024




Inquiry #61: On Sheet IP-4, new mainline is drawn with the same symbol as existing mainline. Please clarify which areas are to receive new mainline.
Inquiry submitted 08/06/2024

Response #1:An addendum will be issued.
Response posted 08/22/2024




Inquiry #62: Bid item 80 is for Riser Sprinkler Assembly which is not shown on the plans and legend. Please identify where these are on the drawings.
Inquiry submitted 08/06/2024

Response #1:An addendum will be issued.
Response posted 08/22/2024




Inquiry #63: Please differentiate between the Concrete Surface Texture (Bay Relief) and Architectural Treatment (Veneer). If the Veneer item is intended to pay for the Water Pattern (Sheet 79) on the Type 60 Barrier then the quantity should be reduced to 666 SF. The additional quantity shown for Retaining Wall No. 110 (Sheet 310) should be accounted for in the Bay Relief item if it is intended to be similar to the pattern shown on the Retaining Wall No. 110 (Modify) Sheets.
Inquiry submitted 08/07/2024

Response #1:Bay Relief is part of the structural items, details and quantities are shown on the structure plan. Veneer have water pattern shown on sheet 79, details and quantities are shown on the roadway plan.
Response posted 08/22/2024




Inquiry #64: _Please provide clarification on the design requirements/criteria for junction structure #2 called out for drainage system 14i. Based on the provided criteria, the structure quantities greatly exceed the allotted quantities identified on the drainage quantity sheets.
Inquiry submitted 08/07/2024

Response #1:Bid as is.
Response posted 08/25/2024




Inquiry #65: _Please confirm the new Section 10 and Section 11 JPCP-RSC is to be isolated from the existing adjacent pavement.
Inquiry submitted 08/07/2024

Response #1:Bid as is.
Response posted 08/28/2024




Inquiry #66: On Sheet IQ-1 it is shown through the quantities table that there is 30 LF of 2" Copper Pipe on IP-2. This is not shown on sheet IP-2. Please provide location of copper pipe.
Inquiry submitted 08/07/2024

Response #1:An addendum will be issued.
Response posted 08/22/2024




Inquiry #67: Besides the quantity of Soil Amendment required as part of plantings for the various plant groups shown, the plans fail to indicate where and to what depth Soil Amendment is to be placed. Thea table-provided quantities suggest that the greater quantity of Amendment is to be cultivated and not considered part of each plant pit. Please indicate the depth of soil amendment to be placed and identify locations where soil amendment is to be placed.
Inquiry submitted 08/08/2024

Response #1:An addendum will be issued.
Response posted 08/22/2024




Inquiry #68: Please provide rates of application for Soil Amendment and Iron Sulfate for each plant type as part of planting sequence. Similarly, provide rate of application and specific location where Iron Sulfate is to be applied as part of the chart information for Planting Area Quantities.
Inquiry submitted 08/08/2024

Response #1:An addendum will be issued.
Response posted 08/22/2024




Inquiry #69: The bid form provides for Weed Germination and Cultivation (Bid Items #0056 and #0057) respectively. Based on the total planted areas identified on the drawings, total landscaped areas measure approximately 250,000 square feet. Confirm the unit of measurement stated on the bid form is to be square footage and not square yards as this is a large discrepancy and should be rectified.
Inquiry submitted 08/08/2024

Response #1:An addendum will be issued.
Response posted 08/22/2024




Inquiry #70: Please provide a detail and depth required for Class II aggregate base where shown on the planting plans; quantities merely provide total quantity required at locations identified for this treatment.
Inquiry submitted 08/08/2024

Response #1:An addendum will be issued.
Response posted 08/22/2024




Inquiry #71: The responses provided to several questions reference that an addendum will be issued. Please confirm when the addendum will be issued. This project bids in one week and Bidders need adequate time to review the addendum.
Inquiry submitted 08/08/2024

Response #1:Addendum #1 extending the bid opening has been posted. Addendum #2 is forthcoming to address bid inquiries as applicable. Follow up responses will be posted to applicable bidder inquiries to refer to the addendum number addressing the changes.
Response posted 08/09/2024




Inquiry #72: The special provisions require two applications of slow-release fertilizer within the plant establishment period but no rates of application or bid item is provided. Confirm Slow Release fertilizer will be required as part of this contract and provide rates of application and where this will be paid for.
Inquiry submitted 08/08/2024

Response #1:An addendum will be issued.
Response posted 08/22/2024




Inquiry #73: Please provide a line item for Control & Neutral conductors or advise where this will be paid for.
Inquiry submitted 08/08/2024

Response #1:An addendum will be issued.
Response posted 08/23/2024




Inquiry #74: Irrigation mainline is not identified by size on the drawings; confirm the entirety of irrigation mainline shown on the drawings is to be 3" size.
Inquiry submitted 08/08/2024

Response #1:An addendum will be issued.
Response posted 08/23/2024




Inquiry #75: Confirm the entirety of (2,590) cubic yards of mulch are to be applied within planted areas and existing areas to be maintained as noted on the drawings. Advise if the stated 4" depth of mulch for existing areas applies to all if this is correct. Separately, advise if all wood mulch to be applied is to be Shredded Wood Mulch.
Inquiry submitted 08/08/2024

Response #1:Bid as is.

The 2,590 includes the area of existing trees at a 4” depth. Per note 2 on the Plant Legend Sheet, all mulch is to be shredded wood mulch.

Response posted 08/23/2024




Inquiry #76: Please confirm if Weed Germination & Cultivation quantities are correct on PQ-2. Converting the Square Yards to Square Feet far exceeds amount of takeoff shown on those sheets.
Inquiry submitted 08/08/2024

Response #1:An addendum will be issued.
Response posted 08/23/2024




Inquiry #77: Please indicate on the plans which areas "Maintain existed planted areas" apply to.
Inquiry submitted 08/08/2024

Response #1:Bid as is. Call outs on planting sheets point to the existing vegetation clouds.
Response posted 08/25/2024




Inquiry #78: On Sheet E-68 where the new 334LS cabinet is going to be installed detector loops are shown; but on the ED-18 drawing an input file is not shown in the cabinet layout. I am not referring to where the old cabinet is going to be removed, and the Loops abandoned – AB.
Will these (2) cabinets require a input file?

Inquiry submitted 08/09/2024

Response #1:Pending
Response posted 08/29/2024


Response #2:Bid as is.
Response posted 09/04/2024




Inquiry #79: Bid item #076 requires the installation of a new 2" irrigation backflow preventer which corresponds to the Main - Supply Side of Control Valve chart provided on Sheet IQ-1, the chart refers to a new backflow however, IP-2 does not have an irrigation point of connection. Sheet IP-1 does show an existing backflow preventer at POC A. Advise if a new backflow will be required for this contract as it does not appear to be required due to fact that the entire irrigation system is being fed from this existing point of connection "A" on IP-1.
Inquiry submitted 08/09/2024

Response #1:An addendum will be issued.
Response posted 08/25/2024




Inquiry #80: Irrigation Sheet IP-1 indicates a symbol for a new flow sensor and what appears to be a master control valve but there are not callouts for both of these. Similar to the backflow preventer in question previously addressed, quantities in the Main - Supply Side of Control Valve chart seem to be incorrectly stated by sheet number. Confirm quantities stated should reflect items shown at POC (point of connection) "A" on Sheet IP-1 of the irrigation plans.
Inquiry submitted 08/09/2024

Response #1:An addendum will be issued.
Response posted 08/25/2024




Inquiry #81: Please define the symbol for the solid triangular symbol that appears in front of manifolded control valve assemblies. This symbol does not correlate to irrigation ball valves and there are no callouts defining these assemblies. Furthermore the quantity of ball valves stated on the chart provided on Sheet IQ-1 does not correspond to those shown on the drawings. Advise what this symbol is and reconcile quantities on chart and bid form.
Inquiry submitted 08/09/2024

Response #1:An addendum will be issued.
Response posted 08/25/2024




Inquiry #82: Refer to irrigation sheet IP-3 where irrigation conduit north of (LK Line) 8" Sch. 40 (42 LF). There is another location south of (LK Line) where a conduit is required but no callout provided. Please specify size of conduit and length to be installed.
Inquiry submitted 08/09/2024

Response #1:An addendum will be issued.
Response posted 08/25/2024




Inquiry #83: Refer to Sheet IQ-2 chart for irrigation conduit. 57' lineal feet of conduit at the LK-1 Line are not shown on the IP-2 sheet. Please provide callout and identify location of this conduit.
Inquiry submitted 08/09/2024

Response #1:An addendum will be issued.
Response posted 08/25/2024




Inquiry #84: 1. Refer to Sprinkler Schedule on Sheet ISS-1. Please specify the 'Swing Joint Type" required for installation of the Tree Well Sprinkler Assemblies.

2. Refer to Sprinkler Schedule on Sheet ISS-1. Bid form item #080 requires the installation of (39) Riser Sprinkler Assemblies, these however are not indicated on the Sprinkler Schedule nor are they shown on the plans. Please advise if these are required and provide relevant information for bidding purposes or delete from the bid form.

Inquiry submitted 08/09/2024

Response #1:1. Bid as is. Tree well assembly details are shown in the standard plans.
2. An addendum will be issued.

Response posted 08/25/2024




Inquiry #85: Refer to IP-2 & IP-4, there are two (2) existing irrigation controllers ICC-E and IC-A that are to be relocated. Please indicate which bid item this scope of work is to be allocated or provide new bid item accounting for all required scope to fulfill relocation of existing irrigation controllers.
Inquiry submitted 08/09/2024

Response #1:An addendum will be issued.
Response posted 08/25/2024




Inquiry #86: Retaining Wall No. 199 concrete quantities appear to be understated. Please review and revise.
Item 125, 16" CIDH Piling (Soundwall) quantity appears to be considerably overstated. Please review and revise.
Where are the "He"s for Soundwall No. 191 shown? This information is typically provided.

Inquiry submitted 08/18/2024

Response #1:Bid as is for retaining wall no. 199.
An addendum will be issued for bid item 125 and to show the “He”s for SW 191.

Response posted 08/25/2024




Inquiry #87: On many plan sheets, I'll use sheet 192. Along the "LK-4" Line, in the Eastbound onramp to Rte 91, under the Construction Noter #4, there is a rectangle/manmade object? This object may be some drainage system? Does it remain? and stay in operation during the construction?
Inquiry submitted 08/20/2024

Response #1:Bid as is. Manmade object is shown on D-4, plan sheet 115. It is existing to remain.
Response posted 08/25/2024




Inquiry #88: As a follow up to the response to Inquiries 41 & 42, the plans and specifications indicate the utility companies will perform the work to relocate the 6- 4” conduits on the Lakeview OC. Furthermore, there is no detail for the contractor to define the scope of the work. Please confirm that all work concerning the furnish, installation, relocation of the 6 – 4” conduits including any supports and appurtenances is the responsibility of the utility companies. Should you wish to add this to the Contractor’s scope, please provide in sufficient detail the plans, specs, and payment methods to add this work to the contract.
Inquiry submitted 08/22/2024

Response #1:Bid as is.
Response posted 09/16/2024




Inquiry #89: As a follow up to the response to Inquiries 41 & 42, the plans and specifications indicate the utility companies will perform the work to relocate the 6- 4” conduits on the Lakeview OC. Furthermore, there is no detail for the contractor to define the scope of the work. Please confirm that all work concerning the furnish, installation and relocation of the 6 – 4” conduits including any supports and appurtenances is the responsibility of the utility companies. Should you wish to add this to the Contractor’s scope, please provide in sufficient detail the plans, specs and payment methods to add this work to the contract.
Inquiry submitted 09/11/2024

Response #1:Bid as is.
Response posted 09/16/2024




Inquiry #90: _Given that the bid is next week on the 19th, when will addendum 2 be issued?
Inquiry submitted 09/11/2024

Response #1:Bid as is.
Response posted 09/16/2024




Inquiry #91: 1. Specifications Page 141 We do not have a HSG#3 (housing) that meets this spec. The spec calls for a locking generator bypass compartment located in the FRONT DOOR. The only one we have is not located on the door but on the top weld rear opposite the police door. Would this be acceptable?

2. Specifications Item 13. Page 140 We have never supplied a power panel like this in a Anaheim 333L cabinet. We would need to know the amperage of the (5) circuit breakers.

3. Specifications Page 141 Terminal 343 through 346 of the Load Bay. Seems to be a NEMA reference not a 333”L” cabinet?


Inquiry submitted 09/11/2024

Response #1:Bid as is.
Response posted 09/19/2024




Inquiry #92: In reference to the 525 working days for substantial completion, we are requesting the owner to analyze the schedule again. There is insufficient time to complete the work as stipulated.

Based on a previous response, having the plant establishment use up construction working days will make the timeline worse. The job does not have enough room for work to be expedited during the weekends or recovery time.

Inquiry submitted 09/11/2024

Response #1:Bid as is
Response posted 09/16/2024




Inquiry #93: Addendum 1 advised bidders that an addendum would be issued with additional changes. In addition, the responses provided to several bidder inquiries references that an addendum will be issued. This project bids in one week, please confirm when the addendum will be issued. Bidders and subcontractors, including DBEs, need adequate time to review the addendum.
Inquiry submitted 09/12/2024

Response #1:Bid as is.
Response posted 09/16/2024




Inquiry #94: For all stage construction temporary detour striping, the plans are calling for temporary traffic stripe paint, however each stage also has contrast stripe thermoplastic alongside the temporary paint. Is that a mistake, the contrast stripe should be paint as well, just like the temporary paint stripe. It makes no sense to have painted temporary stripes with contrast striping in thermoplastic, especially for temporary detour striping.
Inquiry submitted 09/12/2024

Response #1:Addendum will be issued.
Response posted 09/16/2024




Inquiry #95: _Please identify the bid item for payment of the reinforcing steel in sounds walls 191, 183, and 199.
Inquiry submitted 09/16/2024

Response #1:Bid as is.
Response posted 09/19/2024




Inquiry #96: _For the subcontractor listing entry can items that are in sequential order and are the same percentages, but less than 100%, i.e. 98%, be listed in sequential order with the percentage and a description?

example:
1 | 98% | Items 1-10 - Landscape (partial) and related

Inquiry submitted 09/19/2024

Response #1:Bid as is.
Response posted 09/23/2024




Inquiry #97: Addendum #3 was issued October 4, 2024; will the State consider pushing the bid due date back a week to evaluate the changes and re-engage our subcontractors and vendors?
Inquiry submitted 10/07/2024

Response #1:Bid as is.
Response posted 10/08/2024




Inquiry #98: The Lane Closure Charts (H4/H5) only specify full closures of the Express Lanes. In order to complete the work in the designated allowable working days can (1) lane in each direction of the Express lanes be closed Monday - Friday? None of the charts currently allow this.
Inquiry submitted 10/07/2024

Response #1:Bid as is.
Response posted 10/14/2024




Inquiry #99: _Addendum #3 adds specifications for Vibration Monitoring, Crack monitoring, Photo and Video Site Documentation of Existing Non-highway Facilities. These three additions consists of extensive work that was not part of the original bid documents. This new addendum does not provide a method of payment. Please provide a payment method for this added "Vibration Monitoring," "Crack Monitoring," and "Photo and Video Site Documentation of Existing Non-highway Facilities."
Inquiry submitted 10/07/2024

Response #1:Bid as is.
Response posted 10/14/2024




Inquiry #100: With the latest addendum, can Caltrans push the bid due date back a week to evaluate the changes and re-engage the subcontractors and vendors?
Inquiry submitted 10/08/2024

Response #1:Bid as is.
Response posted 10/08/2024




Inquiry #101: Per addendum 3 plan sheet 348 of 817 is revised to include additional pile data on the elevation drawing. The additional data on sheet 348 calls out S =5' max , 4' max, and 3'-3" max for different parts of the wall. The new added data contradicts the various different spacing call outs on the same drawing. The new data indicates closer spacing than the original plan shows therefore adding pile length while the pile LF quantity decreased per addendum 3. Per addendum 3, BI 125 is revised from 2440 LF to 1690 LF. Please confirm the revised plan sheet and BI quantity match. Please confirm which call outs on plan sheet 348 are correct.

Inquiry submitted 10/08/2024

Response #1:Addendum will be issued.
Response posted 10/10/2024




Inquiry #102: Sheet 344 (R3-6) shows the water pattern surface texture to be placed at RW 110. Cross section G-G is missing from the plan set. Please provide the cross sectional detail and depth of water pattern texture.

Inquiry submitted 10/09/2024

Response #1:Bid as is.
Response posted 10/10/2024




Inquiry #103: Regarding section 12-402C(3)(b) the Complete Freeway Closure Hour Charts H1 - H5 for the bridge demolition. The closure time allowed to demolish the bridge span is insufficient. Will this be revised?
Inquiry submitted 10/11/2024

Response #1:Bid as is.
Response posted 10/16/2024




Inquiry #104: Per addendum 3, Typical Cross Sections X-1 was revised to include two new pavement structural sections 16 and 17. The sections indicate the top pavement layer as JPCP-RSC while the base layer as conventional LCB. Please revise typical section to show base layer as LCB RS and revise quantity for BI 102 LCB RS.

Inquiry submitted 10/14/2024

Response #1:Bid as is.
Response posted 10/16/2024




Inquiry #105: In order to construct the center median foundation work. The 91 express lanes will need to be closed nightly during the week. Please confirm traffic chart G1 can be used to close the 91 express lanes.

Inquiry submitted 10/14/2024

Response #1:Bid as is.
Response posted 10/16/2024




Inquiry #106: Refer to Section 86-1.02AD(1). The quote referenced in expired. Please provide assurances that this materails can be purchased as noted in the special provisions during the project duration.
Inquiry submitted 10/14/2024

Response #1:Bid as is.
Response posted 10/16/2024




Inquiry #107: Please confirm that the Contractor will not be charged for closing the express lanes.
Inquiry submitted 10/15/2024

Response #1:Bid as is.
Response posted 10/16/2024


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.