Submit new inquiry for this projectInquiry #1: On Sheet L-19 at Sta 251+00 and 252+00 there is conflicting call out information for the westbound lanes and shoulder. Please clarify if the intent is to place RHMA and fog seal over the top, or if the callout arrows are incorrect.
Inquiry submitted 10/14/2024
Response #1:Addendum will be issued
Response posted 10/23/2024
Inquiry #2: On Sheet L-21 at station 269+50 there is conflicting call out information for the eastbound lanes and shoulder. Please clarify if the intent is to place RHMA and fog seal over the top, or if the callout arrows are incorrect.
Inquiry submitted 10/14/2024
Response #1:Addendum will be issued
Response posted 10/23/2024
Inquiry #3: Can other alternative pipeliners that conform to DIB 83-4 per section 71-3-09 specifically AASHTO M326 be used in place of CIPP? These liners have many advantages including environment as well as can be installed in live flow without the need for by-passing.
Inquiry submitted 10/14/2024
Response #1:Bid as is
Response posted 10/30/2024
Inquiry #4: Retaining Wall No.2, Foundation Plan No.1 and No. 2 (Sheets 3 of 16 and 4 of 16) show the plan of the wall footing solid colored in black, some bottom of footing elevations are blacked out and grade contours are covered up. Can you issue revised drawings that clearly show the footing, bottom of footing elevations and grade contours for retaining wall no. 2?
Inquiry submitted 10/15/2024
Response #1:Addendum will be issued
Response posted 10/24/2024
Inquiry #5: Please provide Electronic file of existing TOPO and/or grading sheets with existing TOPO to quantity Roadway Excavation and Structure Excavation.
Inquiry submitted 10/18/2024
Response #1:Will include in addendum
Response posted 10/30/2024
Response #2:Bid as is
Response posted 12/03/2024
Inquiry #6: Hello,
Will this project have a Project labor Agreement? also is there a list of Project labor Agreement jobs in Southern CA? or Federal projects that will be PLA,s?
Inquiry submitted 10/19/2024
Response #1:Bid as is
Response posted 10/22/2024
Inquiry #7: Reference RW #2, Stage Construction Plan Sheet SC-5(Sheet 189), Caltrans Standard Specifications-Section 19-6.03D, and Contract Special Provisions Section 19-6.03D: The Contractor is to place a 12' high surcharge for RW #2 from Sta 11+26 to Sta 14+34 during Stage 2 Construction. Per Caltrans Standard Specifications the top width of the surcharge is 30' from the face of the wall. Most of the wall has less than 30' of distance from the face of the wall to the temporary K-rail, making it impossible to obtain a 30' wide surcharge. Even constructing a temporary wire wall(hillfiker wall) adjacent to the K-rail the surcharge would only be 25'+/-. The state either must allow a surcharge of less than 30' wide or close the ramp entirely to obtain 30' width for the settlement period of 180 days. Please provide an acceptable surcharge width or the ability to close the ramp.
Inquiry submitted 10/22/2024
Response #1:addendum will be issued
Response posted 11/18/2024
Inquiry #8: How long is the full ramp closure allowed for Stage 3 of the Orangethorpe offramp re-construction?
Inquiry submitted 10/22/2024
Response #1:Bid as is
Response posted 10/30/2024
Response #2:Bid as is
Response posted 12/03/2024
Inquiry #9: On Sheet L-19 at Sta 251+00 and 252+00 there is conflicting call out information for the westbound lanes and shoulder. Please clarify if the intent is to place RHMA and fog seal over the top, or if the callout arrows are incorrect.
Inquiry submitted 10/22/2024
Response #1:Addendum will be issued
Response posted 10/30/2024
Inquiry #10: On Sheet L-21 at station 269+50 there is conflicting call out information for the eastbound lanes and shoulder. Please clarify if the intent is to place RHMA and fog seal over the top, or if the callout arrows are incorrect.
Inquiry submitted 10/22/2024
Response #1:Addendum will be issued
Response posted 10/30/2024
Inquiry #11: Retaining Wall No.2, Foundation Plan No.1 and No. 2 (Sheets 3 of 16 and 4 of 16) show the plan of the wall footing solid colored in black, some bottom of footing elevations are blacked out and grade contours are covered up. Can you issue revised drawings that clearly show the footing, bottom of footing elevations and grade contours for retaining wall no. 2?
Inquiry submitted 10/22/2024
Response #1:Addendum will be issued
Response posted 10/24/2024
Inquiry #12: Between Sheet 3 and 4 of the Wall 2 Plan the CB line and contours do not line up. Please clarify the relevant contours and alignment.
Inquiry submitted 10/22/2024
Response #1:Bid as is
Response posted 10/24/2024
Inquiry #13: There appears to be a discrepancy on the number of working days and plant establishment. Please revise.
Complete the work, excluding plant establishment work, within 600 working days.
Complete the work, including plant establishment work, within 660 working days.
Complete the plant establishment work within 120 working days.
Inquiry submitted 10/24/2024
Response #1:There is 60 days of Overlap Working days.
Response posted 10/24/2024
Response #2:Bid as is
Response posted 10/24/2024
Inquiry #14: Please confirm the states intent for the erosion tongues for the 60MS Barrier.
Sheet No. 97 is very unclear and shows HMA for the erosion tongue. Please Clarify.
Inquiry submitted 10/24/2024
Response #1:Addendum will be issued
Response posted 11/18/2024
Inquiry #15: 1) Is it the states intent for the Concrete Barrier footings/ erosion tongue to be HMA and not poured monolithically with the barrier?
2) Page 120 (C-73) Section B-B has Note HMA Type A See Sheet C-59, on Sheet C-59 does not have information pertaining to HMA, Please Advise?
Inquiry submitted 10/25/2024
Response #1:Addendum will be issued
Response posted 11/18/2024
Inquiry #16: Provide the As-built thickness of the existing approach slabs shown on drawing General Plan No 2, Sht 2 of 3 (Sht 555 of 556).
Inquiry submitted 10/25/2024
Response #1:Bid as is
Response posted 11/18/2024
Inquiry #17: Please provide cross section details that represents the limits of the settlement embankment pile required at retaining wall no 2. Also indicate what bid item includes covers payment.
Inquiry submitted 10/25/2024
Response #1:Addendum will be issued
Response posted 11/18/2024
Inquiry #18: Please provide Original Grade Contours in the area around retaining wall no 2.
Inquiry submitted 10/25/2024
Response #1:Will provide with addendum
Response posted 10/30/2024
Inquiry #19: For bid line item 151, "Furnish Laminated Panel Sign (2 5/8" Type B)", there is no such thing as a 2-5/8" Type B sign panel. Should this line item be added to the 2 1/2" Type B line item?
Inquiry submitted 11/06/2024
Response #1:Addendum will be issued
Response posted 12/03/2024
Inquiry #20: I CANNOT LOCATE THE SPECS AGAINST LINE ITEM 0151, CODE 017094, FURNISH LAMINATED PANEL SIGN (2 5/8" TYPE B). IS THIS ENTERED IN ERROR? SHOULD IT BE 2-1/2" TYPE B OR TYPE H?
Inquiry submitted 11/14/2024
Response #1:Addendum will be issued
Response posted 12/03/2024
Inquiry #21: Reference RW #2, Stage Construction Plan Sheet SC-5(Sheet 189), Caltrans Standard Specifications-Section 19-6.03D, and Contract Special Provisions Section 19-6.03D: The Contractor is to place a 12' high surcharge for RW #2 from Sta 11+26 to Sta 14+34 during Stage 2 Construction. Per Caltrans Standard Specifications the top width of the surcharge is 30' from the face of the wall. Most of the wall has less than 30' of distance from the face of the wall to the temporary K-rail, making it impossible to obtain a 30' wide surcharge. Even constructing a temporary wire wall(hillfiker wall) adjacent to the K-rail the surcharge would only be 25'+/-. The state either must allow a surcharge of less than 30' wide or close the ramp entirely to obtain 30' width for the settlement period of 180 days. Please provide an acceptable surcharge width or the ability to close the ramp.
Inquiry submitted 11/19/2024
Response #1:Bid as is
Response posted 12/03/2024
Inquiry #22: In reference to JPCP RSC - structural section 7. In some instances we are paving the new 2/3 lane against existing JPCP outside lanes, for example at L-20/21 Layout sheets Sta 262+79 to 269+83. The typical sections detail us to install an isolation joint next to the existing PCC inside lanes, however no detail was provided for the longitudinal joint next to the existing JPCP outside lanes. Please confirm if it is the intent to drill and bond tie bars to the existing JPCP or if we are to install 1/4" flexible foam as detailed per section 40-5.03B of the project special provisions .
Inquiry submitted 11/19/2024
Response #1:Bid as is
Response posted 12/03/2024
Inquiry #23: "Please provide a closure chart or MI Plan for the following locations: • WB91 to Valley View Offramp closure and detour routes,. Need a Motorist Information Plan
• WB91to NB5 Connector, need a closure chart or MI Plan
• NB5 to WB91 Connector, need a closure chart or MI Plan
• SB5 to EB91 Connector, need a closure chart or MI Plan
"
Inquiry submitted 11/19/2024
Response #1:Addendum will be issued
Response posted 12/03/2024
Inquiry #24: For the JPCP RSC Random Locations, the lane lines do not match the panel joint layout. This will require closing down at least 3 lanes to do the repairs. This will require shifting all traffic into the HOV lanes for much of the closures. Will the HOV lanes be accepted as the through lane for all traffic during nightly closures?
Inquiry submitted 11/20/2024
Response #1:Bid as is
Response posted 12/03/2024
Inquiry #25: In what stage of the Orangethorpe ramp closure is the sign foundation intended to be built?
Inquiry submitted 11/20/2024
Response #1:Bid as is
Response posted 12/03/2024
Inquiry #26: Bid Line Item #151 Furnish Laminated Panel Sign (2-5/8" Type B) seems to be an error as there is not a 2-5/8" Type B LAM Panel Sign. It should be either 1" Type B or 2-1/2" Type B. Please advise.
Inquiry submitted 11/26/2024
Response #1:Addendum will be issued
Response posted 11/26/2024
Inquiry #27: Addendum 2 revised the quantity for Bid Item 73 to 1,960 tons this is overstated because the Quantity on Q5 is added twice on Q9 and Q10. Please Advise.
Inquiry submitted 11/26/2024
Response #1:Bid as is
Response posted 11/26/2024
Inquiry #28: Will Caltrans please extend the bid date until after the holidays? Reaching out to our vendors and subcontractors has been problematic due the recent addendum issued 11/26.
Inquiry submitted 12/02/2024
Response #1:Addendum was issued. New Bid Opening Date is 12/18/24.
Response posted 12/12/2024
Inquiry #29: In reference to JPCP RSC - structural section 7. In some instances we are paving the new 2/3 lane against existing JPCP outside lanes, for example at L-20/21 Layout sheets Sta 262+79 to 269+83. The typical sections detail us to install an isolation joint next to the existing PCC inside lanes, however no detail was provided for the longitudinal joint next to the existing JPCP outside lanes. Please confirm if it is the intent to drill and bond tie bars to the existing JPCP or if we are to install 1/4" flexible foam as detailed per section 40-5.03B of the project special provisions .
Inquiry submitted 12/02/2024
Response #1:Bid as is
Response posted 12/03/2024
Inquiry #30: Please provide a closure chart or MI Plan for the following locations: • WB91 to Valley View Offramp closure and detour routes,. Need a Motorist Information Plan
• WB91to NB5 Connector, need a closure chart or MI Plan
• NB5 to WB91 Connector, need a closure chart or MI Plan
• SB5 to EB91 Connector, need a closure chart or MI Plan
Inquiry submitted 12/02/2024
Response #1:Addendum will be issued
Response posted 12/03/2024
Inquiry #31: The Settlement Embankment width is 15' each side of the retaining wall LOL. This width will cause the embankment to encroach into the off- ramp at STA 11+26 and 14+34 and will cross over the Right of Way line at station 12+67 to 14+34. Is the intent to provide shoring along ROW to prevent the embankment from encroaching onto the adjacent properties?
Inquiry submitted 12/03/2024
Response #1:Bid as is
Response posted 12/04/2024
Inquiry #32: Staged construction drawings do not show retaining wall No 1. In which stage is Retaining Wall No 1 to be constructed?
Inquiry submitted 12/03/2024
Response #1:Bid as is
Response posted 12/12/2024
Inquiry #33: On sheet DP-4, the profile for drainage system 15, specifically for the 24” RCP, is missing. Could you please provide the profile drawings for this system along the eastbound shoulder at station 165+50?
Inquiry submitted 12/03/2024
Response #1:Bid as is
Response posted 12/16/2024
Inquiry #34: Reinforcement details needed for MS Mod section. C-73
Please confirm this is to be paid under 60MS Bid Item, or if another Item will become available.
Inquiry submitted 12/04/2024
Response #1:Bid as is. Please refer to Construction Details, C-26 and C-45; Bid Item #178 "(F) - CONCRETE BARRIER TRANSITION
Response posted 12/04/2024
Inquiry #35: There are multiple areas on the plans that call for exposed aggregate concrete. However, there are multiple locations with existing architectural hardscape in place. Is the intent to remove and replace or will those areas be eliminated?
Inquiry submitted 12/04/2024
Response #1:Bid as is.
Install Exposed Aggregate Concrete where there is no existing hardscape.
Response posted 12/12/2024
Inquiry #36: REFER TO PLAN SHEET 389. PLEASE CONFIRM THE CONDUIT INSTALLATION METHOD BETWEEN STATION 140+00 AND 140+40 ON E/B RTE 91.
Inquiry submitted 12/05/2024
Response #1:Bid as is
Response posted 12/12/2024
Inquiry #37: For the installation of Bid Item #124 Exposed Aggregate Concrete, there is an area on the shoulder of the Off-Ramp West Bound S. Harbor Blvd that has an existing rock blanket where new work is planned. How will the removal of the existing rock blanket be paid?
Inquiry submitted 12/06/2024
Response #1:Bid as is.
Install Exposed Aggregate Concrete where there is no existing hardscape.
Response posted 12/12/2024
Inquiry #38: Bid Item #124: The exposed aggregate concrete detailed on page LD-1. Underneath the exposed aggregate concrete is an 8” Class 2 aggregate base. Where will payment for this Class 2 aggregate base be paid? Additionally, where will the excavation for this bid item be covered for the Class 2 aggregate base section.
Inquiry submitted 12/06/2024
Response #1: Bid as is.
The 8” Class 2 AB and excavation are included and paid out of the minor concrete per the specification.
Response posted 12/12/2024
Inquiry #39: REFER TO NOTE 2 ON PLAN SHEET 421 (TYPICAL ON APPLICABLE SHEETS FOR THIS WORK). PLEASE CONFIRM THE DETAILS REFERENCED ARE THE CORRECT AND ONLY ONES FOR THE WORK. THERE SEEMS TO BE SOME DETAILS MISSING FOR THIS WORK REGARDLESS.
Inquiry submitted 12/06/2024
Response #1:Bid as is
Response posted 12/12/2024
Inquiry #40: REFER TO PLAN SHEET 454. CONFIRM IF RUN #1 REQUIRES NEW CABLE OR NOT.
Inquiry submitted 12/06/2024
Response #1:Bid as is
Response posted 12/12/2024
Response #2:Bid as is
Response posted 12/12/2024
Inquiry #41: Please Provide the current smoothness data for the roadway.
Inquiry submitted 12/09/2024
Response #1:Bid as is.
It is included in the bid package. Supplemental Project Information
Response posted 12/12/2024
Inquiry #42: Will a variance be granted for smoothness due to the roughness of the current roadway?
Inquiry submitted 12/09/2024
Response #1:Bid as is.
the Project Special Provisions address the pavement smoothness requirement for each application specified on the Project Plans.
For JPCP-RSC Random, smoothness is only subject to the 12-foot straightedge
Response posted 12/12/2024
Inquiry #43: Please confirm that Concrete Barrier from stations "ORA-1" 10+54.17 to "ORA-1" 13+07.37 and "ORA-1" 10+54.17 to "A" 26+84.31 is NOT within a Corrosive Environment.
Confirm that only concrete directly involved with RW #2 is considered Corrosive Environment.
Inquiry submitted 12/10/2024
Response #1:Bid as is
Response posted 12/16/2024
Inquiry #44: Addendum 2 Plan sheets Q-7 through Q-9 call out HMA paving at MBGR locations, Please provide details with dimensions and depths for this work.
Please adjust Item 73 to reflect the correct tonnage for this project, since the 873 tons on Q-5 is added twice on Q-9 and Q-10.
Inquiry submitted 12/11/2024
Response #1:Bid as is.
Please follow Sheet C-25, structural section 9, 50' clear recovery area in front of the Crash Cushion
Response posted 12/16/2024
Inquiry #45: Will Caltrans consider extending the bid date until after the Holidays and into the beginning of the new year?
Inquiry submitted 12/16/2024
Response #1:Bid as is
Response posted 12/16/2024
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.